Opinion for the court filed by Circuit Judge WALLACH.
Opinion concurring-in-part and dissenting-in-part filed by Circuit Judge BRYSON.
WALLACH, Circuit Judge.
This case arises under the Contract Disputes Act, 41 U.S.C. §§ 7101-09. The Department of Energy (“DOE”) appeals and Rockwell International Company (“Rockwell”) cross-appeals from decisions of the Civilian Board of Contract Appeals (“Board”) that certain litigation defense costs are allowable under the parties’ management and operating contracts (“contracts”) and thus may be recovered by Rockwell.1 We affirm-in-part and reverse-in-part the Board’s determinations.
BackgRound
A. The Contracts
Beginning in 1975, DOE entered into a series of contracts with Rockwell for the management, operation, and maintenance of the government-owned Rocky Flats Nuclear Weapons Plant in Colorado (“Rocky Flats”). Abraham v. Rockwell Int’l Corp., 326 F.3d 1242, 1244 (Fed.Cir.2003).2 Private industrial firms have managed and operated the facility since its construction in the early 1950s. Id. at 1245. The contracts governing the management and operation of the facility require the Government, not the private firms, to assume almost all operational and financial risks because of the inherent danger in manufacturing nuclear weapon components. Id. Rockwell’s contracts contain cost-reimbursement provisions that enable Rockwell to recover all allowable costs. Id. The [981]*981dispute here centers on whether certain costs incurred by Rockwell in defending itself in litigation are recoverable.
The two contracts currently at issue are the 1986 contract effective from January 1, 1986 until December 31, 1988 and the 1989 contract effective from January 1, 1989 until December 31,1989.3 They were both cost-plus-award-fee contracts. 48 C.F.R. § 16.405-2.4 Both contracts provided that “allowable cost shall not include the cost of any item described as unallowable....”
Effective January 1, 1987, the parties adopted Modification M097, which added clause (e)(32) to the 1986 contract (“clause (e)(32)”), and provided as follows:
(e) Items of Unallowable Costs. The following items of costs are unallowable under this contract to the extent indicated:
(32) Costs incurred in defense of any civil or criminal fraud proceeding or similar proceeding (including filing of any false certification) brought by the Government where the Contractor, its agents or employees, is found liable or has pleaded nolo contendere to a charge of fraud or similar proceeding (including filing of a false certification).
(emphasis added).5
Effective January 1, 1989, the parties adopted Modification M124, which provides:
(d) Items of Allowable Cost. Subject to the other provisions of this clause, the following items of cost of work done under this contract shall be allowable to the extent indicated:
(16) All cost incurred by the Contractor with respect to any and all liabilities, claims, demands, damage costs, or penalties (such as civil sanctions including fines), arising out of, or related to environmental, safety and health activities, including costs incurred with respect to investigation, removal, remedial action, ground and surface water or other clean-up of hazardous, toxic or contaminated material(s), except for those costs that result from conduct identified in subparagraph (e)(17)(ii) of the clause entitled, “Allowable Costs, Base Fee and Award Fee.”
[982]*982(“Environmental Costs Clause”) (emphasis added). Subparagraph (e)(17)(ii) expressly excludes costs that “result from willful misconduct or lack of good faith on the part of any of the Contractor’s managerial personnel.”
B. The Stone Suit
On June 25, 1987, Mr. James Stone6 informed the Federal Bureau of Investigations of alleged environmental crimes that occurred at Rocky Flats; the Department of Justice began investigating in 1988.7
On July 5, 1989, Mr. Stone, instituted a qui tarn, action alleging violations of the FCA against Rockwell in the United States District Court for the District of Colorado. However, on December 20, 1996, the Government and Mr. Stone (collectively, “plaintiffs”) filed a joint amended complaint alleging violations of the FCA (Count 1), common law fraud (Count 2), breach of contract (Count 3), payment by mistake (Count 4), and unjust enrichment (Count 5); Mr. Stone additionally asserted other FCA violations (Count 6). Plaintiffs contended that during certain time periods, Rockwell violated the FCA by using false or fraudulent statements to obtain its award fees and operating costs. Following a jury trial, the district court entered judgment against Rockwell solely for Count 1 for certain time periods. The judgment provided for plaintiffs’ recovery of $4,172,327.40 (three times the jury award), and the Government’s recovery of a civil penalty of $15,000.00. The Tenth Circuit affirmed these awards. United States v. Rockwell Int’l Corp., 282 F.3d 787 (10th Cir.2002).
