Laka Tool & Stamping Co. v. United States

32 Cont. Cas. Fed. 73,202, 7 Cl. Ct. 213, 1984 U.S. Claims LEXIS 1229
CourtUnited States Court of Claims
DecidedDecember 17, 1984
DocketNo. 425-78
StatusPublished
Cited by4 cases

This text of 32 Cont. Cas. Fed. 73,202 (Laka Tool & Stamping Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Laka Tool & Stamping Co. v. United States, 32 Cont. Cas. Fed. 73,202, 7 Cl. Ct. 213, 1984 U.S. Claims LEXIS 1229 (cc 1984).

Opinion

OPINION

LYDON, Judge:

This government contract case is before the court for Wunderlich Act review (41 U.S.C. §§ 321, 322 (1976)) of a decision, adverse to plaintiff, by the Armed Services Board of Contract Appeals (the Board) on April 12, 1984. Laka Tool & Stamping Co., ASBCA No. 21338 (Reinstated), 84-2 BCA, ¶ 17,326. This case was .previously before the United States Court of Claims pursuant to a Wunderlich Act review request by plaintiff. Laka Tool & Stamping Co. v. United States, 226 Ct.Cl. 83, 639 F.2d 738 (1980), reh’g denied, 227 Ct.Cl. 468, 650 F.2d 270 (1981), cert. denied, 454 U.S. 1086, 102 S.Ct. 645, 70 L.Ed.2d 6220. In its decision in this case, the Court of Claims, inter alia, remanded this case to the Board for further proceedings on the narrow issue of plaintiff’s entitlement “to recover those excess costs, if any, which plaintiff expended in attempting to comply with the original impossible specifications before modification.” (227 Ct.Cl. at 469, 650 F.2d at 271).1 The April 12, 1984 Board decision, supra, represents the Board’s compliance with the remand directive of the Court of Claims. Plaintiff challenges this Board decision on legal and factual grounds. Defendant maintains that the Board decision is correct as a matter of law and that plaintiff’s challenges to certain Board “findings of fact” are without merit. Both parties have moved for summary judgment. Upon consideration of the briefs of the parties and oral argument, the court concludes that defendant’s cross-motion for summary [215]*215judgment should be granted and plaintiff’s motion for summary judgment denied.

I.

The background facts in this case were fully set forth in the earlier opinion of the Court of Claims (226 Ct.Cl. 83, 639 F.2d 738). Briefly, on June 4, 1975, plaintiff was awarded a contract by the United States Army Armament Command to manufacture and deliver certain rifle magazines. The original contract specifications proved impossible of performance in certain respects and accordingly were modified. However, plaintiff was unable to perform the contract under the modified specifications which were found not to be impossible of performance. Eventually, plaintiff was terminated for default. As indicated previously, the Court of Claims found this default termination to be proper, but remanded the case to the Board for a determination of the excess costs, if any, that plaintiff expended in attempting to comply with the original impossible to perform specifications before said specifications were modified.2 The amount of any excess costs determined by the Board on this remand was to be offset against the amount of the Government’s counterclaim.

Before the Board on remand, plaintiff filed a complaint seeking a recovery of $1,109,329. The supporting cost data were itemized on termination for convenience settlement proposal forms. There was no indication by plaintiff in this submission as to how the amount claimed related to the excess costs incurred by plaintiff prior to March 30, 1976 in attempting to satisfy the impossible 7-inch flatness requirement. The Board, properly viewing plaintiff’s submission to be unrelated to the narrow issue remanded to it, directed plaintiff to file an amended complaint. In its amended complaint, plaintiff sought recovery of total costs of $365,000 incurred up to March 30, 1976, plus $147,290 incurred by a subcontractor, a total cost figure of $512,290. Again plaintiff did not attempt to break down these figures to show their relationship to the narrow remand issue. The Board again asked plaintiff for an explanation or breakdown of its claim. In response, plaintiff submitted a claim in the amount of $485,854.13 which indicated plaintiff was claiming all of its costs allocable to the contract from contract inception to March 30, 1976. Despite the Board’s efforts to explain to plaintiff the difficulties with a total cost presentation and its emphasis on the need for some probative evidence to establish a linkage between the original impossible specification and the quantum of recovery sought, plaintiff persisted in its total cost approach.

Plaintiff moved the Board to reopen the record so that plaintiff could recover all the costs it incurred and not just those costs incurred in attempting to comply with the impossible specifications. Plaintiff argued before the Board, as it does before the court, that there was no accord and satisfaction relative to the March 30, 1976 agreement regarding the specification modification contrary to the holding by the Court of Claims that there was an accord and satisfaction. Too, plaintiff sought to recover the total costs it incurred under a termination for convenience despite the fact that the Court of Claims held that the termination of plaintiff’s contract for default was proper (see 226 Ct.Cl. at 91-94, 639 F.2d at 743-744). Plaintiff argues that the Board erred as a matter of law in refusing to reopen the record for entitlement purposes. The court finds that the Board properly denied plaintiff’s motion to reopen the record for entitlement purposes.

II.

Plaintiff’s efforts to reopen the record to retry its entitlement to recover all [216]*216the costs it incurred prior to March 30, 1976, flies in the face of the prior holding of the Court of Claims that plaintiff was only entitled to recover those costs, if any, it incurred in attempting to comply with the impossible specifications. This holding by the Court of Claims, along with its holdings that the March 30, 1976, agreement represented an accord and satisfaction and that plaintiffs default termination was proper, constitute the “law of the case” and were binding on the Board. Under the “law of the case” doctrine, legal issues previously determined by the same trial court or an appellate court in the same case are binding on the trial court or an administrative board throughout the case. See Northern Helex Co. v. United States, 225 Ct.Cl. 194, 197-202, 634 F.2d 557, 560-562 (1980). See also Gindes v. United States, 740 F.2d 947, 949-950 (Fed.Cir.1984), cert. denied, — U.S.-, 105 S.Ct. 569, 83 L.Ed.2d 509. The prior holdings of the Court of Claims have neither been shown to be clearly erroneous or plainly wrong, Department of Nat. Res. & Cons. of St. Of Montana v. United States, 1 Cl.Ct. 727, 733-734 (1983); nor has plaintiff shown that an exception to application of the doctrine in this case is appropriate, e.g., a change of law, discovery of new evidence, works a manifest injustice. See Northern Helex Co. v. United States, supra. Plaintiffs counsel asserted during oral argument that plaintiff is entitled to relief from the previous judgment of the Court of Claims based on RUSCC 60(b)(6). The court, however, finds no manifest injustice or any other reason in this case to warrant such relief.

The “law of the case” is clearly for application herein. Its application promoted judicial efficiency and prevented the possibility of endless litigation. See Central Soya Company, Inc. v. Geo. A. Hormel & Co. 723 F.2d 1573, 1580 (Fed.Cir.1983). Having concluded that the “law of the case” applies, plaintiffs attack (i.e.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Titan Pacific Construction Corp. v. United States
35 Cont. Cas. Fed. 75,693 (Court of Claims, 1989)
De Graffenried v. United States
14 Cl. Ct. 517 (Court of Claims, 1988)
Fuentes v. United States
14 Cl. Ct. 157 (Court of Claims, 1987)
Gevyn Construction Corp. v. United States
33 Cont. Cas. Fed. 74,851 (Court of Claims, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 73,202, 7 Cl. Ct. 213, 1984 U.S. Claims LEXIS 1229, Counsel Stack Legal Research, https://law.counselstack.com/opinion/laka-tool-stamping-co-v-united-states-cc-1984.