General Mills, Inc. v. Illinois Commerce Commission

559 N.E.2d 225, 201 Ill. App. 3d 715, 147 Ill. Dec. 225, 1990 Ill. App. LEXIS 1100
CourtAppellate Court of Illinois
DecidedJuly 27, 1990
Docket1-89-0491
StatusPublished
Cited by9 cases

This text of 559 N.E.2d 225 (General Mills, Inc. v. Illinois Commerce Commission) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Mills, Inc. v. Illinois Commerce Commission, 559 N.E.2d 225, 201 Ill. App. 3d 715, 147 Ill. Dec. 225, 1990 Ill. App. LEXIS 1100 (Ill. Ct. App. 1990).

Opinion

JUSTICE LORENZ

delivered the opinion of the court:

General Mills, Inc. (General Mills), appeals from an order of the Illinois Commerce Commission (Commission) denying its complaint against Commonwealth Edison Company (Edison). We address the issue of whether the Commission properly found Edison’s rate schedule was ambiguous on its face and properly examined other documents to construe the rate schedule. For the following reasons, we affirm.

General Mills filed a complaint with the Commission on October 2, 1987, against Edison under section 9 — 252 of the Public Utilities Act (Ill. Rev. Stat. 1987, ch. lll2/s, par. 9 — 252) alleging that Edison charged General Mills an excessive and unjustly discriminatory rate for electric service from March 8, 1985, to at least December 1, 1986. General Mills alleged it was a manufacturer served under Edison’s “Rate 6L-Large General Service” (Rate 6L). On November 29, 1984, a revised version of Rate 6L became effective and provided in part:

“This rate is applicable to (1) any commercial, industrial, or governmental customer with a maximum demand of 1,000 kilowatts or more in three of the 12 months preceding the billing month, (2) successors to customers served under these charged immediately prior to the date of succession whose estimated maximum demands meet the demand requirements in clause (1) above, (3) new customers whose estimated maximum demands meet the demand requirements in clause (1) above, and (4) any customer previously billed hereunder pursuant to clauses (1) or (2), except as otherwise provided below.
If a customer at one time was served pursuant to (1) above on Large General Service — Time of Day and has a maximum demand which has not exceeded 200 kilowatts in any month of the twelve month period preceding the billing month, such customer may elect, in written application to the Company, to be served on Rate 6, General Service. Rate 6L, Large General Service — Time of Day, shall not again be applicable until such customer qualifies for such rate under clause (1) above.
The Large General Service — Time of Day charges of this rate shall not be applicable to customers or their successors with electric space heating taking service under the Heating with Light provisions of Rider 25 prior to November 23, 1977, except upon written application by the Customer to the Company. Except as stated above, the Large General Service charges shall apply to these customers.”

The rate schedule provided energy charges for two types of service: “Large General Service — Time of Day” and “Large General Service.” Under “Large General Service — Time of Day” (time-of-day charge), a customer was charged dependent on the time of day the service was provided. The charge was higher during peak periods than during off-peak periods. Under “Large General Service” (non-time-of-day charge), a customer was charged dependent on the number of kilowatt-hours supplied in a month. The charge decreased when the number of kilowatt-hours supplied increased during the month. The rate schedule also provided that it was issued pursuant to the Commission’s order entered on July 12, 1984, in case No. 83 — 0537, and its special permission order No. R — 18552, entered on November 14, 1984.

General Mills alleged that under the rate schedule neither the time-of-day charge nor the non-time-of-day charge was restricted to a certain type of customer. In a letter to Edison dated March 8, 1985, General Mills requested a transfer from the time-of-day charge to the non-time-of-day charge for its West Chicago plant. In a similar letter dated March 26, 1985, General Mills made the same request for its South Chicago plant. Edison rejected the requests and, as a result, General Mills filed a complaint seeking reparation in the amount of $700,000 plus interest.