On April 4, 2006, Rockwell filed a petition for a writ of certiorari. The only issue before the Supreme Court was “whether respondent Mr. Stone was an original source” for purposes of standing to bring suit. Rockwell Int’l Corp. v. United States, 549 U.S. 457, 460, 127 S.Ct. 1397, 167 L.Ed.2d 190 (2007). An “original source” is “an individual who [1] has direct and independent knowledge of the information on which the allegations are based and [2] has voluntarily provided the information to the Government before filing an action under this section which is based on the information.” 31 U.S.C. § 3730(e)(4)(B). This question pertained only to FCA violations involving pond-crete.8 On March 27, 2007, the Court held that Mr. Stone was not an “original source” with respect to FCA violations involving pondcrete. Rockwell, 549 U.S. at 479, 127 S.Ct. 1397. Therefore, the Court found that the district court lacked jurisdiction to enter judgment in favor of Mr. Stone, and reversed the Tenth Circuit’s holding to the contrary. Id.9
[983]*983On June 18, 2007, the Tenth Circuit affirmed the judgment in favor of the Government for the reasons articulated in its prior opinion, United States v. Rockwell Int’l Corp., 282 F.3d 787 (10th Cir.2002), but remanded with directions to vacate the portion of the judgment entered in favor of Mr. Stone and dismiss his portion of the case. United States v. Rockwell Int’l Corp.,
Free access — add to your briefcase to read the full text and ask questions with AI
Opinion for the court filed by Circuit Judge WALLACH.
Opinion concurring-in-part and dissenting-in-part filed by Circuit Judge BRYSON.
WALLACH, Circuit Judge.
This case arises under the Contract Disputes Act, 41 U.S.C. §§ 7101-09. The Department of Energy (“DOE”) appeals and Rockwell International Company (“Rockwell”) cross-appeals from decisions of the Civilian Board of Contract Appeals (“Board”) that certain litigation defense costs are allowable under the parties’ management and operating contracts (“contracts”) and thus may be recovered by Rockwell.1 We affirm-in-part and reverse-in-part the Board’s determinations.
BackgRound
A. The Contracts
Beginning in 1975, DOE entered into a series of contracts with Rockwell for the management, operation, and maintenance of the government-owned Rocky Flats Nuclear Weapons Plant in Colorado (“Rocky Flats”). Abraham v. Rockwell Int’l Corp., 326 F.3d 1242, 1244 (Fed.Cir.2003).2 Private industrial firms have managed and operated the facility since its construction in the early 1950s. Id. at 1245. The contracts governing the management and operation of the facility require the Government, not the private firms, to assume almost all operational and financial risks because of the inherent danger in manufacturing nuclear weapon components. Id. Rockwell’s contracts contain cost-reimbursement provisions that enable Rockwell to recover all allowable costs. Id. The [981]*981dispute here centers on whether certain costs incurred by Rockwell in defending itself in litigation are recoverable.
The two contracts currently at issue are the 1986 contract effective from January 1, 1986 until December 31, 1988 and the 1989 contract effective from January 1, 1989 until December 31,1989.3 They were both cost-plus-award-fee contracts. 48 C.F.R. § 16.405-2.4 Both contracts provided that “allowable cost shall not include the cost of any item described as unallowable....”
Effective January 1, 1987, the parties adopted Modification M097, which added clause (e)(32) to the 1986 contract (“clause (e)(32)”), and provided as follows:
(e) Items of Unallowable Costs. The following items of costs are unallowable under this contract to the extent indicated:
(32) Costs incurred in defense of any civil or criminal fraud proceeding or similar proceeding (including filing of any false certification) brought by the Government where the Contractor, its agents or employees, is found liable or has pleaded nolo contendere to a charge of fraud or similar proceeding (including filing of a false certification).
