Department of Natural Resources & Conservation v. United States

30 Cont. Cas. Fed. 70,906, 1 Cl. Ct. 727, 1983 U.S. Claims LEXIS 1826
CourtUnited States Court of Claims
DecidedMarch 14, 1983
DocketNo. 46-80C
StatusPublished
Cited by18 cases

This text of 30 Cont. Cas. Fed. 70,906 (Department of Natural Resources & Conservation v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Department of Natural Resources & Conservation v. United States, 30 Cont. Cas. Fed. 70,906, 1 Cl. Ct. 727, 1983 U.S. Claims LEXIS 1826 (cc 1983).

Opinion

OPINION

LYDON, Judge:

In this action, plaintiff seeks reimbursement from the United States of amounts it had to pay a third party, arising out of a contract between plaintiff and the third party, as a result of a State court judgment. Plaintiff contends that, since this adverse judgment resulted solely from the government’s breach of its obligations under a contract between plaintiff and the government, a provision in this contract, purporting to limit the government’s liability under the contract to only 50 percent of any such payment, is inapplicable.

I.

This case arises out of a “Project Agreement,” or contract, entered into by plaintiff, and the United States Soil Conservation Service (Service) on May 1, 1970. The project agreement was entered pursuant to the Watershed Protection and Flood Prevention Act, 16 U.S.C. Sec. 1002 (1972), and enabled the Federal Government to cooperate with the State of Montana in preserving, protecting and improving the State’s land and water resources.

The purpose of this particular Project Agreement or contract was to rehabilitate and enlarge an existing State-owned irrigation system in Montana. This required the construction and replacement of pumps located along the Yellowstone River in Montana, and the building of some new relift stations. Under the contract, the State agreed to engage a contractor to build the various irrigation pump stations along the river and to provide 50t percent of the cost of constructing the pump stations. In exchange, the Service agreed to design and prepare plans and specifications for the construction sites and also to pay 50 percent of the construction costs of the planned improvements.

The Service designed the pump stations and prepared the plans and specifications. The plaintiff then issued an invitation for bids to construct the pump stations according to the Service plans and specifications. Plaintiff awarded the Sornsin Construction Company (Sornsin) the contract on the basis of its low bid. During the course of performing the contract, Sornsin encountered difficulties which it attributed to the Service plans and specifications. Sornsin presented several claims for equitable adjustments to plaintiff due to the increased costs incurred as a result of alleged faulty plans and specifications. All of Sornsin’s equitable adjustment claims were ultimately denied by plaintiff’s contracting officer, a State official.1

[731]*731Sornsin then initiated an action in a Montana State court seeking damages from plaintiff for breach of contract. After a lengthy jury trial, Sornsin received a damage award. This award was later upheld, for the most part, by the Supreme Court of the State of Montana. Sornsin Constr. Co. v. State of Montana, 180 Mont. 248, 590 P.2d 125 (1978) and Sornsin, by an amended judgment, was awarded damages of $320,-984.05.

The United States thereafter paid plaintiff one-half of the State court judgment, or $160,492.02, pursuant to Clause E 5 of the contract between plaintiff and the Service. Clause E 5 reads as follows:

E. It is mutually agreed that:

******
5. Additional funds required as the result of a decision of the Contracting Officer on a contractor’s claim or a judgment as a result of a lawsuit brought by the contractor will be provided in the same ratio as construction funds are contributed under the terms of this agreement; the Service will not contribute additional funds where a judgment of a court is based upon a breach of contract by the Contracting Local Organization [plaintiff]; the Contracting Local Organization has failed to discharge its responsibilities under this agreement or the resulting contract; the State Administrative Officer has not approved the decision of the Contracting Officer; the State Administrative Officer has not approved the plans for and defense of the lawsuit; or the Contracting Local Organization has not exercised its right of appeal when requested to do so by the Service. In no case will the Service contribute additional funds for payment of attorney’s fees.

Plaintiff brought this action against the United States in the United States Court of Claims to recover the remaining 50 percent of the judgment, or $160,492.03, which plaintiff paid Sornsin pursuant to the State court judgment, plus $31,855.22 for attorney’s fees plaintiff incurred in defense of Sornsin’s action in the State courts.

