Gates v. Raytheon Co.

584 F.3d 1062, 2009 U.S. App. LEXIS 20382, 2009 WL 2914340
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 14, 2009
Docket2008-1543
StatusPublished
Cited by24 cases

This text of 584 F.3d 1062 (Gates v. Raytheon Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gates v. Raytheon Co., 584 F.3d 1062, 2009 U.S. App. LEXIS 20382, 2009 WL 2914340 (Fed. Cir. 2009).

Opinion

GAJARSA, Circuit Judge.

The issue before the court is whether Raytheon Co. was required to pay interest to the Government for a potential violation of Cost Accounting Standard 413 (“CAS 413”), 48 C.F.R. § 9904.413. The Government appeals from a decision of the Armed Services Board of Contract Appeals (“Board”), which held on summary judg *1064 ment that Raytheon’s potential violation of CAS 413 had not caused the Government to pay increased costs and therefore did not require Raytheon to pay interest on certain money it owed the Government. Because Raytheon’s failure to pay the Government in the accounting period required by CAS 413 necessarily resulted in increased costs to the Government, we reverse and remand.

BACKGROUND

This appeal relates to certain contracts between Raytheon and the Government. 1 These contracts are subject to certain Cost Accounting Standards (“CAS”), which provide uniformity in how contractors measure, assign, and allocate costs to Government contracts. 2 See 48 C.F.R. § 9901.302(b). If the contractor does not follow the relevant CAS and consequently overcharges the Government, the contract price must be adjusted. To implement these adjustments, contracts subject to the CAS include a clause that provides:

[T]he Contractor, in connection with this contract, shall ... (5) [ajgree to an adjustment of the contract price or cost allowance, as appropriate, if the Contractor ... fails to comply with an applicable Cost Accounting Standard ... and such failure results in any increased costs paid by the United States. Such adjustment shall provide for recovery of the increased costs to the United States, together with interest thereon computed at the annual rate established under section 6621 of the Internal Revenue Code of 1986 (26 U.S.C. 6621) for such period, from the time the payment by the United States was made to the time the adjustment is effected....

48 C.F.R. § 52.230-2(a) (the “CAS clause”).

One type of cost that was allocable to the contracts at issue related to Ray-theon’s defined-benefit pension plans for its employees. See 48 C.F.R. § 9904.412-40(d); 48 C.F.R. § 9904.413-40(c). Defined-benefit plans guarantee fixed payments to retired employees, leaving the company responsible for ensuring that sufficient funds will be available. Companies therefore must make assumptions regarding, inter alia, the amount of money they expect to pay in the future, and the expected performance of the investments held by their pension plans. Based on these assumptions, companies determine how much money to invest in the plan in a given period so that future liabilities will be met. Because these contributions to the pension fund are part of the cost of doing business with the contractor, in the case of cost-type contracts they are paid, in part, by the Government. 48 C.F.R. § 3.205 — 6(j); see also Allegheny Teledyne, Inc. v. United States, 316 F.3d 1366, 1370 (Fed.Cir.2003).

The CAS provide rules for the appropriate determination of pension costs alloca-ble to a particular business segment and to individual contracts within that segment. See 48 C.F.R. § 9904.412-40(d); 48 C.F.R. *1065 § 9904.413-40(c). 3 The CAS also provide that when a business segment is closed, 4 the contractor must calculate both the market value of the assets in the pension plan allocated to the segment and the actuarial accrued liability for the segment. 48 C.F.R. § 9904.413-50(c)(12). The difference between the plan’s assets and liabilities indicates the amount by which the plan is over- or under-funded. 5 CAS 413-50(c)(12)(vi) provides a method for calculating the Government’s “share” of this difference, and subsection (vii) provides that the “full amount of the Government’s share of an adjustment is allocable, without limit, as a credit or charge during the cost accounting period in which the event occurred and contract prices/costs will be adjusted accordingly.” CAS 413-50(c)(12)(vii). Thus, if the plan is over-funded, the contractor will owe the Government money in the form of a price adjustment, referred to as a “segment closing adjustment.”

Here, Raytheon sold two of its business segments that had performed work on CAS-covered Government contracts. In 1998, Raytheon sold Montek Aerospace to Moog Inc., but retained all of the pension assets and actuarial liabilities. It is undisputed that this constituted a segment closing. Approximately two years later, Ray-theon informed the Government that it had calculated a pension surplus as of the date of the segment closing. The contracting officer asked Raytheon to calculate the Government’s share of the surplus (i.e., the segment closing adjustment). After several years of calculations, re-calculations, and disputes, Raytheon eventually agreed that the Government’s share was $487,305. On August 30, 2004, the Government then requested that Raytheon pay the adjustment. Because CAS 413-50(c)(12)(vii) refers to an adjustment in the period of the segment closing, the Government viewed the debt as due in 1998, and therefore also demanded simple interest on the amount due dating back to the initial segment closing. On September 21, 2004, Raytheon submitted a check for the segment closing adjustment, but refused to pay interest.

In 2000, Raytheon sold Raytheon Engineers and Constructors (“REC”) to Washington Group International, but retained the pension assets and liabilities. This sale also constituted a segment closing. Raytheon informed the Government that there was a pension surplus, and calculated the Government’s share at $4,935,197. The parties disputed the appropriate amount of this share for some time, and eventually settled on a Government share of $14,681,268. On August 31, 2004, the Government requested payment of the calculated adjustment, as well as simple interest on that amount dating back to the segment closing. On September 21, 2004, Raytheon submitted a check for the segment closing adjustment, but refused to pay interest.

The dispute here stems from Raytheon’s failure to pay interest on the amounts owed under CAS 413 — 50(c)(12) for the period between the segment closing and the date of payment. The contracting officer

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flightsafety International Inc. v. Air Force
130 F.4th 926 (Federal Circuit, 2025)
Northrop Grumman Corporation
Armed Services Board of Contract Appeals, 2023
Electric Boat Corporation v. Secretary of the Navy
958 F.3d 1372 (Federal Circuit, 2020)
Allison Transmission, Inc.
Armed Services Board of Contract Appeals, 2014
Raytheon Company v. United States
747 F.3d 1341 (Federal Circuit, 2014)
General Motors Corporation v. United States
112 Fed. Cl. 608 (Federal Claims, 2013)
General Electric Company v. United States
112 Fed. Cl. 1 (Federal Claims, 2013)
Unisys Corporation v. United States
111 Fed. Cl. 191 (Federal Claims, 2013)
Directv Group, Inc. v. United States
670 F.3d 1370 (Federal Circuit, 2012)
Gates v. Raytheon Co.
636 F.3d 1363 (Federal Circuit, 2011)
Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
Raytheon Co. v. United States
92 Fed. Cl. 549 (Federal Claims, 2010)
Wood v. United States
91 Fed. Cl. 569 (Federal Claims, 2009)
DIRECTV Group, Inc. v. United States
89 Fed. Cl. 302 (Federal Claims, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
584 F.3d 1062, 2009 U.S. App. LEXIS 20382, 2009 WL 2914340, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gates-v-raytheon-co-cafc-2009.