(emphasis added).5
Effective January 1, 1989, the parties adopted Modification M124, which provides:
(d) Items of Allowable Cost. Subject to the other provisions of this clause, the following items of cost of work done under this contract shall be allowable to the extent indicated:
(16) All cost incurred by the Contractor with respect to any and all liabilities, claims, demands, damage costs, or penalties (such as civil sanctions including fines), arising out of, or related to environmental, safety and health activities, including costs incurred with respect to investigation, removal, remedial action, ground and surface water or other clean-up of hazardous, toxic or contaminated material(s), except for those costs that result from conduct identified in subparagraph (e)(17)(ii) of the clause entitled, “Allowable Costs, Base Fee and Award Fee.”
[982]*982(“Environmental Costs Clause”) (emphasis added). Subparagraph (e)(17)(ii) expressly excludes costs that “result from willful misconduct or lack of good faith on the part of any of the Contractor’s managerial personnel.”
B. The Stone Suit
On June 25, 1987, Mr. James Stone6 informed the Federal Bureau of Investigations of alleged environmental crimes that occurred at Rocky Flats; the Department of Justice began investigating in 1988.7
On July 5, 1989, Mr. Stone, instituted a qui tarn, action alleging violations of the FCA against Rockwell in the United States District Court for the District of Colorado. However, on December 20, 1996, the Government and Mr. Stone (collectively, “plaintiffs”) filed a joint amended complaint alleging violations of the FCA (Count 1), common law fraud (Count 2), breach of contract (Count 3), payment by mistake (Count 4), and unjust enrichment (Count 5); Mr. Stone additionally asserted other FCA violations (Count 6). Plaintiffs contended that during certain time periods, Rockwell violated the FCA by using false or fraudulent statements to obtain its award fees and operating costs. Following a jury trial, the district court entered judgment against Rockwell solely for Count 1 for certain time periods. The judgment provided for plaintiffs’ recovery of $4,172,327.40 (three times the jury award), and the Government’s recovery of a civil penalty of $15,000.00. The Tenth Circuit affirmed these awards. United States v. Rockwell Int’l Corp., 282 F.3d 787 (10th Cir.2002).
On April 4, 2006, Rockwell filed a petition for a writ of certiorari. The only issue before the Supreme Court was “whether respondent Mr. Stone was an original source” for purposes of standing to bring suit. Rockwell Int’l Corp. v. United States, 549 U.S. 457, 460, 127 S.Ct. 1397, 167 L.Ed.2d 190 (2007). An “original source” is “an individual who [1] has direct and independent knowledge of the information on which the allegations are based and [2] has voluntarily provided the information to the Government before filing an action under this section which is based on the information.” 31 U.S.C. § 3730(e)(4)(B). This question pertained only to FCA violations involving pond-crete.8 On March 27, 2007, the Court held that Mr. Stone was not an “original source” with respect to FCA violations involving pondcrete. Rockwell, 549 U.S. at 479, 127 S.Ct. 1397. Therefore, the Court found that the district court lacked jurisdiction to enter judgment in favor of Mr. Stone, and reversed the Tenth Circuit’s holding to the contrary. Id.9
[983]*983On June 18, 2007, the Tenth Circuit affirmed the judgment in favor of the Government for the reasons articulated in its prior opinion, United States v. Rockwell Int’l Corp., 282 F.3d 787 (10th Cir.2002), but remanded with directions to vacate the portion of the judgment entered in favor of Mr. Stone and dismiss his portion of the case. United States v. Rockwell Int’l Corp., 492 F.3d 1157 (10th Cir.2007).
C. Stone Defense Costs
At the beginning of the Stone suit, when Rockwell was served with Mr. Stone’s Complaint on November 13, 1995, Rockwell submitted to DOE vouchers for payment of related defense costs (“Stone defense costs”). On April 22, 1993, DOE stated it would provisionally reimburse Rockwell and “reserve[ ] the right to evaluate the final outcome of the case and seek reimbursement from Rockwell for any amount paid....” A160. After conditionally reimbursing Rockwell $4,060,669.03 in Stone defense costs, DOE notified Rockwell on December 6, 1995, that those costs were unallowable pursuant to the DOE and Rockwell contracts.
