Redondo Construction Corp. v. Puerto Rico Highway & Transportation Authority (In Re Redondo Construction Corp.)

411 B.R. 89, 2009 Bankr. LEXIS 2452, 2009 WL 2827961
United States Bankruptcy Court, D. Puerto Rico·Decided August 31, 2009·No. 18-06378·Published·Cited by 6 cases

Opinion

DECISION AND ORDER

GERARDO A. CARLO, Bankruptcy Judge.

On March 19, 2002, Redondo Construction Corporation (“RCC”) filed a voluntary petition under Chapter 11 of the Bankruptcy Code. On December 23, 2003, RCC filed three complaints against the Puerto Rico Highway Authority (“PRHA”), claiming amounts due for construction work performed in three projects: AC-005317 (“Desvío Sur de Patillas”), Adversary No. 03-0192; AC-20009 (“PR 2 Mayagüez”), Adversary No. 03-0194; and AC-01657 (“Dorado-Toa Alta”), Adversary No. 03-0195. On October 5, 2005, the Court confirmed RCC’s plan of reorganization, as amended. (Docket No. 1207).

After significant discovery by the parties, the trial on these adversaries was held on February 12-16, 26-28, and July 2 and 6, 2007. During the trial, RCC offered extensive documentary evidence and the testimony of Arq. Miguel Redondo, Engs. Rodolfo Montero, Raúl Bras, Angel Mercado, Humberto Reynolds, Luis Garcia, Mr. Andrew Civitello, and Rafael Pér-ez-Villarini, CPA.

PRHA had announced Dr. Sergio Gon-zález, Engs. Fabián Delgado, Víctor Pérez, Gonzalo Aponte, José Borges, and Messrs. *91 Rubén del Valle, Frank López, and Carlos Alamo, as its witnesses. (Pre-trial Reports) (RCC’s EX 63 1 ) (Tr. of 2/27/07, pp. 1523-1530) (Docket No. 109). Thereafter, PRHA informed that Dr. González was not going to be used as a witness and consequently, RCC offered into evidence certain portions of Dr. Gonzalez’s deposition. During the hearing of February 16, 2007, PRHA indicated that it would use all of its witnesses and the case was scheduled to include July 2, 3, 6, and 9, and if necessary, July 10, 2007. (Tr. of 2/16/07, pp. 1069-1079).

On February 28, 2007, PRHA offered the testimony of Eng. Delgado. However, on July 2, 2007, PRHA announced that of the six remaining witnesses, it was only going to use two, Engs. Pérez and Aponte (Tr. of 7/2/07, pp. 93-94), and Miguel Diaz (“Diaz”), announced by RCC as its witness, renounced as cumulative evidence, and made available to PRHA. Eng. Pérez testified on July 2, 2007. However, on July 6, 2007, PRHA announced that it was not going to use Eng. Aponte either and submitted its case.

Since RCC had deposed the witnesses renounced by PRHA, during the hearing of July 6, 2007, RCC, without opposition from PRHA, offered in evidence part of the transcripts of the following depositions, admitted as RCC’s exhibits: Mr. Alamo’s (RCC’s EX 62), Mr. López’ (RCC’s EX 66), and Eng. Del Valle’s (RCC’s EX 67). 2

At the conclusion of the trial, the Court directed the parties to file simultaneous post-trial memoranda by August 31, 2007, which was subsequently extended until November 9, 2007.

BACKGROUND

The Contracts

RCC is a corporation organized and authorized to do business in accordance with the laws of the Commonwealth of Puerto Rico. (Pretrial Report, Stipulated Facts). PRHA is a body, politic and corporate, duly established and existing under the laws of the Commonwealth of Puerto Rico. (Pretrial Report, Stipulated Facts).

On April 18, 1990, PRHA entered into a contract with RCC as to the PR-2, Maya-güez project (Federal Aid Project No. HES-2-5(17)), consisting of improvements and additional lanes at Road PR-2 from Mayagüez Terrace to PR-10. (Pretrial Report, Stipulated Facts; Joint EXs 1, 2, 3, 7, 53 3 ; RCC’s EX 8) (Tr. of 2/12/07, pp. 93-95,102-103,105,110-113).

On August 30, 1991, PRHA entered into a second contract with RCC as to the Desvío Sur de Patillas project (Federal Aid Project PR-53 Fed. F-53-1). (Pretrial Report, Stipulated Facts). This project consisted mainly of a large bridge crossing the Patillas River, with an approach road. It required pile driving to support the bridge bed and lasted about three years. The original contract price was $8,729,000.00, with an original 540-day term and was substantially completed on March 18, 1994. (Pretrial Report)(Joint EX 1; RCC’s EXs 3, 4, 5, 6 and 9 4 ) (Tr. of 2/12/07, pp. 18, 20, 33, 63-64; Tr. of 2/26/07, pp. 715-716, 725-728, 731-735, 743).

On June 7, 1993, PRHA awarded RCC a third contract, the Dorado-Toa Alta project, consisting of the replacement of a bridge and access roads between Dorado *92 and Toa Alta, Puerto Rico, for $2,657,000.00, known as Construction of Federal Aid Project BR-2165 (12), Replacement of Bridge No. 365, Highway PR 165R, Municipalities of Dorado and Toa Alta, PR, also with a 540-day term. (Pretrial Report, Stipulated Facts). This project was completed on September 5, 2005. (Joint EX 1; RCC’s EXs 11, 12, 13, 14 5 )(Tr. of 2/12/07, pp. 19-20, 45).

The plans and specifications for all three projects were prepared by PRHA. (Tr. 2/12/07, pp. 50-51). The three were unit-price projects and had federal funds participation. (Tr. of 2/12/07, pp. 45-46, 139-141; Tr. of /15/06, pp. 801-802, 878-882).

The master contract for each of the three projects is contained in a contract book that incorporates the award, the bid documents, the plans and specifications and general provisions, as an integral part thereof. It also incorporates the Commonwealth of Puerto Rico Department of Transportation and Public Works and Highway Authority’s “Standard Specifications for Road and Bridge Construction of 1989,” known as the “Blue Book.” (Pretrial Reports, Stipulated Facts; Joint EXs 1 and 53 as to the 3 projects)(Tr. of 2/12/07, pp. 45, 102-103, 105, 109, 111-113, 117-121).

Blue Book Provisions

The pertinent parts of the Blue Book are as follows:

Section 104 of the Blue Book titled Scope of Work provides as to the intent of the contract and the alterations of plans or character of the proposed work:

104.01 Intent of Contract — The intent of the Contract is to provide for the construction and completion in every detail of the work described. The Contractor shall furnish all labor, materials, equipment, tools, transportation and supplies required to complete the work in accordance with the plans, specifications and terms of the contract.
104.02 Alteration of Plans or Character of Proposed Work—
a. The Authority reserves the right to make, at any time during the progress of the work, such increases or decreases in quantities and such alterations in the work as necessary to satisfactorily complete the project. Such increases or decreases and alterations shall not invalidate the contract nor release the Surety, and the Contractor agrees to perform the work as altered.

Free access — add to your briefcase to read the full text and ask questions with AI

Redondo Construction Corp. v. Puerto Rico Highway & Transportation Authority (In Re Redondo Construction Corp.), 411 B.R. 89, 2009 Bankr. LEXIS 2452, 2009 WL 2827961 (prb 2009).

411 B.R. 89 (Redondo Construction Corp. v. Puerto Rico Highway & Transportation Authority (In Re Redondo Construction Corp.)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related