Defendant thereafter moved for summary judgment on two grounds: (1) that the Court of Claims lacked jurisdiction because the Project Agreement between plaintiff and the Service was not a “contract” within the purview of the Tucker Act,2 and (2) that the Service did not violate its contractual obligations. By order dated March 6, 1981, the Court of Claims denied defendant’s motion for summary judgment holding that the Project Agreement constituted a contract in the traditional sense and thus came within the pale of the Tucker Act. Department of Natural Resources and Conservation of Montana v. United States, 227 Ct.Cl. 552 (1981). In remanding the case to the Trial Division for further proceedings, the Court of Claims stated in pertinent part as follows:

[732]*732In refusing to pay the remaining monies that the plaintiff paid pursuant to the judgment in the suit against it by the contractor, the government relies on the provision of the agreement that obligates it to pay only one-half of ‘[additional funds required as a result of ... a judgment as a result of a lawsuit brought by the contractor.’ It asserts that this provision limits its liability for any alleged expenses the plaintiff incurs as a result of a judgment in a lawsuit by the contractor to 50 percent of that judgment. The plaintiff responds that that provision does not apply where, as here, the judgment itself resulted from the government’s breach of the contract. The plaintiff asserts that in that situation it may recover from the government its total damages resulting from the breach even though those damages resulted from the judgment.
The meaning of the 50 percent judgment clause is unclear and difficult to determine. The clause itself is ambiguous, and other provisions of the contract provide little assistance in interpreting it. In these circumstances we conclude that parol evidence regarding the negotiation of the contract and the intention of the parties might aid in construing the provision. Moreover, if it were held either that the Service had not breached its obligation under the contract to furnish plans and specifications or that, even if there had been such a breach, it was not the cause of the plaintiff’s judgment liability to the contractor, there would be no need to interpret the 50 percent judgment provision. Accordingly, we decline at this time to decide whether the government complied with its contractual obligation by paying the plaintiff 50 percent of the amount the plaintiff paid to its contractor pursuant to the State court judgment. [227 Ct.Cl. at 554-55.]

Following trial, on remand, the parties submitted proposed findings of fact and briefs.

The initial issue confronting the court is whether Clause E 5 is for application under the facts of this case. Defendant maintains that Clause E 5 limits its liability for any expenses plaintiff incurs as a result of a judgment in a lawsuit by a contractor against plaintiff to 50 percent of that judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scott Timber, Inc. v. United States
86 Fed. Cl. 102 (Federal Claims, 2009)
Precision Pine & Timber, Inc. v. United States
50 Fed. Cl. 35 (Federal Claims, 2001)
Martin v. United States
30 Fed. Cl. 542 (Federal Claims, 1994)
National Medical Enterprises, Inc. v. United States
28 Fed. Cl. 540 (Federal Claims, 1993)
Keene Corp. v. United States
12 Cl. Ct. 197 (Court of Claims, 1987)
Sperry Corp. v. United States
33 Cont. Cas. Fed. 74,234 (Court of Claims, 1986)
Saunooke v. United States
8 Cl. Ct. 327 (Court of Claims, 1985)
Carpenter v. United States
7 Cl. Ct. 732 (Court of Claims, 1985)
Little River Lumber Co. v. United States
7 Cl. Ct. 492 (Court of Claims, 1985)
Laka Tool & Stamping Co. v. United States
32 Cont. Cas. Fed. 73,202 (Court of Claims, 1984)
Sioux Tribe of Indians v. United States
6 Cl. Ct. 91 (Court of Claims, 1984)
Cedar Lumber, Inc. v. United States
32 Cont. Cas. Fed. 72,561 (Court of Claims, 1984)
Baldwin Park Community Hospital v. United States
4 Cl. Ct. 347 (Court of Claims, 1984)
Joseph Morton Co. v. United States
31 Cont. Cas. Fed. 71,809 (Court of Claims, 1983)
International Electronics Corp. v. United State
31 Cont. Cas. Fed. 71,240 (Court of Claims, 1983)
Ables v. United States
2 Cl. Ct. 494 (Court of Claims, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
30 Cont. Cas. Fed. 70,906, 1 Cl. Ct. 727, 1983 U.S. Claims LEXIS 1826, Counsel Stack Legal Research, https://law.counselstack.com/opinion/department-of-natural-resources-conservation-v-united-states-cc-1983.