In May 2005, Rockwell requested a contracting officer’s final decision, seeking $11,344,081.14 as reimbursement for the Stone defense costs incurred from November 14, 1995, to December 31, 2004. On September 30, 2005, the contracting officer issued a final decision denying Rockwell’s claim. Additionally, the contracting officer rendered a final decision granting the Government’s claim against Rockwell for recovery of $4,060,669.03, the amount that DOE provisionally advanced as reimbursement for Rockwell’s Stone defense costs, plus interest. Rockwell appealed this final decision along with other related later decisions to the Board which were consolidated into various appeals before the Board.
D. Board Decisions
From July 9, 2007 to March 8, 2011, six Board decisions were issued which currently are being challenged by one or both parties.10 The Board considered whether Rockwell’s costs incurred defending Stone were unallowable under clause (e)(32) and held that such costs could be apportioned on a claim-by-claim basis and determined that: (1) costs relating solely to claims where the Government was successful are unallowable; (2) costs relating solely to claims where Rockwell was successful are allowable under clause (e)(32); and (3) costs relating to common costs, i.e., costs incurred defending against both claims where Rockwell was successful and was found liable, are unallowable.
DOE filed a timely appeal. Rockwell cross-appealed. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10).11
[984]*984Discussion
The Board’s factual determinations will be set aside if arbitrary, capricious, so grossly erroneous as to necessarily imply bad faith, or not supported by substantial evidence. 41 U.S.C. § 7107(b)(2). The Board’s determinations of questions of law, including interpretation of contracts, statutes and regulations, are subject to de novo review. Lear Siegler Servs. v. Rumsfeld, 457 F.3d 1262, 1265-66 (Fed. Cir.2006).
We first address the term “proceeding” in clause (e)(32) and this clause’s interaction with the Environmental Costs Clause within the contract. Next, we turn to the Stone defense costs incurred by Rockwell after Mr. Stone filed the now reversed qui tarn action and before the Government intervened. Finally, we turn to the “common costs” incurred by Rockwell in defending against claims during the period of litigation after the Government intervened where Rockwell was successful on some claims but was found liable on others.
A. “Proceeding” in clause (e)(32) and the Environmental Costs Clause
The Stone jury found Rockwell liable on three FCA violations against the Government. Whether Rockwell’s costs of defending this lawsuit are allowable under its contracts with DOE rests in large part on the proper interpretation of two provisions found in those contracts: clause (e)(32) and the Environmental Costs Clause.
We find that a plain reading of clause (e)(32) suggests that the Board’s more limited reading of “proceeding” found within this provision is correct. Read in its entirety, the clause disallows
[cjosts incurred in defense of any civil or criminal fraud proceeding or similar proceeding (including filing of any false certification) brought by the Government where the Contractor, its agents or employees, is found liable or has pleaded nolo contendere to a charge of fraud or similar proceeding (including filing of a false certification).
DOE contends that in “Clause (e)(32), the choice of the word ‘charge,’ which Rockwell agrees means a claim, stands in contrast to the choice of the word ‘proceeding.’ ” Response and Reply Br. of the Secretary of Energy at 8 (internal citation omitted). We disagree. In this context, “charge of fraud” is immediately followed by “or similar proceeding,” illustrative that a “charge of fraud” is a type of “proceeding.” This indicates that a “proceeding” means something less than an entire litigation action as DOE contends. Additionally, “proceeding” is twice followed by “including filing of any false certification,” which again is a claim, not an entire case.12 However, as [985]*985pointed out by the DOE, “proceeding” is also joined to the words “civil” and “criminal,” two types of actions, not two types of claims.13
When construing a contract containing conflicting terms, general rules of interpretation apply. It is a general rule of contract interpretation that terms should not be interpreted so as to render them ineffective or superfluous. Lockheed Martin IR Imaging Sys. v. West, 108 F.3d 319, 322 (Fed.Cir.1997); see also Restatement (Second) of Contracts § 203(a) (“an interpretation which gives a reasonable, lawful, and effective meaning to all the terms is preferred to an interpretation which leaves a part unreasonable, unlawful, or of no effect”). The narrow reading of clause (e)(32) adopted by the Board is necessary to avoid conflict with other provisions of the contract, particularly the Environmental Costs Clause, which clearly provide for reimbursement of costs incurred in defending claims related to environmental, safety, and health activities except in cases of willful misconduct or lack of good faith.
