SCM Corp. v. United States

645 F.2d 893, 28 Cont. Cas. Fed. 81,113, 227 Ct. Cl. 12, 1981 U.S. Ct. Cl. LEXIS 173
United States Court of Claims·Decided March 11, 1981·No. No. 6-76·Published·Cited by 8 cases

Opinion

PER CURIAM:

OPINION OF THE TRIAL JUDGE*

MILLER, Trial Judge:

Plaintiff seeks review of a decision of the Armed Services Board of Contract Appeals (ASBCA) (78-1 BCA ¶ 13,127) holding that plaintiff is not entitled to reimbursement of its costs under a cost-plus-incentive fee contract with the U. S. Army until plaintiff rescinds its refusal to permit government auditors to make a proper audit of its asserted costs. In so holding the board rejected plaintiffs position that defendant’s auditors may not remove their work papers from plaintiffs premises without plaintiffs permission if they contain any proprietary information (other than cost data), and particularly the names of plaintiffs parts suppliers and the names and compensation of its employees; and that to insure compliance plaintiff has the right to review the work papers each day as the auditors leave the plant.

Contract DAAB07-70-C-0177 was awarded to plaintiffs Kleinschmidt Division1 by the U.S. Army Electronics Command effective April 1, 1970. Phase I of the contract called for the delivery of engineering development/service test models of forward area tactical teletypewriter equipment. After several modifications and supplemental agreements the contract price for Phase I was as follows:

$5,528,352 Target Cost
625,868 Target Profit
6,154,219 Target Price
6,676,145 Ceiling Price

To the extent that plaintiffs cost was below target, it was entitled to share the saving in a 60/40 ratio. To the extent [15] its cost was above target, plaintiff was to share the additional burden in an 80/20 ratio.

On June 26, 1975, plaintiff submitted to the contracting officer a "Contract Pricing Proposal-Price Redetermination” form for the contract period April 1,1970 to June 30, 1973, showing Phase I performance costs of $8,805,068, a sum more than $2,127,923 in excess of the ceiling price. However, on January 21, 1976, after bringing this suit, plaintiff submitted a revised form showing total contract costs for the same period to be $7,730,896, about a million dollars less than the previous claim. Mr. Harry S. Gaples, plaintiffs president, explained the discrepancy as attributable to the fact that the first claim was unaudited by plaintiff.

Shortly after receipt of the first form, the contracting officer requested the Defense Contract Audit Agency (DCAA), Chicago, to perform an audit evaluation of the proposed price. However, when on August 4, 1975, the auditors met with Mr. Gaples, he laid down five rules he expected them to follow in conducting their audit, of which Rules 1 and 5 are:

Rule 1: No proprietary information other than cost data shall be taken out of this building, for example, vendor names.
Rule 5: Kleinschmidt doesn’t want government personnel to take out of the Kleinschmidt plant originals or copies of originals of Kleinschmidt data.

The auditors left the plant, declining to make the audit, on the ground that an adequate audit could not be made under such conditions.

Plaintiff originally brought this suit on January 8, 1976. It alleged that on September 22, 1975, the contracting officer had informed plaintiff that since the contract auditors were not able to conduct the audit under plaintiffs restrictions on the removal of proprietary information from its plant, there was no dispute for him to rule upon and he could make no final decision on plaintiffs claim. However, on January 21, 1976, 2 weeks after the suit was filed, the contracting officer did issue a final decision denying payment for lack of a meaningful audit.

[16] After considerable negotiation, on February 2, 1976, DCAA again sent two auditors to plaintiffs plant, and they commenced their audit. At the end of the following day, Gaples and another Kleinschmidt employee physically blocked the auditors’ leaving until they turned over their work papers to him. Gaples then called the auditors’ supervisor and told him that he had caught the auditors attempting to walk out with Kleinschmidt data. However, it was stipulated at the hearing that such work papers contained no data which plaintiff considers to be proprietary. The auditors did not return.

On February 17, 1976, plaintiff appealed the contracting officer’s decision to the ASBCA.

On March, 8, 1976, defendant moved to dismiss this suit without prejudice for plaintiffs failure to exhaust its administrative remedies, and on April 8, 1976, plaintiff cross-moved for summary judgment. By order filed December 6, 1976, 212 Ct. Cl. 565, the court ruled that the contracting officer’s delay was not so unreasonable as to constitute a breach of contract and thereby to relieve plaintiff of its obligation to exhaust its administrative remedies. Accordingly, the court ordered the case remanded to the ASBCA for further proceedings under the contract.

The board found that because Mr. Gaples did not define "proprietary information” so that the auditors could themselves determine whether particular information was proprietary and because he indicated to them a lack of trust in their work (78-1 BCA, supra, at 64,168)—

the practical effect of rule 1 was to give appellant the power (1) to keep all information in its plant or (2) to review auditors’ work papers to determine what information could be removed from appellant’s plant and this applied to all information an auditor might seek to remove and was not limited to information labeled "proprietary” in advance of the audit. '

This finding is supported by the record. Indeed, Mr. Gaples admitted it to be correct on cross-examination.

Free access — add to your briefcase to read the full text and ask questions with AI

SCM Corp. v. United States, 645 F.2d 893, 28 Cont. Cas. Fed. 81,113, 227 Ct. Cl. 12, 1981 U.S. Ct. Cl. LEXIS 173 (cc 1981).

645 F.2d 893 (SCM Corp. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kelly v. Northeastern Educational Intermediate Unit
36 Pa. D. & C.5th 300 (Lackawanna County Court of Common Pleas, 2014)
BLR Group of America, Inc. v. United States
94 Fed. Cl. 354 (Federal Claims, 2010)
Todd Construction, L.P. v. United States
94 Fed. Cl. 100 (Federal Claims, 2010)
District of Columbia v. Organization for Environmental Growth, Inc.
700 A.2d 185 (District of Columbia Court of Appeals, 1997)
S.J. Amoroso Construction Co., Inc. v. United States
12 F.3d 1072 (Federal Circuit, 1993)
Department of General Services v. Harmans Associates Ltd. Partnership
633 A.2d 939 (Court of Special Appeals of Maryland, 1993)