Beuc v. Morrissey

463 S.W.2d 851, 1971 Mo. LEXIS 1103
CourtSupreme Court of Missouri
DecidedMarch 8, 1971
Docket55688
StatusPublished
Cited by13 cases

This text of 463 S.W.2d 851 (Beuc v. Morrissey) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beuc v. Morrissey, 463 S.W.2d 851, 1971 Mo. LEXIS 1103 (Mo. 1971).

Opinion

FINCH, Judge.

This is an appeal from a verdict and judgment for defendant in plaintiff’s action to recover on a written contract whereby he was to prepare architectural plans. On appeal, the St. Louis Court of Appeals, having concluded that plaintiff’s motion for directed verdict on liability should have been sustained, reversed and remanded for trial on the issue of damages only. On application, we ordered the case transferred on the theory that the opinion of the St. Louis Court of Appeals was in conflict with our decision in Kansas City Bridge Co. v. Kansas City Structural Steel Co., Mo., 317 S.W.2d 370. On transfer, we decide this case as though originally appealed to this court. Art. V, § 10, Constitution of Missouri, 1945, V.A.M.S. We reverse and remand for retrial.

Plaintiff, an architect, sued on a written contract dated January 29, 1965, wherein he agreed to furnish preliminary sketches and plans plus general contract working drawings for multiple living units to be constructed by defendant in Mankato, Minnesota. The contract gave no details as to size and number of buildings for which plans were to be prepared and contained no provision as to when plaintiff was to complete his work under the contract. It provided that the contract shotdd be construed according to the laws of Missouri. Plaintiff’s petition alleged that after he had partially performed his obligations under the contract, defendant notified him to stop work on the project, although plaintiff was ready, able and willing to complete the work. It also alleged that defendant then hired another architect to complete the plans and that defendant thereafter refused to pay plaintiff in accordance with the contract. The contract provided a formula for payment based on cost of construction and plaintiff sought recovery of what was allegedly the entire fee provided by the contract plus certain expenses. Plaintiff did not' seek recovery on quantum meruit.

Defendant’s answer was a general denial plus allegations that plaintiff failed to perform as required by the contract; that said performance by plaintiff was a condition to defendant’s duty to perform; and that by reason of plaintiff’s breach, the defendant terminated the contract. 1 The answer made no reference to what defendant *853 at the trial asserted to be a prior oral agreement that the plans were to be delivered by March 1, 1965.

The transcript on appeal is quite lengthy, but the disposition we make of this case does not necessitate a recital of all the evidence.

The testimony discloses that in December, 1964, defendant met with plaintiff relative to the possibility of plaintiff doing work for defendant involving two proposed construction projects, one at Springfield, Missouri (with which we are not concerned in this case) and one at Man-kato, Minnesota. It was agreed at that time that plaintiff would do the work on the Mankato job and defendant gave plaintiff various plans of the Paxton Lumber Company (for a dormitory and a 24-family apartment building) which he desired altered and adapted for the project. Plaintiff conceded that defendant stated that he wanted the plans in a hurry and that someone from defendant’s office stated they wanted the plans in order to get a loan commitment, building permits and firm bids. He also testified that defendant had said that he wanted to get the buildings completed in time for occupancy at the fall term, 1965, of the college at Mankato. Plaintiff denied, however, that defendant ever said to him that he wanted the plans by March 1, 1965. He further said that he did not recall that Bill Koman, an employee of defendant, ever said they wanted the plans by March 1. Defendant testified that in December, 1964, he told plaintiff he wanted the plans completed by March 1, 1965, and plaintiff agreed to furnish them by that time.

Plaintiff started work on the plans after the December, 1964, meeting. Subsequently, plaintiff prepared a written contract covering the Mankato job which he submitted to defendant and which both executed on January 29, 1965. That was the contract on which plaintiff brought suit.

Although defendant’s answer made no reference to the alleged oral agreement as to time of performance, defendant consistently, in his deposition before trial and at the trial itself, maintained that there was an oral agreement that the completed plans were to be furnished by March 1, 1965. He tried the case on that theory and there was considerable evidence on the subject introduced at the trial, most of it without objection.

The question of whether such parol testimony that there was an earlier verbal agreement on a March 1, 1965, completion date is to be considered in determining the respective rights of the parties is one which we must decide at the outset as a prelude to the consideration of other questions presented on this appeal.

Plaintiff’s position, briefly stated, is that the written contract of January 29, 1965, represented the entire agreement between the parties, all prior negotiations and agreements being merged therein. Plaintiff contends that defendant, by his testimony as to a prior verbal agreement that plaintiff should complete and deliver the plans by March 1, 1965, sought to contradict or vary the terms of the written instrument, in violation of the so-called parol evidence rule, and hence said evidence was inadmissible and cannot be considered. Rather, says plaintiff, the law implies a reasonable time for performance when the contract is silent as to a specific date therefor. Plaintiff adds that the fact that much of this evidence came in without objection is immaterial because actually the parol evidence rule is one of substantive law rather than of evidence, and such evidence must be ignored even if received in evidence without objection.

At the outset, we note that the parol evidence actually did not undertake to contradict or vary the written terms of the contract of January 29. That agreement said absolutely nothing about time for per- *854 formalice by plaintiff. 2 The parol evidence only sought to show that the parties previously had agreed verbally on a time for performance and that the written contract was not a complete integration of their understanding.

This court, in Kansas City Bridge Co. v. Kansas City Structural Steel Co., supra, held that where a contract on its face discloses that it is incomplete as to time for performance, evidence of a prior oral agreement as to time for performance is admissible to rebut the presumption that plaintiff has a reasonable time for performance (which presumption would prevail in the absence of a prior or contemporaneous agreement as to a specific time for performance). In so holding, the court recognized that there is a split of authority on the question of whether, when a written contract is silent as to time of performance, there is to be a conclusive presumption that the parties, by such silence, intended that there should be a reasonable time for performance (just as though they had specifically so stated in the contract) or whether the doctrine of partial integration should be applied so as to permit ora] evidence of agreement on a matter which the written contract did not purport to cover.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tribus, LLC v. Greater Metro, Inc.
Missouri Court of Appeals, 2019
Compass Bank v. Eager Road Associates, LLC
922 F. Supp. 2d 818 (E.D. Missouri, 2013)
White v. Land Clearance for Redevelopment Authority
841 S.W.2d 691 (Missouri Court of Appeals, 1992)
Gilomen v. Southwest Missouri Truck Center, Inc.
737 S.W.2d 499 (Missouri Court of Appeals, 1987)
Weltscheff v. Medical Center of Independence, Inc.
597 S.W.2d 871 (Missouri Court of Appeals, 1980)
Tile-Craft Products Co., Inc. v. Exxon Corp.
581 S.W.2d 886 (Missouri Court of Appeals, 1979)
Gruhala v. Lacy
559 S.W.2d 286 (Missouri Court of Appeals, 1977)
Forsythe v. Starnes
554 S.W.2d 100 (Missouri Court of Appeals, 1977)
Hardwick v. ISC Industries, Inc.
542 S.W.2d 302 (Missouri Court of Appeals, 1976)
South Side Plumbing Co. v. Tigges
525 S.W.2d 583 (Missouri Court of Appeals, 1975)
Modine Manufacturing Company v. Carlock
510 S.W.2d 462 (Supreme Court of Missouri, 1974)
Garden Park Homes Corp. v. Martin Marietta Corp.
507 S.W.2d 368 (Supreme Court of Missouri, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
463 S.W.2d 851, 1971 Mo. LEXIS 1103, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beuc-v-morrissey-mo-1971.