The Environmental Costs Clause states that “all cost incurred ... with respect to any and all liabilities, claims, demands, damage costs, or penalties (including fines), arising out of, or related to environmental, safety and health activities” are allowable for reimbursement. As we have previously stated concerning this clause:
[986]*986The clause refers to “all costs ... with respect to any and all ... penalties (such as civil sanctions including fines), arising out of, or related to environmental ... activities.” Further, it expressly refers to the costs incurred “with respect to investigation.” Tellingly, the clause specifically excludes “costs that result from conduct identified in subpar-agraph (e)(17)(ii).” That subparagraph refers to costs that “result from willful misconduct or lack of good faith on the part of any of the Contractor’s managerial personnel.” The limited nature of this exclusion suggests a broad scope of coverage where, as here, there is no claim of willful misconduct or lack of good faith by managerial personnel.
Abraham, 326 F.3d at 1252-1253.
In Abraham we found that the Environmental Costs Clause prevailed over the Contesting Actions Clause14 in the context of allegations against Rockwell that had not ripened to criminal charges. Id. at 1254. Abraham is informative in this context. As in this case, we were confronted with a conflict between the Environmental Costs Clause and a clause under “Items of Unallowable Costs.” In Abraham, we rejected DOE’s argument that the unallowa-ble costs provision at issue excluded costs allowable under the Environmental Costs Clause because instead of “partially limit[ing] the coverage of the [Environmental Costs Clause],” the Government’s reading “effectively ... rewr[o]te the clause” to render it “entirely inapplicable to all proceedings brought under the federal environmental laws, an area that the clause was explicitly drafted to cover.” 326 F.3d at 1253.
Similarly here, DOE’s interpretation would render the Environmental Costs Clause completely inapplicable to an entire action involving liabilities and claims related to environmental, safety and health activities whenever, as part of that entire action, liability was found for fraud or claims similar to fraud. This is an area the Environmental Costs Clause was explicitly drafted to cover. See A1054-55 (the Environmental Costs Clause covers “any and all liabilities [and] claims ... arising out of, or related to environmental, safety and health activities”). By contrast, there is nothing in the text of clause (e)(32) or elsewhere in the record that indicates clause (e)(32) was explicitly drafted to cover claims related to environmental, safety and health activities or any claims that are not “fraud ... or similar proceeding^]” and where Rockwell was not “found liable.” Indeed, the “proceedings” as articulated in this clause are limited to “fraud” proceedings and therefore renders themselves distinct from other types of proceedings, e.g., those related to environmental claims.
DOE argues at length that there are adequate applicable regulations, statutes, legislative history, and case law to indicate that “proceeding” means “action.” However, these indications do not overcome the expansive language of the Environmental Costs Clause. DOE’s interpretation overlooks the explicitly broad scope of the Environmental Costs Clause and the explicitly narrow limitation of clause (e)(32) to “fraud ... or similar proceeding^]” where the contractor is “found liable.” We therefore affirm the Board’s interpretation of “proceeding.”
[987]*987B. Stone Defense Costs and the Supreme Court
DOE contends that the Board “erred in applying its ‘restrictive’ definition of ‘proceeding’ to Rockwell’s claim for Stone defense costs incurred from the time the suit was filed to the date the Government moved for leave to intervene, and determining such costs ‘could be considered to have been expended in a different and separate suit or proceeding.’ ” Opening Br. of the Secretary of Energy at 51. DOE argues, notwithstanding the findings of the Supreme Court, “[t]here was only one Stone suit.” Id.
Rockwell contends that it does not matter how many suits there were in Stone, only that “as the Board correctly concluded, allowability turns on whether the Government Claim involves costs of defending a ‘fraud ... or similar proceeding’ where Rockwell was ‘found hable.’ ” Br. of Rockwell at 51. Rockwell also contends that the Board was correct in determining that the issues before it were identical and actually litigated in the Supreme Court action, and thus collateral estoppel applied.
