Bloom Township High School v. Illinois Commerce Commission

722 N.E.2d 676, 309 Ill. App. 3d 163, 242 Ill. Dec. 892
CourtAppellate Court of Illinois
DecidedNovember 24, 1999
Docket1-99-0625
StatusPublished
Cited by30 cases

This text of 722 N.E.2d 676 (Bloom Township High School v. Illinois Commerce Commission) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bloom Township High School v. Illinois Commerce Commission, 722 N.E.2d 676, 309 Ill. App. 3d 163, 242 Ill. Dec. 892 (Ill. Ct. App. 1999).

Opinion

JUSTICE HOFFMAN

delivered the opinion of the court:

The petitioners, Bloom Township High School, K&M Plastics, Inc., Marshall Field & Company (Marshall Field), and St. Therese Medical Center, filed separate complaints with the Illinois Commerce Commission (Commission) against the respondent, Commonwealth Edison Company (ComEd), alleging that ComEd wrongfully assessed penalty fees and other charges against them for excessive use of electrical power during the “heat wave” in July 1995. The Commission consolidated the complaints and subsequently entered summary judgment in favor of ComEd. The petitioners have filed a joint petition for review, contending that the Commission erred in granting summary judgment for the following reasons: (1) the “Rider 30 Interruptible/ Curtailment Service” tariff (Rider 30), under which they were receiving electrical power, required ComEd to make reasonable efforts to provide them with “buy-through energy” 1 in lieu of curtailment; (2) the Commission violated section 2 — 1005 of the Code of Civil Procedure (Code) (735 ILCS 5/2 — 1005 (West 1996)) by determining on summary judgment that ComEd made reasonable efforts to provide buy-through energy and that “emergency conditions” existed on July 14, 1995, such that the purchase of buy-through energy was impermissible; and (3) the Commission erred in denying Marshall Field’s motion for summary judgment, asserting that it did not receive proper notice of the curtailment.

ComEd filed a tariff with the Commission, known as Rider 30, the purpose of which is to assist ComEd in providing cost-effective and reliable electricity by reducing the amount of electricity that ComEd must provide during peak periods of demand. Service pursuant to Rider 30 is available to certain nonresidential customers of ComEd who have discretionary electrical loads that can be interrupted or curtailed. Under Rider 30, customers such as the petitioners enter into contracts with ComEd and agree to reduce their electricity usage to a preestablished firm power level 2 (FPL) upon request by ComEd. In exchange for their commitment to limit their electricity usage, ComEd agrees to compensate the customers by applying credits to their electricity bills.

Pursuant to Rider 30, the customers must elect to receive service under one of three options (A, B, or C). The three types of service differ in the number of interruptions or curtailments ComEd is allowed to invoke per year, the maximum number of hours an interruption or curtailment may last, the extent of the notice period before a curtailment can be initiated, the credits to which the customer is entitled, and the ability of the customer to purchase buy-through energy in lieu of curtailment. In this case, all of the petitioners elected to receive service under option C, which specifically provides:

“Under this option, the customer may purchase energy during a curtailment period at a cost of $.15/kWh for all kilowatthours consumed during the curtailment period associated with 30-minute demands which exceed the customer’s Firm Power Level. Such purchases are referred to as purchases in lieu of curtailment. Demand levels associated with such purchases shall be considered when determining the customer’s Maximum Demand as determined by the otherwise applicable rate. The availability of such energy shall be at the discretion of the Company, which shall notify the customer of its expected availability at the time the notice of curtailment is given. A reasonable effort to maintain that availability during a curtailment period will be made. The customer shall not be allowed to make purchases during emergency conditions.” (Emphasis added.)

Rider 30 further provides that all customers, other than those option C customers who purchase buy-through energy, shall be assessed a penalty 3 if their demand for power during a curtailment exceeds their preselected FPL.

