Autotrol Corporation v. Continental Water Systems Corporation and Olin Corporation

918 F.2d 689, 1990 U.S. App. LEXIS 20376, 1990 WL 178547
CourtCourt of Appeals for the Seventh Circuit
DecidedNovember 19, 1990
Docket90-1038
StatusPublished
Cited by19 cases

This text of 918 F.2d 689 (Autotrol Corporation v. Continental Water Systems Corporation and Olin Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Autotrol Corporation v. Continental Water Systems Corporation and Olin Corporation, 918 F.2d 689, 1990 U.S. App. LEXIS 20376, 1990 WL 178547 (7th Cir. 1990).

Opinion

POSNER, Circuit Judge.

This is a diversity suit, primarily for breach of contract. The suit was tried to a jury, and the plaintiff, Autotrol Corporation, obtained a judgment of more than $1.5 million. The appeal raises a large number of issues, only a handful of which require discussion. So far as the remaining issues are concerned, it is enough to note that the district judge resolved most of them in a thoroughly satisfactory manner and that the others could not possibly have affected the outcome of the trial.

The contract provides that any dispute under it shall be resolved in accordance with the law of Texas. Neither party questions the validity of this choice-of-law stipulation but it is rather academic because there are no Texas cases on the hotly contested issues.

The contract, signed in May 1986, established a joint venture between Autotrol’s controls division and Continental Water Systems Corporation to create a system for water purification based on a patented new technology, known as “electrodiarese,” that Continental owned the exclusive right to exploit. Autotrol was to manufacture the control for the system and Continental the rest and both companies would sell the completed systems — Autotrol the large systems, Continental the small ones. There was an ambiguity, later to prove critical, about the dividing line between large and small.

Before production could begin, there had to be product specifications. These had not been completed when the contract was signed. Anticipating this possibility, the contract provided that when approved by both parties the specifications would be attached to, and thereby made a part of, the contract; and should the parties be “unable, in good faith, to agree upon the contents of the Products Specifications Schedule by June 30, 1986, either party *691 hereto may elect to terminate this Agreement.” On June 25 the parties agreed to extend this deadline to July 17. July 17 came and went and the product specifications had not been agreed upon but neither party exercised its right of termination. It was almost a year later, with the product specifications still not having been agreed upon, that Continental declared the contract terminated. That is the alleged breach. Meanwhile the other defendant, Olin Corporation, had acquired all the stock of Continental, and according to evidence that the jury reasonably could credit had decided that unless Autotrol acceded to the defendants’ understanding of what the smallest system was that Autotrol was entitled to sell — which Autotrol refused to do — Autotrol would be encroaching on the segment of the market that Olin wanted to reserve for Continental.

The defendants argue that they were free to terminate the contract at any time after July 17, for any reason or no reason, without liability, provided only that the product specifications had not been finally agreed upon and attached to the contract as a schedule. Yet Continental encouraged Autotrol to continue working, which meant continue spending, on Autotrol’s share of the project for many months after July 17 — indeed, right up to the notice of termination — even though the product specifications had not been agreed upon. Autotrol does not argue that this encouragement was sufficiently promissory in form to support liability under a theory of promissory estoppel, on which see Restatement (Second) of Contracts § 89(c) and comment d (1981). But it does argue that, in conjunction with Autotrol’s parallel forbearance to exercise its right of termination, Continental’s encouragement supports an inference that the parties had modified the contract to waive Continental’s right to terminate after July 17 for failure to agree on product specifications. This is assuming Continental had such a right, which Autotrol denies, thus giving it two grounds upon which to argue that there was a breach of contract. The jury found a breach but was not asked to indicate the ground, so we must affirm if either ground is supportable; as a matter of fact both are.

Under either of Autotrol’s theories, once July 17 came and went Continental could not terminate the contract without liability — ever—even if the parties never did work out product specifications. At first acquaintance the argument is implausible. The parties could not go into production without such specifications. If they reached impasse after bargaining in good faith, would not either party be entitled to walk away from the contract without liability? Apparently not. The contract is deliberately asymmetrical with respect to termination after July 17 (June 30 in the original contract, before the date was extended). Until then either party can walk if the product specifications have not been agreed upon. After that Autotrol can walk until production commences but “Continental shall have no right to terminate this Agreement except as provided in” certain paragraphs of the contract that relate to specific (and immaterial) changed circumstances, such as bankruptcy, but not to failure to work out product specifications. Not only by encouraging Autotrol to continue working after July 17, but in the contract itself, Continental seems to have surrendered the right it would otherwise have had to terminate the contract upon the failure of an essential condition.

What sense can this make? The answer lies in the asymmetry of the parties’ position. Continental controlled the patent on electrodiarese and if it abandoned the project, say by failing to agree on product specifications, Autotrol would be unable to go forward and would lose its investment. But if Autotrol abandoned the project Continental could always get another partner. Making the contract terminable by Auto-trol but not by Continental gave Autotrol leverage to force Continental to license the patent to Autotrol on reasonable terms if Continental lost interest in the project.

If all this is wrong and Continental somehow retained an implicit right to terminate the contract without liability, even after July 17, provided that the parties were unable to agree upon product *692 specifications, still the jury was entitled to find that the parties had modified the contract to forbid termination on this ground at least until such time as the need to agree on product specifications was urgent and agreement impossible. That deadline had not been reached when the defendants terminated — on a ground, moreover, that had nothing to do with product specifications, but rather with the division of the market for the product. The modification was supported by consideration; both parties benefited from relaxing the deadline, inasmuch as this allowed the project to proceed. United States v. Stump Home Specialties Mfg., Inc., 905 F.2d 1117, 1122 (7th Cir.1990). Though oral, and somewhat vague about the duration of Continental’s commitment, the modification was sufficiently definite to be enforceable, cf. Gold-stick v. ICM Realty, 788 F.2d 456, 462-63 (7th Cir.1986), and an oral modification is enforceable under Texas law even if the contract forbids oral modifications, as this one did. Adams v. Can-Dee Oil Corp., 357 S.W.2d 808 (Tex.Civ.App.1962). The Texas approach, by no means idiosyncratic, 2 Farnsworth on Contracts § 7.6, at pp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Merry Gentleman, LLC v. George & Leona Productions, Inc.
76 F. Supp. 3d 756 (N.D. Illinois, 2014)
Chevron U.S.A., Inc. v. United States
116 Fed. Cl. 202 (Federal Claims, 2014)
Southern Nuclear Operating Co. v. United States
77 Fed. Cl. 396 (Federal Claims, 2007)
Dominion Nutrition, Inc. v. Cesca
467 F. Supp. 2d 870 (N.D. Illinois, 2006)
Energy Capital Corp. v. United States
47 Fed. Cl. 382 (Federal Claims, 2000)
Mercedes Hoffman v. Grossinger Motor Corporation
218 F.3d 680 (Seventh Circuit, 2000)
Rule Sales & Service, Inc. v. U.S. Bank National Ass'n
991 P.2d 857 (Idaho Court of Appeals, 1999)
United States v. Seymour Sapoznik
161 F.3d 1117 (Seventh Circuit, 1998)
Hollywood Fantasy Corp. v. Gabor
151 F.3d 203 (Fifth Circuit, 1998)
J.R. Cousin Industries, Inc. v. Menard, Inc.
127 F.3d 580 (Seventh Circuit, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
918 F.2d 689, 1990 U.S. App. LEXIS 20376, 1990 WL 178547, Counsel Stack Legal Research, https://law.counselstack.com/opinion/autotrol-corporation-v-continental-water-systems-corporation-and-olin-ca7-1990.