Maizel v. Bush

337 S.W.2d 337, 1960 Tex. App. LEXIS 2397
CourtCourt of Appeals of Texas
DecidedJuly 1, 1960
Docket15597
StatusPublished
Cited by7 cases

This text of 337 S.W.2d 337 (Maizel v. Bush) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maizel v. Bush, 337 S.W.2d 337, 1960 Tex. App. LEXIS 2397 (Tex. Ct. App. 1960).

Opinion

DIXON, Chief Justice.

Our former opinion in this appeal is withdrawn and the following opinion is substituted.

Appellee J. E. Bush, doing business as Texas Automatic Sprinkler Company, sued appellant Noah Maizel, doing business as Texas Waste Salvage Company, seeking judgment for the contract price of $6,134 alleged to be due and unpaid for the installation of a sprinkler system in appellant’s place of business in San Antonio, Texas.

Appellant defended on the ground that appellee had not finished the job in accordance with the terms of the contract, and as a result it had been necessary to employ another company at a cost to appellant of $2,690 to do additional work in order to complete the job, and to expend the sum of $962 in increased insurance premiums.

The case was tried before a jury which answered issues adversely to appellant. Judgment was accordingly rendered for ap-pellee and against appellant for $6,134, plus $613.40 attorney’s fees, a total of $6,747.40. The judgment provided for interest at the rate of 6% per annum from January 1, 1956.

The facts in this case are unusual and at times confusing.

Appellee had begun work in connection with the installation of the sprinkler system in November 1954, before the written contract was signed on January 27, 1955.

The premises where the sprinkler system was to be installed are described in the written contract as a “one story building having approximate dimensions of 30/ x 28', 32/x66/, 32'x40', 68'x 156', and 140' x 1507’ The testimony of the witnesses for both sides refers to several buildings. Apparently there were several buildings involved, as the above dimensions suggest, but they were connected in such a way that in a sense they might be considered one building. Not all of the buildings or sections had been erected when appellee began his work in November 1954, or when the written contract was signed January 27, 1955. Appellant and appellee had conferred and thereafter appellee prepared a set of plans and later a second set of plans. According to appellee these two sets of plans supplement each other and taken together make a complete set of plans for the installation of the sprinkler system.

The plans prepared by appellee were not submitted to appellant for approval. They are not attached to, or referred to in the written contract. Appellant testified, and the testimony is undisputed, that the first time he ever saw the plans was at the trial of this case in October 1958.

The two sets of plans were sent to the Fire Prevention and Engineering Bureau of •Texas for approval, and were approved ,by the Bureau- on January 17, 1955 and April 29, 1955, respectively. The Bureau is an organization maintained by approximately 200 stock fire insurance companies *339 to render engineering service in connection with the fire insurance business.

The written contract provides that after installation the sprinkler system shall he “subject to inspection by Fire Prevention & Engineering Bureau of Texas, acting as the Agent of both parties, whose inspection and approval of the work done hereunder by the Seller shall be conclusive evidence of the proper performance and completion of the Seller’s obligation hereunder.”

The approval of the plans by the Bureau is not to be interpreted as meaning that the plans were necessarily in accordance with the written contract. Henly H. Davis, Assistant Chief Engineer of the Bureau, testified that the Bureau does not undertake to see that sprinkler systems are installed according to terms of contracts. Its duty is to see that sprinkler systems are put in according with requirements of National Board standards of fire prevention. In this case the Bureau did not even see the contract and had no knowledge of its contents whatever.

Henly H. Davis also testified that approval of plans by the Bureau does not necessarily mean that the Bureau will later approve the system as actually installed, though it may have been installed according to the approved plans. This occurs sometimes because the Bureau does not make a physical inspection of the premises in question before approving the plans. The plans may show a satisfactory sprinkler service of wall to wall areas and ceiling areas, but fail to show particular areas needing sprinkler service, such, for instance, as an area underneath heavy machinery. This situation may not be disclosed by the plans, but will be discovered when the Bureau inspector visits the premises after a sprinkler system is installed, and goes all over the areas regardless of whether they are shown on the plans. The present case presents such an instance.

We think the undisputed testimony of Davis in this particular is of sufficient importance to- be quoted:

“Q. Now, it is possible that those plans might not show some machines or some equipment or some eaves that are actually down there and if they do it just like the plans say will not pass your inspection, is that correct? A. That is correct.
“Q. And that is exactly what happened, here, isn’t it? A. Apparently gQ. ⅜ ⅜ ⅜
“Q. If there had been shown to have been some hammermills and conveyor belts and so forth on that first plan, you would have had to require some additional sprinklers before you approved that first plan, would you not? A. That’s right. We would not have stamped those approvals; if they were not on the plans.
“Q. And you don’t know who submitted those or who put them on, or who left them off? A. I know they were submitted to us by the Texas Automatic Sprinkler Company; by whom personally, I do not know.
“Q. In other words, the sprinkler company gave them to you and they didn’t show any machinery in the floor ? A. That’s right.
“Q. And substantially the defects you found on your physical inspection, was that they had omitted putting the sprinklers underneath this machinery, is that correct? A. The machinery and that one room; you can refer to it as machinery or construction areas.”

Appellee says that he completed performance of the contract in July 1955. He demanded payment, and following appellant’s refusal to pay, appellee filed this suit October 5, 1955.

The suit -was filed before the Fire Prevention and Engineering Bureau had made its inspection of the sprinkler system installed by appellee. The actual physical -inspection was not made until June 27, 1956. The System was not approved in full.

*340 Certain deficiencies were pointed out in the Bureau’s letter to appellee dated June 28, 1956. We quote from the letter: ■’

“The following deficiencies were noted at the time of inspection and will have to be corrected before final approval for the protection afforded can be issued. 1. There is a 12 x 40-foot frame metal-clad room which has been erected inside of the Baling Section which will have to be sprinklered.
“2. There is a 12 x 13-foot metal hopper which should have sprinklers installed beneath it unless it is dismantled and removed as the owners indicated would be done.
“3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hall v. Birchfield
718 S.W.2d 313 (Court of Appeals of Texas, 1986)
Zion Missionary Baptist Church v. Pearson
695 S.W.2d 609 (Court of Appeals of Texas, 1985)
Exxon Corp. v. Eastman Kodak Co.
589 S.W.2d 473 (Court of Appeals of Texas, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
337 S.W.2d 337, 1960 Tex. App. LEXIS 2397, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maizel-v-bush-texapp-1960.