General Dynamics Corp. v. United States

69 Fed. Cl. 180, 97 A.F.T.R.2d (RIA) 412, 2005 U.S. Claims LEXIS 388
CourtUnited States Court of Federal Claims
DecidedDecember 30, 2005
DocketNo. 01-664 T
StatusPublished

This text of 69 Fed. Cl. 180 (General Dynamics Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Dynamics Corp. v. United States, 69 Fed. Cl. 180, 97 A.F.T.R.2d (RIA) 412, 2005 U.S. Claims LEXIS 388 (uscfc 2005).

Opinion

OPINION

MEROW, Senior Judge.

Plaintiffs, General Dynamics Corporation and Affiliated Corporations (hereinafter [182]*182“General Dynamics”) filed consolidated federal income tax returns for calendar years 1991, 1992, and 1993. After completing the necessary prerequisites by submitting claims to the Internal Revenue Service (hereinafter “IRS”), plaintiffs initiated the instant litigation by filing a four count Complaint. Count I of the Complaint seeks tax refunds of $57,355,541 for 1991, $11,721,580 for 1992, and $7,075,699 for 1993. At issue in the Count I refund claims is the correct time period for reporting gain or loss from plaintiffs’ long-term contract with the Department of the Navy to develop and build the “A-12”, a carrier-based low observable (“Stealth”) attack aircraft. The Navy’s Contracting Officer terminated this 1988 long-term A-12 Contract on January 7, 1991 for plaintiffs’ asserted default. The validity of the default action remains in separate (Docket No. 91-1204 C) active litigation in this court. See McDonnell Douglas Corp. v. United States, 323 F.3d 1006 (Fed.Cir.2003). Here, the parties have each moved for partial summary judgment with respect to Count I of the Complaint, seeking a determination as to whether plaintiffs’ proposed amended reporting of gain or loss on the basis that the A-12 Long-Term Contract was completed in 1991 is sanctioned by the Internal Revenue Code and whether such reporting would require prior approval by the IRS Commissioner as a change in method of accounting.

For the following reasons it is concluded that plaintiffs’ attempted amended reporting of losses attributable to the terminated A-12 Contract on the basis of its completion in 1991 is not sanctioned by the applicable law, but any such reporting, if so sanctioned, would require prior approval by the Commissioner.

FACTS

The parties have stipulated the facts relevant to a ruling on the Count I issues presented and the following is derived therefrom.

In 1984, and for years prior to that, General Dynamics was engaged in the development, manufacturing, and integration of major air combat systems through its Fort Worth Division. Commencing in 1984, the Department of the Navy initiated the A-12 “Advanced Tactical Aircraft Program” and asked four defense contractors to form teams to compete for an A-12 studies contract. McDonnell Douglas Corporation and General Dynamics Corporation agreed to bid as a team and between 1984 and 1988 performed concept formulation and demonstration and validation work pursuant to contracts awarded by the Navy with respect to the A-12 program. In September 1987, the McDonnell Douglas — General Dynamics team submitted a Best and Final Offer, for an A-12 Full Scale Engineering and Development Contract (“FSED Contract”). The A-12 FSED Contract was awarded to the McDonnell Douglas — General Dynamics team by the Navy on January 13, 1988, and provided that each team member “shall be jointly and sev-erably liable for all obligations of this contract.”

The 1988 A-12 FSED Contract was an incrementally funded, fixed-price incentive contract with a ceiling price of $4,777,330,294 and a target price of $4,379,219,436. The contract comprised fifty-eight contract line items identifying tasks to be performed, and required the team to produce eight FSED aircraft. Option provisions in the contract provided for the delivery of production aircraft in four lots, including Lot I (six aircraft) and Lot II (eight aircraft). The Navy exercised the Lot I option on May 31, 1990.

On December 17, 1990, the Navy issued a cure notice to the team, asserting that their failure to meet contract specifications and slippage in the contract schedule were endangering performance of the A-12 FSED Contract. The team was warned that a failure to cure these deficiencies by January 2, 1991 might result in termination of the contract for default. On December 31,1990, the team submitted certified claims to the Navy for equitable adjustments to the A-12 FSED Contract totaling $1,401,181,205. The team also responded to the Navy’s cure notice by a letter dated January 2, 1991. On January 7, 1991, the Navy’s Contracting Officer issued a letter to the team stating that they were in default of the A-12 FSED Contract and that the Government was terminating the contract “... in accordance with FAR Clause [183]*18352.249-8, ‘Default (Fixed-Price Supply and Services)’ and [FAR Clause] 52.249-9, ‘Default (Fixed-Price Research and Development).’ ” The Navy’s letter also stated that, “The Team’s right to proceed further under Contract N00019-88-C-0050 [the A-12 FSED Contract] is terminated immediately upon receipt of this letter.”

Upon receipt of the January 7, 1991 termination letter, the team halted performance of the A-12 FSED Contract. General Dynamics terminated most of its employees who worked on the A-12 program, maintaining a limited number to assist in the close-out effort. The assets of the A-12 program were gathered, inventoried and stored in secured areas to the extent possible. The team sold, returned for credit, transferred to other Government programs or otherwise disposed of the A-12 program assets. Stop work orders were issued to all A-12 program subcontractors and suppliers, and termination settlement proposals were requested from each A-12 subcontractor. General Dynamics informed each A-12 subcontractor and supplier that “a restart of your contract is not anticipated.” General Dynamics subsequently sold substantially all of the assets of its total military aircraft business to Lockheed Corporation, including the facility that had housed the A-12 program effort.

In conjunction with the termination of the A-12 Contract on January 7, 1991, the Government did not obligate $553 million in A-12 FSED funds scheduled for obligation on that date. A-12 production line money (about $30 million) was removed from the fiscal year 1992 budget. The Navy withdrew its on-site employees from the team’s A-12 program facilities and transferred A-12 personnel to a different program. On February 5,1991, the Navy issued a formal demand for the return of unliquidated progress payments, in excess of $1,300,000,000, made to the team during the performance of the A-12 FSED Contract. Contract modifications were issued which “de-obligated” the A-12 FSED Contract funds in the amount of $2,311,525,448.31. A-12 FSED and production appropriations were deleted from the Department of Defense and Congressional Budgets for the Fiscal Year 1992. The Government never re-let the A-12 FSED Contract.

In June of 1991, the team filed suit in this court, Docket No. 91-1204 C, contending that the default termination of the A-12 FSED Contract was not justified. Pursuant to FAR § 52.249-8(g) and FAR § 52.249-9(g), the team sought conversion of the default termination to a termination for the convenience of the Government with the monetary relief provided pursuant to FAR § 52.249-2. The team sought a judgment against the United States in an amount in excess of $1,200,000,000 plus interest. Also, in June of 1991, the team submitted a certified termination for convenience proposal and claim to the Government, using the total cost method, for FSED Lots I and II. In this contract litigation, the Government defends the default termination of the A-12 FSED Contract and asserts that the team owes the Government unliquidated progress payments in an amount in excess of $1,300,000,000 plus interest accrued since the demand letter was sent on February 5, 1991.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
69 Fed. Cl. 180, 97 A.F.T.R.2d (RIA) 412, 2005 U.S. Claims LEXIS 388, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-dynamics-corp-v-united-states-uscfc-2005.