Lear Siegler Services v. Rumsfeld, Secretary of Defense

457 F.3d 1262, 11 Wage & Hour Cas.2d (BNA) 1273, 180 L.R.R.M. (BNA) 2083, 2006 U.S. App. LEXIS 18932, 2006 WL 2088273
CourtCourt of Appeals for the Federal Circuit
DecidedJuly 28, 2006
Docket2006-1080
StatusPublished
Cited by25 cases

This text of 457 F.3d 1262 (Lear Siegler Services v. Rumsfeld, Secretary of Defense) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lear Siegler Services v. Rumsfeld, Secretary of Defense, 457 F.3d 1262, 11 Wage & Hour Cas.2d (BNA) 1273, 180 L.R.R.M. (BNA) 2083, 2006 U.S. App. LEXIS 18932, 2006 WL 2088273 (Fed. Cir. 2006).

Opinion

GAJARSA, Circuit Judge.

Lear Siegler Services, Inc. (“LSI” or “the contractor”) appeals from the decision of the Armed Services Board of Contract Appeals (“Board”), granting summary judgment to the government and denying summary judgment to LSI. Lear Siegler Servs., Inc., 2005 WL 852139, 2005 ASBCA LEXIS 31, 2005-1 B.C.A. (CCH) P32,937, ASBCA No. 54449, aff'd on reconsideration, 2005 WL 2716494, 2005 ASBCA LEXIS 90, 2005-2 B.C.A. (CCH) P33,110. LSI had claimed that the Price Adjustment Clause (part of the regulatory scheme of the Service Contract Act of 1965) required the government to compensate LSI for increases in the cost of providing its employees with a defined-benefit health plan, as required by the terms of a collective bargaining agreement (“CBA”). See Service Contract Act of 1965, ch. 286, Pub.L. No. 89-286, 79 Stat. 1034 (codified as amended at 41 U.S.C. § 351-358); 48 C.F.R. § 52.222-43 (“Price Adjustment Clause”). LSI timely appealed.

The Board had jurisdiction pursuant to the Contract Disputes Act, 41 U.S.C. § 607(d)(2), and we have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10) and 41 U.S.C. § 607(g)(1)(A). For the reasons discussed below, we hold that the Board erred in granting summary judgment in favor of the government, and it abused its discretion in denying summary judgment to LSI. Accordingly, we reverse.

*1265 I. BACKGROUND

The Air Force awarded a firm, fixed price contract to LSI, under which LSI was to provide aircraft maintenance services at Sheppard Air Force Base, Texas. The base year of the contract ran from October 2001 to October 2002, with multiple renewal options thereafter. LSI’s predecessor contractor was Lockheed Martin.

LSI’s contract incorporated the terms of the Service Contract Act (“SCA”), which serves generally to protect the wages and fringe benefits of service workers. The contract included both a SCA wage/benefit determination, which incorporated the wages and fringe benefits set forth in the CBA between the Air Force and Lockheed’s predecessor, and a Price Adjustment Clause, which required the government to pay LSI for “increased] ... in applicable ... fringe benefits ... made to comply with ... [the] wage determination ....” 48 C.F.R. § 52.222-43.

LSI’s CBA specifically required it to provide its employees with a defined-benefit health plan. As distinct from a defined-contribution plan, a defined-benefit plan obligates an employer to spend whatever is necessary to continue to provide its employees with an agreed-upon level of benefit. A defined-benefit plan thez’eby ensures that employees will continue to receive the same level of benefit (here health coverage), even as costs rise. Although the future costs of providing benefits under a defined-benefit plan are not known with certainty at the time of contracting, such costs may reasonably be projected on the basis of actuarial determinations.

In February, 2003, LSI submitted a request for a price adjustment under the SCA Price Adjustment Clause for Option Year 2003, seeking reimbursement for the increased costs of providing its employees with the defined-benefit health plan. The Air Force denied the request, and LSI appealed to the Board. The Board distinguished between increases in an employer’s costs of providing benefits, which it deemed insufficient to trigger the Price Adjustment Clause, and increases in the benefits themselves. See 48 C.F.R. § 52.222-43(d) (requiring “increase[s] ... in applicable ... fringe benefits ... ”).

