Redondo Construction Corp. v. Puerto Rico Highway & Transportation Authority (In Re Redondo Construction Corp.)

678 F.3d 115, 2012 WL 1649704
CourtCourt of Appeals for the First Circuit
DecidedMay 11, 2012
Docket11-1614
StatusPublished
Cited by17 cases

This text of 678 F.3d 115 (Redondo Construction Corp. v. Puerto Rico Highway & Transportation Authority (In Re Redondo Construction Corp.)) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Redondo Construction Corp. v. Puerto Rico Highway & Transportation Authority (In Re Redondo Construction Corp.), 678 F.3d 115, 2012 WL 1649704 (1st Cir. 2012).

Opinion

SELYA, Circuit Judge.

This appeal consolidates three adversary proceedings that were tried in the bankruptcy court. Each proceeding involves a discrete set of claims by the debt- or, a construction company that has fallen upon hard times, against a government agency, the Puerto Rico Highway and Transportation Authority (the Authority). The bankruptcy court awarded the debtor a total of nearly $12,000,000 in damages, plus prejudgment interest. On intermediate appeal, the district court deemed the Authority’s claims of error unpreserved and affirmed the judgment in all respects. After careful consideration, we find that only one of the Authority’s claims of error is forfeited. Proceeding to the merits, we reject some of the Authority’s other contentions but vacate and remand for a recalculation of home-office overhead damages and reconsideration of the issue of prejudgment interest.

I. BACKGROUND

The bankruptcy court (Carlo, J.) wrote a comprehensive rescript describing the factual background of these proceedings, see Redondo Constr. Corp. v. P.R. Highway & Transp. Auth. (In re Redondo Constr. Corp.) (Redondo I), 411 B.R. 89 (Bankr.D.P.R.2009), and we assume the reader’s familiarity with that exegesis. Our factual account is correspondingly brief.

During the early 1990s, the debtor, Re-dondo Construction Corporation, entered into three separate construction contracts with the Authority. Each contract required the debtor to undertake work on a particular project: one project entailed the construction of a bridge and access road (the Patillas project); another entailed the replacement of a different bridge (the Do-rado-Toa Alta project); and the third entailed highway improvements (the Maya-giiez project). The Authority spelled out the design plans, specifications, and anticipated site conditions for each project in the contract documents. The documents also prescribed procedures for implementing variances and adding extra work.

In the contract documents, the Authority retained the right to modify the plans and specifications. To the extent that the Authority chose to exercise this power, however, the debtor had the right to seek extra compensation (as long as the changes were material). The debtor also could lay claim to extra compensation in the event of certain contingencies requiring substantial additional work (say, unforeseen site conditions, shortcomings in the specifications, or other circumstances beyond its control). Its right to such additional compensation was, of course, subject to conditions delineated in the contract documents.

Each of the three projects encountered unanticipated problems, including unforeseen site conditions and flawed design plans. The need to take corrective actions substantially delayed completion of the projects, forced the debtor to perform extra work, and ratcheted up the costs. By way of example, the Mayagüez project ran nearly three years past schedule due to necessary modifications and change orders requested by the Authority. Despite the plethora of problems, however, the record contains no evidence that the work on any *120 of the projects was ever suspended or that the debtor was placed on standby for any period of time.

The debtor eventually navigated this obstacle course and completed all three of the projects. Not surprisingly, it submitted claims for additional amounts owed under the contracts. These included claims for monies allegedly owed by the Authority for services rendered by two subcontractors who toiled on the Maya-güez project (Continental Lord, Inc. and Remodelco, Inc.).

While the claims were still unresolved, the debtor filed for bankruptcy protection. In the Chapter 11 proceedings, 11 U.S.C. §§ 1101-1174, the debtor served the Authority with a trio of adversary complaints. Each complaint concerned amounts allegedly owed with respect to a particular project.

The complaints were tried before the bankruptcy court. See 28 U.S.C. § 157(a). With the consent of the parties, the court issued a final judgment in the matters. See Sheridan v. Michels (In re Sheridan), 362 F.3d 96, 99-100 (1st Cir.2004). The court found that each of the three projects experienced delays and cost overruns for which the Authority was responsible. See Redondo I, 411 B.R. at 95-113. It concluded, among other things, that the physical conditions at the construction sites differed materially from those described by the Authority in the contract documents and that some specifications and design elements were flawed. See id. In the end, the court awarded the debtor a total of $12,028,311.92 plus prejudgment interest at 6.5% per annum. After the Authority moved to alter or amend the judgment, see Fed.R.Civ.P. 59(e), and the debtor cross-moved to correct clerical errors therein, see Fed.R.Civ.P. 60(a), the court reduced the amount of damages by $69,792.26 but otherwise left the judgment intact. See Redondo Constr. Corp. v. P.R. Highway & Transp. Auth. (In re Redondo Constr. Corp.), 424 B.R. 29 (Bankr.D.P.R. 2010). 1

The Authority sought first-tier review of the bankruptcy court’s decision in the district court. See 28 U.S.C. § 158(a). The district court scrutinized the Authority’s assignments of error, deemed them unpre-served, and affirmed the judgment without any substantive analysis of the Authority’s assertions. This timely second-tier appeal ensued.

The appeal outlines four claims of error. First, the Authority argues that the debtor waived any claims related to the Mayagüez project by failing to furnish timely written notice of its intention to seek additional recompense. Second, it argues that the court incorrectly awarded the debtor extended overhead damages and, in the alternative, miscalculated those damages. Third, it argues that the debtor lacked standing to assert subcontractor claims. Finally, it argues that the court erred in awarding prejudgment interest.

II. ANALYSIS

We afford the final decision of a bankruptcy court plenary review without formal deference to the district court’s intermediate affirmance. Berliner v. Pap-palardo (In re Sullivan), 674 F.3d 65, 68 (1st Cir.2012); City Sanitation, LLC v. Allied Waste Seros, of Mass., LLC (In re Am. Cartage, Inc.), 656 F.3d 82, 87 (1st Cir.2011). The bankruptcy court’s legal conclusions engender de novo review, but its factual findings are examined only for

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
678 F.3d 115, 2012 WL 1649704, Counsel Stack Legal Research, https://law.counselstack.com/opinion/redondo-construction-corp-v-puerto-rico-highway-transportation-ca1-2012.