Edison answered the complaint denying the material allegations and raised three affirmative defenses, only one of which is relevant here. Edison asserted that the version of Rate 6L at issue was filed in response to the Commission’s previous order to include a non-time-of-day charge for “Heating with Light” customers. Because General Mills was not a “Heating with Light” customer, it was not entitled to the non-time-of-day charge.

For a hearing before the Commission on the complaint, General Mills and Edison stipulated to the following facts. At all relevant times, General Mills was charged for electric service under the time-of-day energy charge of Rate 6L. Beginning November 29, 1984, Rate 6L provided for both time-of-day and non-time-of-day energy charges. On March 8, 1985, and March 26, 1985, General Mills requested a transfer from the time-of-day charge to the non-time-of-day charge under Rate 6L. Edison rejected those requests.

After a hearing, the Commission entered an order denying General Mills’ complaint. The Commission found Rate 6L was ambiguous on its face regarding the applicability of the two sets of energy charges. Although the rate schedule clearly stated that the time-of-day charge was not applicable to certain “Heating with Light” customers, it did not clearly state which charge applied to other Rate 6L customers. Further, Rate 6L did not state that those other customers had an option to choose between time-of-day and non-time-of-day charges. On the day the rate schedule went into effect, General Mills and other similarly situated customers were charged under the existing time-of-day charge. The Commission reasoned that if customers, other than certain “Heating with Light” customers, had an option between time-of-day and non-time-of-day charges under the rate schedule, a mechanism would have had to be in place for customers to make that selection at the time Rate 6L became effective. Because Rate 6L did not contain such a mechanism, the Commission found that it was ambiguous.

In its order the Commission stated, “[wjhen a question of tariff interpretation arises other documents bearing on the meaning of the tariff can be examined.” Therefore, to resolve the ambiguity the Commission examined the previous version of Rate 6L and its previous orders requiring Edison to file the rate schedule in question. Prior to November 29, 1984, Rate 6L only provided a time-of-day charge. The rate schedule in question was the result of orders dated July 12, 1984, and July 17, 1984, where the Commission directed Edison to revise Rate 6L to include a non-time-of-day charge for certain “Heating with Light” customers. In its order in the present case, the Commission found that under its previous orders it did not intend to extend the non-time-of-day charge to customers other than qualified “Heating with Light” customers. Because General Mills was not a “Heating with Light” customer, it was not entitled to the non-time-of-day charge. Accordingly, the Commission denied General Mills’ complaint and it now appeals.

Opinion

Under the Public Utilities Act, all rates for public utilities must be just and reasonable and every public utility must file schedules of rates with the Commission. (Ill. Rev. Stat. 1987, ch. lll2/3, pars. 9 — 101, 9 — 102.) A rate is defined, in part, as any schedule or tariff of a public utility. (Ill. Rev. Stat. 1987, ch. lll2/s, par.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Globalcom, Inc. v. Illinois Commerce Comm'n
Appellate Court of Illinois, 2004
Globalcom, Inc. v. Illinois Commerce Commission
806 N.E.2d 1194 (Appellate Court of Illinois, 2004)
NORTH AVE. PROP. v. Zoning Bd. of Appeals of City of Chicago
726 N.E.2d 65 (Appellate Court of Illinois, 2000)
Bloom Township HS v. Commerce Comm'n
Appellate Court of Illinois, 1999
Bloom Township High School v. Illinois Commerce Commission
722 N.E.2d 676 (Appellate Court of Illinois, 1999)
People ex rel. Hartigan v. Illinois Commerce Commission
578 N.E.2d 46 (Appellate Court of Illinois, 1991)
Moncada v. Illinois Commerce Commission
571 N.E.2d 1004 (Appellate Court of Illinois, 1991)
Shortino v. Illinois Bell Telephone Co.
565 N.E.2d 170 (Appellate Court of Illinois, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
559 N.E.2d 225, 201 Ill. App. 3d 715, 147 Ill. Dec. 225, 1990 Ill. App. LEXIS 1100, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-mills-inc-v-illinois-commerce-commission-illappct-1990.