Hancock Electronics Corp. v. Washington Metropolitan Area Transit Authority

81 F.3d 451, 1996 WL 176219
CourtCourt of Appeals for the Fourth Circuit
DecidedApril 16, 1996
Docket95-2159, 95-2920
StatusPublished
Cited by1 cases

This text of 81 F.3d 451 (Hancock Electronics Corp. v. Washington Metropolitan Area Transit Authority) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hancock Electronics Corp. v. Washington Metropolitan Area Transit Authority, 81 F.3d 451, 1996 WL 176219 (4th Cir. 1996).

Opinion

Affirmed by published opinion. Judge NIEMEYER wrote the opinion, in which Chief Judge WILKINSON and Judge RUSSELL joined.

OPINION

NIEMEYER, Circuit Judge:

Hancock Electronics Corporation, a Massachusetts company, filed suit in May 1995 against Washington Metropolitan Area Transit Authority (WMATA) for damages resulting from an alleged breach of contract. The district court dismissed the action without prejudice on the ground that Hancock had failed to exhaust its contractually prescribed administrative remedies. We affirm.

I

WMATA, a quasi-govemmental agency created by an interstate compact and approved by Congress to provide a rapid transit system for the Washington, D.C., metropolitan area, awarded Hancock a contract in spring 1994 to provide replacement braking systems for approximately 300 rail cars. The contract obligated Hancock to design, manufacture, and install the braking systems, which contain both mechanical and electronic components. The contract also required Hancock to demonstrate its contract performance to WMATA through testing and to provide WMATA with certain technical data about the systems.

WMATA contends that it does not possess the equipment or expertise to monitor testing of the systems’ software and, consequently, that it was required to subcontract that function to a third party. Shortly before the scheduled testing of the brake systems in April 1995, WMATA wrote to Hancock, “You are kindly reminded that Hancock Electronics can not [sic] start qualification testing unless the technical documentation requested in the Reference is received and reviewed.” Less than a week later, WMATA again advised Hancock that qualification testing “will not be permitted” until Hancock submits “all technical data including software to WMA-TA” WMATA also demanded Hancock’s permission to provide the technical data to a third party to determine “whether the data is sufficient and complete for a Failure Modes and Effects Analysis.” At WMATA’s request, the third party agreed to enter into a lifetime nondisclosure agreement with Hancock to protect Hancock’s proprietary information, and WMATA’s contracting officer averred in his affidavit that Hancock had consented, during a telephone conversation on April 7, 1995, “to disclose the technical data and software documentation to [the third party] provided that [the third party] entered into a lifetime nondisclosure agreement.”

Hancock, however, responded that its technical data and software are proprietary and that its contract with WMATA does not provide for their disclosure either to WMATA or to a third party. It further claimed that WMATA’s insistence that the data and software be provided before Hancock conducted contractually required qualification testing constituted a breach of their contract. On May 11, 1995, Hancock notified WMATA by letter that WMATA’s breach prevented and excused Hancock’s further performance of the contract and, therefore, that Hancock was treating the contract as terminated. That same day, Hancock filed suit against WMATA in the district court for breach of contract, demanding more than $2 million in damages.

WMATA thereafter informed Hancock that WMATA was terminating the contract pursuant to the contract’s Default Clause, contending that Hancock’s May 11 letter, its lawsuit, its cancellation of a subcontract, and its “failure to deliver the technical data as of June' 15, 1995 ... constitute a repudiation and abandonment of all work under the contract.” WMATA’s contracting officer stated that his decision was a “Final Decision ... appealable under the Disputes Clause of the contract.” WMATA also filed a motion to dismiss Hancock’s complaint on the ground that Hancock had not exhausted its contractually prescribed administrative remedies.

Following a hearing, the district court granted WMATA’s motion to dismiss Han *454 cock’s complaint without prejudice. The court concluded that even if WMATA had breached the contract, the contract’s “termination for convenience” provision limited WMATA’s liability and required Hancock to avail itself of the specified administrative procedures. This appeal followed.

II

The contract between the parties in this case is a standard government contract containing a Disputes Clause, a Default Clause, and a Termination for Convenience Clause. The Disputes Clause states that “[ejxcept as otherwise provided ... any dispute concerning a question of fact arising under this Contract which is not disposed of by agreement shall be decided by the Contracting Officer.” The Clause gives Hancock the right to appeal to WMATA’s Board of Directors or its authorized representative, which in this ease is the Army Corps of Engineers Board of Contract Appeals. Ultimately, decisions resolving factual disputes under the contract are reviewable by the courts under a deferential standard.

The Default Clause permits WMATA to declare the contractor in default and sets forth the procedures that the parties must follow when a default has been declared. If the parties are unable to agree on a resolution, the Clause provides that their disagreement shall constitute “a dispute concerning a question of fact within the meaning of the DISPUTES article of this Contract.”

Finally, the Termination for Convenience Clause confers upon WMATA the option of terminating the contract “whenever the Contracting Officer shall determine that such termination is in the best interest of [WMA-TA].” The Clause provides for a quantum meruit adjustment for performance already rendered by the contractor. Again, any disputes about the parties’ disengagement under the Termination for Convenience Clause are to be resolved according to the Disputes Clause.

Under settled law, whether WMA-TA breaches or wrongfully terminates a contract, the event is treated as a constructive termination under the Termination for Convenience Clause. See, e.g., General Builders Supply Co. v. United States, 187 Ct.Cl. 477, 409 F.2d 246, 249 (1969). The law thus recognizes that, in entering into a contract, the government limits its potential liability to the value of the performance rendered at the time it terminates the contract for convenience. The combination of Termination for Convenience, Default, and Dispute Clauses in Hancock’s contract with WMATA provides in essence that upon WMATA’s default, Hancock is entitled to its quantum meruit performance under the contract but not its anticipated profits. See generally Ralph C. Nash, Jr. & John Cibinic, Jr., Federal Procurement Law 1104, 1124 (3d ed. 1980). The principle is unique to government contracts and well understood by parties entering into such contracts.

Ill

Hancock does not take issue with these generally established tenets of government contract law. Rather, it seeks to invoke an exception that applies when a government agency effects a cardinal change to a government contract, thereby nullifying the contract and denying the government agency the privilege of relying on any of the contract’s dispute resolution provisions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
81 F.3d 451, 1996 WL 176219, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hancock-electronics-corp-v-washington-metropolitan-area-transit-authority-ca4-1996.