According to the parties, on July 13, 1995, the temperatures in the Chicago area reached record levels and ComEd experienced a system peak demand for power. ComEd gave its option C customers notice of a curtailment and provided them with the opportunity to purchase buy-through energy. On July 14, 1995, the temperatures again reached record levels, and ComEd issued another curtailment. This time, ComEd did not offer its option C customers buy-through energy, and all of the petitioners refused to limit their energy usage during the curtailment. As a result, ComEd imposed penalty fees and other charges against them for their energy demand that exceeded their FPL during the curtailment. Each of the petitioners subsequently filed a complaint with the Commission, alleging that ComEd misapplied Rider 30 and wrongfully assessed penalty fees and other charges against them because ComEd failed to make reasonable efforts to provide them with buy-through energy during the curtailment as required by option C. The petitioners did not challenge the amount of the fees and charges assessed against them. In fact, they admitted that, if ComEd was entitled to such fees, then the amounts assessed against them were correct. The Commission consolidated the petitioners’ complaints and scheduled an evidentiary hearing for April 20, 1998.

Prior to the hearing, both the petitioners and ComEd submitted extensive written testimony in support of their positions, as permitted by section 200.660 of the Public Utilities Rules of Practice (83 111. Adm. Code § 200.660 (1996)). 4 At the hearing, Marshall Field presented the testimony of Andrew J. Sebescak, its senior maintenance manager. Following Sebescak’s testimony, the hearing examiner gave the parties the option of either limiting the cross-examination of all witnesses to 15 minutes or filing written briefs regarding the issue of whether Rider 30 required ComEd to make reasonable efforts to provide its option C customers with buy-through energy during a curtailment period. The parties objected to limiting the time allowed for cross-examining witnesses. Although the parties agreed that a threshold question existed as to whether option C required ComEd to use reasonable efforts to provide buy-through energy in lieu of curtailment, they disagreed as to whether the decision on this issue was outcome determinative. Consequently, the petitioners objected to the suggestion of filing cross-motions on this issue and expressed their desire to proceed with the hearing. After a lengthy discussion, the hearing examiner stated:

“[S]ince the parties are not in agreement, I just need to make a ruling or issue a direction which I feel is going to be of benefit to the Commission.
And so to that end, what I am going to direct the parties to do is to, basically, brief for me, and it can be done in the form of a motion for summary judgment with memo attached, again, with any type of testimony attached as exhibits, to indicate what the parties’ positions are in regards to the interpretation of Rider 30C.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth Edison Co v. Illinois Commerce Comm'n
2025 IL App (3d) 240697-U (Appellate Court of Illinois, 2025)
Buffalo Grove Ventures, LLC v. Five Fifths, LLC
2023 IL App (1st) 220787-U (Appellate Court of Illinois, 2023)
Hadley v. Doe
2014 IL App (2d) 130489 (Appellate Court of Illinois, 2014)
Sheffler v. Commonwealth Edison Company
Appellate Court of Illinois, 2010
Sheffler v. Commonwealth Edison Co.
923 N.E.2d 1259 (Appellate Court of Illinois, 2010)
Thomson Learning, Inc. v. Olympia Properties, LLC
850 N.E.2d 314 (Appellate Court of Illinois, 2006)
Harrisonville Telephone Co. v. Illinois Commerce Commission
817 N.E.2d 479 (Illinois Supreme Court, 2004)
Adams v. Northern Illinois Gas Co.
809 N.E.2d 1248 (Illinois Supreme Court, 2004)
Burns v. Department of Employment Security
Appellate Court of Illinois, 2003
Adams v. Northern Illinois Gas Co.
774 N.E.2d 850 (Appellate Court of Illinois, 2002)
Illinois-American Water Co. v. Illinois Commerce Commission
772 N.E.2d 390 (Appellate Court of Illinois, 2002)
Cook County Sheriff's Enforcement Ass'n v. County of Cook
753 N.E.2d 309 (Appellate Court of Illinois, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
722 N.E.2d 676, 309 Ill. App. 3d 163, 242 Ill. Dec. 892, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bloom-township-high-school-v-illinois-commerce-commission-illappct-1999.