J. Brodie & Son, Inc. v. George A. Fuller Co.

167 N.W.2d 886, 16 Mich. App. 137, 1969 Mich. App. LEXIS 1325
CourtMichigan Court of Appeals
DecidedFebruary 25, 1969
DocketDocket 5,572, 5,579
StatusPublished
Cited by22 cases

This text of 167 N.W.2d 886 (J. Brodie & Son, Inc. v. George A. Fuller Co.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. Brodie & Son, Inc. v. George A. Fuller Co., 167 N.W.2d 886, 16 Mich. App. 137, 1969 Mich. App. LEXIS 1325 (Mich. Ct. App. 1969).

Opinion

Bronson, J.

On or about May 3,1963, defendants, First Federal Savings and Loan Association of Detroit (“First Federal”) and George A. Fuller Company (“Fuller”) entered into a contract covering the *139 major portion of work to be performed in the construction of the First Federal Building located at 1001 Woodward Avenue, Detroit, Michigan. First Federal was the owner and Fuller was the general contractor. Each plaintiff as a subcontractor entered into a separate subcontract with Fuller for portions of the work covered by the general contract. The “General Conditions” set forth in the contract between Fuller and First Federal provided for arbitration of disputes under rules of the American Arbitration Association. The subcontracts between the plaintiffs and Fuller also provided for arbitration of disputes. On or about October 28, 1965, plaintiffs each filed demands for arbitration of claims asserted against Fuller which collectively totaled approximately $550,000. On or about November 26,1965, Fuller filed a claim against First Federal and a demand for arbitration in the amount of $1,835,143.69. Thereafter, Fuller filed “An Outline of Additional Compensation Requested in Claim Dated November 26,1965”, showing, among other things, the following:

Total Fuller claim, $1,206,220.88

Total subcontractor’s claim, 486,959.22

Total Fuller and subcontractor’s claim,

$1,693,180.10

On or about November 26, 1965, First Federal filed a demand for arbitration of its claim against Fuller in the total amount of $1,794,562.17, subsequently amended so as to be in the amount of $1,417,976.88. The claims asserted by First Federal and the claims asserted by Fuller, including those asserted by Fuller based upon claims of the plaintiffs (subcontractors), arise in part out of the undisputed delay that occurred in the progress and completion of the project. There is no privity of contract be *140 tween the plaintiffs (subcontractors) and First Federal (owner). Three arbitrators have been selected by Fuller and First Federal and they have consented to act. The plaintiffs have stated their willingness to accept these arbitrators in their arbitration proceedings with Fuller.

On March 18, 1968, plaintiffs-appellees (subcontractors) filed a complaint and motion in the Wayne county circuit court praying that an order be entered requiring the consolidation of the arbitration proceedings between plaintiffs (subcontractors) and Fuller (general contractor) with the arbitration proceedings between Fuller and First Federal. No other relief is requested. The matter was presented to the trial court on pleadings, briefs and arguments of counsel. The sole issue presented to the trial court was whether arbitration proceedings of the subcontractors with Fuller should be consolidated with the arbitration proceedings between Fuller and First Federal. The trial judge said yes, and from that order of consolidation First Federal and Fuller appeal.

Under Michigan special proceedings, arbitrations are governed by GrCR 1963, 769, which states in part:

“.2 Proceedings to Compel or Stay Arbitration.
“(1) On application of a party showing an agreement to arbitrate which conforms to the arbitration statute, and the opposing party’s refusal to arbitrate, the court shall order the parties to proceed with arbitration, and to take such other steps essential to carry into effect the arbitration agreement and the arbitration statute, but if the opposing party denies the existence of the agreement to arbitrate, the court shall proceed summarily to the determination of the issue so raised and shall order arbitration if found for the moving party, otherwise the application shall be denied.
*141 “(2) On application, the court may stay an arbitration proceeding commenced or threatened on a showing that there is no agreement to arbitrate. Such an issue, when in substantial and bona fide dispute, shall be forthwith and summarily tried and the stay ordered if found for the moving party. If found for the opposing party, the court shall order the parties to proceed to arbitration.”

To fall within the scope of GrCE 1963, 769, there must be an agreement to arbitrate between the principals. In the present case we can find no such agreement between plaintiffs, and defendant First Federal.