Given our interpretation of the applicable contract provisions above, Rockwell is correct that allowability of costs turns on whether the claim involves costs of defending a “fraud ... or similar proceeding” where Rockwell was “found liable.” We find that because the Supreme Court determined that Mr. Stone was not an original source and therefore the district court was unable to properly exercise jurisdiction over his part of the litigation, it follows that Rockwell could not be liable for that part of the litigation. As pointed out by the Board, “the claims where Rockwell was found liable were not even asserted until the amended complaint was filed.” DOE’s argument that the “gravamen of the initial and amended complaints was the same, ie., Rockwell concealed from the Government environmental problems involving unstable pondcrete in order to get claims paid or approved,” may be true, Response and Reply Br. of the Secretary of Energy at 33; however, the contracts require Rockwell be found liable before the costs are disallowed — Rockwell cannot be held hable for costs incurred defending against claims brought by a plaintiff who has no standing. Accordingly, costs incurred prior to the Government’s intervention are allowable reimbursements.
C. Common Defense Costs
With regards to the claims or issues Rockwell both won and lost after the Government’s intervention, ie., the “common costs,” Rockwell argues that “[wjhile the Board correctly concluded that clause (e)(32) does not bar all Stone defense costs, it erred in limiting Rockwell’s recovery.” Br. of Rockwell at 53. Rockwell argues that “the Board had discretion to award Rockwell all its costs.... But the Board found that it lacked the power to do so, or even apportion costs, despite Rockwell’s limited liability in Stone.” Id. at 66.
We agree with Rockwell that the Board has the authority to apportion costs based on Rockwell’s liability in Stone. In Abraham, we noted that
Normally the costs of a database used for more than one purpose should have been apportioned in some manner to reflect both the allowable and unallowa-ble uses. Here, however, the government did not argue for the apportionment of those costs, but rather followed an all or nothing approach, arguing only that these costs be found unallowable in their entirety for the same reasons that it urged that the corporate defense costs were unallowable. Having found that the corporate defense costs are allowable, the database costs are similarly allowable because the government has [988]*988waived its right to argue for apportionment.
Abraham, 326 F.3d at 1255. This language clearly contemplates the ability of the Board, under these contract terms, to apportion costs in certain cases. Additionally, this ability is consistent with our limited construction of the term “proceeding” above. To disallow such costs in every situation where liability for fraud or similar proceeding is found is too broad of a contention, encouraging potential piecemeal litigation, judicial inefficiency, and unfair results.
However, we find that the Stone litigation involved a “common core of facts” and was “based on related legal theories.” See Hensley v. Eckerhart, 461 U.S. 424, 485, 108 S.Ct. 1933, 76 L.Ed.2d 40 (1983). As stated by other circuits, there are circumstances “[w]here several claims arise out of a common factual core or are based on related legal theories, separating out the legal services rendered with respect to these overlapping claims would be an exercise in futility.” Munson v. Milwaukee Bd. of School Directors, 969 F.2d 266, 272 (7th Cir.1992); see also Garrity v. Sununu, 752 F.2d 727, 735 (1st Cir.1984). Here, the Board expressly recognized that the claims at issue were interrelated and based on the same core facts: “Counts 1 through 5 all involved issues relating to pondcrete and sal1> crete.... Those core facts all supported to some degree alleged claims for FCA violations, common law fraud, breach of contract, payment by mistake, and unjust enrichment.” A34. In this case, we find that because there is a common core of facts all relating to the fraud for which Rockwell was found liable, apportionment is inappropriate in this case. See A491-94, Department of Justice’s Amended Complaint.
Conclusion
Because the Board correctly determined that costs relating to claims sounding in fraud where the Government was successful are unallowable and that costs relating to claims where Rockwell was successful are allowable under clause (e)(32), we AFFIRM IN PART. Because we find that the Board had the authority to apportion costs, we REVERSE IN PART. However, apportionment is inappropriate in this case; therefore, it is unnecessary to remand.
AFFIRMED-IN-PART, REVERSED-IN-PART
Costs
No costs.