Professional Laundry Management Systems, Inc. v. Aquatic Technologies, Inc.

109 S.W.3d 200, 2003 Mo. App. LEXIS 953, 2003 WL 21446549
CourtMissouri Court of Appeals
DecidedJune 24, 2003
DocketED 80853
StatusPublished
Cited by16 cases

This text of 109 S.W.3d 200 (Professional Laundry Management Systems, Inc. v. Aquatic Technologies, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Professional Laundry Management Systems, Inc. v. Aquatic Technologies, Inc., 109 S.W.3d 200, 2003 Mo. App. LEXIS 953, 2003 WL 21446549 (Mo. Ct. App. 2003).

Opinion

LAWRENCE E. MOONEY, Chief Judge.

In this contract dispute, Aquatic Technologies, Inc. (Seller) and Dennis Flaum (Flaum) (collectively Appellants), appeal the trial court’s judgment against them and in favor of Professional Laundry Management Systems, Inc. (Buyer) in Buyer’s suit for breach of contract and for misrepresentation. Seller also appeals the court’s adverse judgment on its counterclaim/third-party petition for breach of contract and unjust enrichment. Appellants argue the trial court erred in: (1) considering extrinsic evidence regarding delivery dates in violation of the parol evidence rule; (2) holding Flaum personally hable for breach of contract, because Flaum was an agent acting on behalf of Aquatic; and (3) entering judgment against them on the misrepresentation claim, because Buyer failed to prove all the essential elements for fraudulent misrepresentation. We affirm in part and reverse in part. Because Appellants’ claim of error regarding the alleged violation of the parol evidence rule affords them no relief, the court’s judgment against Seller on the breach of contract claim is affirmed. And, *202 because we affirm the court’s judgment against Seller on the breach of contract claim, and because Seller raises no separate claim of error regarding the judgment against it on its counterclaim/third-party petition, the court’s judgment on Seller’s counterclaim/third-party petition is affirmed. However, because there is not substantial evidence to impose personal liability on Flaum, the court’s judgment against him on the breach of contract claim is reversed. Additionally, because there is not substantial evidence to support a claim for misrepresentation, the court’s judgment on that count is also reversed.

Factual and Procedural Background

This dispute arises out of two contracts entered into by Buyer and Seller for the purchase of certain used laundry equipment. Buyer, a commercial laundry, had entered into an agreement with a healthcare provider to process the provider’s linens, beginning in April of 1999. In order to handle this increased volume, Buyer needed to expand its facility and laundry system. Initial conversations took place in the fall of 1998 between Buyer’s employees and Mr. Flaum, part-owner of Seller, as a potential supplier of laundry equipment. These conversations consisted of a basic exchange of information about Buyer’s substantial increase in business, its plans for expansion, the time frame for completion of the expansion in order to meet the increased volume, as well as the equipment Seller had available. Following these conversations and Flaum’s tour of Buyer’s facilities, Seller submitted a contract proposal to Buyer, whereby Seller agreed to provide certain used laundry equipment to the Buyer, for a sum total of $235,000. Buyer signed the contract on October 21, 1998, and made an initial payment of $70,000.

This October contract contained no provision regarding delivery times. Buyer’s president testified at trial that the entire system was to be delivered and in-house by December 15,1998. Installation was to be completed and the system operational for a test run by February 1,1999, and the system was expected to be up and running by March 1st, giving Buyer a month’s leeway before it was to begin processing the additional laundry. Evidence adduced at trial showed that Seller was aware of Buyer’s expansion and that Buyer needed the equipment installed and running by March 1st in order to handle the increased volume of laundry.