Observing that there had been no “change in the CBA ... [or the] scope of benefits to be provided,” it concluded that the CBA-based wage determination did not require LSI to incur the increased cost of maintaining the defined level of health benefit, and that the Price Adjustment Clause was therefore inapplicable. Accordingly, the Board granted summary judgment in favor of the Air Force and denied LSI’s request for the same. The Board also rejected LSI’s course-of-dealing argument, holding that a course of dealing cannot alter the meaning of an unambiguous contract term. LSI timely appealed to this court, and we have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10) and 41 U.S.C. § 607(g)(1)(A).

II. DISCUSSION

The principal issue on appeal is whether the Board erred in its construction of the Price Adjustment Clause. For the reasons discussed below, we conclude that it did commit legal error in its determination, and we reverse the judgment of the Board without needing to reach the merits of LSI’s other arguments.

A. Standard of Review

This case requires us to review the Board’s construction of the Price Adjustment Clause. Our standard of review is governed by the Contracts Disputes Act, which provides that “the decision of the agency board on any question of law shall not be final or conclusive ....” 41 U.S.C. *1266 § 609(b). Statutory and regulatory constructions are questions of law, which we review de novo. The interpretation of a government contract is also question of law, which we review de novo on appeal. Forman v. United States, 329 F.3d 837, 841 (Fed.Cir.2003). Nonetheless, we give the Board’s legal conclusions “careful consideration due to the board’s considerable experience in construing government contracts.” Wickham Contracting Co. v. Fischer, 12 F.3d 1574, 1577 (Fed.Cir.1994). See also Titan Corp. v. West, 129 F.3d 1479, 1481 (Fed.Cir.1997) (“The Board’s interpretation of a contract is not final, and is subject to de novo review on appeal, although due respect is often warranted by the Board’s experience in interpreting the Federal Acquisition Regulations (FAR).”); Erickson Air Crane Co. v. United States, 731 F.2d 810, 814 (Fed.Cir.1984) (“[Ljegal interpretations by tribunals having expertise are helpful to us, even if not compelling.”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

HD Inc.
Armed Services Board of Contract Appeals, 2025
BAE Systems Technology Solutions & Services Inc.
Armed Services Board of Contract Appeals, 2024
Amentum Services, Inc.
Armed Services Board of Contract Appeals, 2024
Innovative Technologies, Inc.
Armed Services Board of Contract Appeals, 2023
Northrop Grumman Corporation
Armed Services Board of Contract Appeals, 2023
Dynamic Systems Technology, Inc.
Armed Services Board of Contract Appeals, 2023
cooper/ports America, LLC v. Secretary of Defense
959 F.3d 1373 (Federal Circuit, 2020)
Alutiiq Commercial Enterprises, LLC
Armed Services Board of Contract Appeals, 2020
Fluor Federal Solutions, LLC
Armed Services Board of Contract Appeals, 2019
KiewitPhelps
Armed Services Board of Contract Appeals, 2019
Call Henry, Inc. v. United States
855 F.3d 1348 (Federal Circuit, 2017)
Government Contracting Resources, Inc.
Armed Services Board of Contract Appeals, 2015
Em Logging v. Department of Agriculture
778 F.3d 1026 (Federal Circuit, 2015)
Sec. Of Energy v. The Boeing Co.
497 F. App'x 978 (Federal Circuit, 2012)
Arctic Slope Native Ass'n, Ltd. v. Sebelius
629 F.3d 1296 (Federal Circuit, 2010)
Gates v. Raytheon Co.
584 F.3d 1062 (Federal Circuit, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
457 F.3d 1262, 11 Wage & Hour Cas.2d (BNA) 1273, 180 L.R.R.M. (BNA) 2083, 2006 U.S. App. LEXIS 18932, 2006 WL 2088273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lear-siegler-services-v-rumsfeld-secretary-of-defense-cafc-2006.