While recognizing this lack of contractual agreement between plaintiffs and defendant First Federal, plaintiffs contend that consolidation does not affect such rights. Eather, plaintiffs feel that although there is no privity of contract there is a great degree of identity of issues involved in the dispute between Fuller and First Federal, and between plaintiffs and Fuller. They point out that the contract between Fuller and First Federal contemplates a third party and even provides for the presence of the subcontractor in any proceedings involving their rights. Plaintiffs correctly recognize that to disallow consolidation would, to a great degree, create a duplication of arbitration.

While recognizing that the proposed consolidation by the learned trial judge represents the more efficient solution, this Court must reverse.

According to 17 Am Jur 2d, § 242, the following rules are expressed:

- “It is a fundamental principle that a court may not make a new contract for the parties or rewrite their contract under the guise of construction. * * * It must be construed and enforced according to the terms emplpyed, and a court has no right to interpret the agreement as meaning something *142 different from what the parties intended as expressed by the language they saw fit to employ. -* *

The plain intent of the parties in the instant ease, as gathered from a reconstruction of the unambiguous language of these separate contracts, is clear. In case of trouble between Fuller and First Federal, the differences were to be submitted to arbitration. In the second contract, if contractual differences existed between Fuller and the subcontractors, these troubles were to be arbitrated.

This is the only logical construction of the terms of these contracts as written. Nowhere, in either contract, is there any indication that troubles are to be arbitrated together or as part of a single action. Here neither Fuller nor First Federal has consented to be joined in a combined arbitration of differences under the separate contracts.

According to CLS 1961, § 600.5001 (Stat Ann § 27A.5001), arbitration is a matter of contract:

“(2) A provision in a written contract to settle by arbitration under this chapter, a controversy thereafter arising between the parties to the contract, with relation thereto * * * . Such an agreement shall stand as a submission to arbitration of any controversy arising under said contract not expressly exempt from arbitration by the terms of the contract. * * *”

G-CR 1963, 505.1, relevant to consolidation, provides :

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ure v. Wangler Const. Co., Inc.
597 N.E.2d 759 (Appellate Court of Illinois, 1992)
Barclay Townhouse Associates v. Stephen L. Messersmith, Inc.
508 A.2d 507 (Court of Special Appeals of Maryland, 1986)
Bay County Building Authority v. Spence Bros.
362 N.W.2d 739 (Michigan Court of Appeals, 1984)
Pueblo of Laguna v. Cillessen & Son, Inc.
682 P.2d 197 (New Mexico Supreme Court, 1984)
Arrow Overall Supply Company v. Peloquin Enterprises
323 N.W.2d 1 (Michigan Supreme Court, 1982)
Keating v. Superior Court
645 P.2d 1192 (California Supreme Court, 1982)
Litton Bionetics, Inc. v. Glen Construction Co.
437 A.2d 208 (Court of Appeals of Maryland, 1981)
W. J. Megin, Inc. v. State
434 A.2d 306 (Supreme Court of Connecticut, 1980)
S. K. Barnes, Inc. v. Valiquette
597 P.2d 941 (Court of Appeals of Washington, 1979)
La. Stadium & Exposition Dist. v. Huber, Hunt & Nichols, Inc.
349 So. 2d 491 (Louisiana Court of Appeal, 1977)
Polshek v. Bergen Cty. Iron Works
362 A.2d 63 (New Jersey Superior Court App Division, 1976)
Stop & Shop Companies, Inc. v. Gilbane Building Co.
304 N.E.2d 429 (Massachusetts Supreme Judicial Court, 1973)
Grover-Dimond Associates, Inc. v. American Arbitration Ass'n
211 N.W.2d 787 (Supreme Court of Minnesota, 1973)
Wm. C. Blanchard Co. v. Beach Concrete Co.
297 A.2d 587 (New Jersey Superior Court App Division, 1972)
George A. Fuller Co. v. Shelby Fireproofing, Inc.
171 N.W.2d 589 (Michigan Court of Appeals, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
167 N.W.2d 886, 16 Mich. App. 137, 1969 Mich. App. LEXIS 1325, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-brodie-son-inc-v-george-a-fuller-co-michctapp-1969.