The first delivery of equipment arrived in early December, 1998. However, only part of the equipment contracted for was delivered. Delivery on the remaining items was delayed until the end of December, and then delayed again until January. In mid-January, when the remaining equipment had yet to be delivered and when it was clear that the equipment was not going to be delivered in time to be installed and operational for Buyer to handle its increased load, Seller induced Buyer to sign a second contract for additional equipment. Buyer would not have entered into this second contract had the equipment contracted for under the October contract been delivered as expected. Two other deliveries were made, in February and March. Again, these were only partial deliveries. Buyer began sending demand letters after the February delivery, and continued to demand delivery or return of his money until the middle of April, well past the start-up date for Buyer’s increased business. However, the vast majority of the items contracted for, under either contract, were never delivered.

As to the few items which were delivered, all or substantially all of the equipment was defective in one way or another, *203 having arrived broken, in disrepair, missing parts, or damaged beyond the point of use. Buyer contacted Seller following each delivery to express its complaints about the condition of the delivered items, as well as its concern about the items that had not been delivered. After the February delivery, Seller promised to send a mechanic to repair the equipment, but this promise was never fulfilled. Buyer held a public auction in the fall of 2000, but was unable to sell any of the items, and could only dispose of the equipment by giving it away to third parties, with Buyer incurring the shipping expenses.

Buyer filed suit against Appellants, both Seller and Flaum, for rescission, breach of contract, and damages for misrepresentation. Seller filed a counterclaim against Buyer and a third-party petition against Buyer’s president, Bill Hammerstroem, for breach of contract due to nonpayment, or alternatively, for unjust enrichment. Following a bench trial, the court found Appellants in breach of contract for failure to deliver pursuant to the promised time frames, and entered judgment in favor of Buyer and against both Seller and Flaum on Buyer’s counts for breach of contract and misrepresentation. The court also entered judgment against Seller on its counterclaim/third-party petition. 1

Standard of Review

On review of this court-tried case, we will affirm the trial court’s judgment unless there is no substantial evidence to support the court’s decision, the decision is against the weight of the evidence, or the court erroneously declares or applies the law. Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. banc 1976). We are primarily concerned with the correctness of the trial court’s result, not the route taken by the trial court to reach that result. Business Men’s Assur. Co. of America v. Graham, 984 S.W.2d 501, 506 (Mo. banc 1999). Thus, we will affirm the trial court’s judgment under any reasonable theory supported by the evidence, regardless of whether the reasons advanced by the trial court are wrong or not sufficient. Id. We view the evidence, and permissible inferences therefrom, in the light most favorable to the trial court’s decision and disregard all contrary evidence and inferences. Farmers’ Elec. Co-op., Inc. v. Missouri Dept. of Corrections, 59 S.W.3d 520, 522 (Mo. banc 2001).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tribus, LLC v. Greater Metro, Inc.
Missouri Court of Appeals, 2019
Allen Quarries, Inc. v. Auge
244 S.W.3d 781 (Missouri Court of Appeals, 2008)
Milligan v. CHESTERFIELD VILLAGE GP, LLC
232 S.W.3d 683 (Missouri Court of Appeals, 2007)
Cadco, Inc. v. Fleetwood Enterprises, Inc.
220 S.W.3d 426 (Missouri Court of Appeals, 2007)
Cotton v. Flik International Corp.
213 S.W.3d 189 (Missouri Court of Appeals, 2007)
Reding v. Goldman Sachs & Co.
382 F. Supp. 2d 1112 (E.D. Missouri, 2005)
Peet v. Randolph
157 S.W.3d 360 (Missouri Court of Appeals, 2005)
Jackson v. Cannon
147 S.W.3d 168 (Missouri Court of Appeals, 2004)
Christian Health Care of Springfield West Park, Inc. v. Little
145 S.W.3d 44 (Missouri Court of Appeals, 2004)
Citibank (South Dakota), N.A. v. Mincks
135 S.W.3d 545 (Missouri Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
109 S.W.3d 200, 2003 Mo. App. LEXIS 953, 2003 WL 21446549, Counsel Stack Legal Research, https://law.counselstack.com/opinion/professional-laundry-management-systems-inc-v-aquatic-technologies-inc-moctapp-2003.