William J. Perry, Secretary of Defense v. Martin Marietta Corporation

47 F.3d 1134, 40 Cont. Cas. Fed. 76,748, 1995 U.S. App. LEXIS 2485, 1995 WL 54028
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 10, 1995
Docket93-1164
StatusPublished
Cited by38 cases

This text of 47 F.3d 1134 (William J. Perry, Secretary of Defense v. Martin Marietta Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
William J. Perry, Secretary of Defense v. Martin Marietta Corporation, 47 F.3d 1134, 40 Cont. Cas. Fed. 76,748, 1995 U.S. App. LEXIS 2485, 1995 WL 54028 (Fed. Cir. 1995).

Opinion

ARCHER, Chief Judge.

The Secretary of Defense appeals the decision of the Armed Services Board of Contract Appeals (board), ASBCA Nos. 38,920 and 41,565, 92-3 BCA ¶ 25,175 (1992), holding that Martin Marietta Corporation’s (MMC) 1986 internal corporate reorganizations did not result in a change in cost accounting practices, other than those already reported and disclosed by MMC, under the terms of its cost-type contracts. We affirm.

DISCUSSION

I.

A. MMC is a large, diversified company with many government contracts. Among these are cost-type contracts subject to the Cost Accounting Standards (CAS), a set of accounting standards for government contracts promulgated by the Cost Accounting Standards Board (CASB). See 4 C.F.R. § 301.2 (1992). 1 These standards are incorporated into the Federal Acquisition Regulation (FAR), which in turn provide for the inclusion of appropriate contract clauses in government contracts. 2 One of these contract clauses requires a contractor to provide the government with notice of any changes in cost accounting practices. See FAR 52.230-3. Such notice must include a cost impact proposal. See FAR 52.230^1. This allows an adjustment to be made to the contract if the change in accounting practice results in an increase in cost to the government.

In this case, the Secretary claims that certain organizational changes made by ’MMC as a result of its internal corporate reorganizations in 1986 resulted in a change to a cost accounting practice within the meaning of the CAS and FAR. See FAR 52.230-3. The Secretary contends these changes required MMC to file a cost impact proposal that could result in an adjustment being made to at least some of MMC’s CAS-covered contracts.

B. In the early 1980s, MMC was structured so that there were three intermediate home offices that reported to its corporate headquarters. One of these home offices, Aerospace Headquarters (ASH), was responsible for MMC’s government contract work and had five business segments that reported to it. Three of the segments (Baltimore, Orlando, and Michoud) performed aerospace work, one segment (Air Traffic Control) performed information and communications systems work, and one segment (Denver Aerospace) performed both. The indirect expenses incurred by ASH and its segments were collected and grouped in three different cost pools (marketing, foreign marketing, and residual) at ASH. These indirect expenses were then proportionally allocated (by sales, foreign sales, and total cost input) to the five business segments and, in turn, to the various government contracts that the segments were performing.

*1136 In January 1986, MMC underwent internal corporate reorganizations. MMC abolished ASH and realigned the segments that had previously reported to it. Some of the segments were realigned to report directly to MMC corporate headquarters. Others were assigned to a newly created intermediate home office, Information & Communications Systems Headquarters (I & CSH). The segments reporting to corporate headquarters included the Baltimore, Orlando, and Mi-choud aerospace businesses and the aerospace business portion of Denver Aerospace. The new I & CSH segments included Air Traffic Control and the information and communications business portion of Denver Aerospace.

After this reorganization the indirect expenses previously accumulated in the three pools at ASH were split among the pools at the corporate headquarters and at the I & CSH. The former ASH indirect costs related to aerospace functions were accumulated in the marketing, foreign marketing and residual pools at corporate headquarters, and the former share of ASH indirect expenses related to the segments transferred to I & CSH were accumulated in its marketing and residual pools.

MMC filed a cost impact proposal as a result of the reorganizations, disclosing that it had made certain changes in its accounting practices within the meaning of its contract clauses concerning the CAS. 3 These changes involved how costs were allocated from the cost pools to the segment bases. Costs that had been previously allocated from the pools on the basis of a single factor such as “sales” or “total cost input” were now to be allocated on the basis of a three factor formula. MMC did not include as an accounting practice change any changes in the grouping of indirect costs or business segments resulting from the reorganization. The submitted proposal was audited by the Defense Contract Audit Agency (DCAA) which determined the cost impact to the government was insignificant and that no contract adjustment was necessary.

C. The transfer of the management function for information and communication systems from ASH to I & CSH resulted in an increased allocation of cost to a Federal Aviation Administration (FAA) contract that was being performed by a business segment under I & CSH. The FAA contracting officer decided the reorganization itself effected a change in cost accounting practices which required MMC to submit a cost impact proposal and required an adjustment to the FAA contract. The FAA contracting officer, therefore, did not allow reimbursement of the increased cost allocated from I & CSH pools to the FAA contract. 4

Believing that the FAA contracting officer was not the cognizant contracting officer, MMC requested a decision from the Department of Defense (DOD) contracting officer. When the DOD contracting officer failed to issue a decision within 60 days, MMC appealed the deemed denial of its claim to the board on May 30, 1989 (ASBCA No. 38,920). After the appeal to the board, the DOD contracting officer issued a decision finding that MMC’s reorganization did result in changes in accounting practices based on changes in home office cost and segment groupings and required submission of a new cost impact proposal. MMC also appealed this decision to the board (ASBCA No. 41,-565).

The board rendered a decision in favor of MMC in the two consolidated appeals. The board distinguished between “changes in cost and segment. groupings (organizational changes)” and “changes in the proportional allocation method (accounting method changes).” It held that the organizational changes, which occurred as a result of MMC’s reorganizations, did not constitute changes to an accounting practice. The Secretary has appealed.

*1137 II.

This ease requires the interpretation of two FAR provisions, FAR 52.230-3 and 52.230-4, which were incorporated into MMC’s CAS-eovered contracts. 5 These FAR provisions were intended to implement the CAS, the CAS being the source for the language and authority for these provisions of the FAR. Thus our task in interpreting the meaning of these FAR provisions is ultimately to ascertain the CASB’s intended meaning when it promulgated the CAS.

Our standard of review in this case is dictated by the Contract Disputes Act of 1978 (CDA).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

IAP Worldwide Services, Inc.
Armed Services Board of Contract Appeals, 2026
Parsons Government Services, Inc.
Armed Services Board of Contract Appeals, 2025
Nothrop Grumman Corporation
Armed Services Board of Contract Appeals, 2020
Exelis, Inc.
Armed Services Board of Contract Appeals, 2016
Sikorsky Aircraft Corporation v. United States
773 F.3d 1315 (Federal Circuit, 2014)
General Motors Corporation v. United States
112 Fed. Cl. 608 (Federal Claims, 2013)
General Electric Company v. United States
112 Fed. Cl. 1 (Federal Claims, 2013)
Unisys Corporation v. United States
111 Fed. Cl. 191 (Federal Claims, 2013)
Sikorsky Aircraft Corp. v. United States
102 Fed. Cl. 38 (Federal Claims, 2011)
Raytheon Co. v. United States
92 Fed. Cl. 549 (Federal Claims, 2010)
CBS Corp. v. United States
90 Fed. Cl. 456 (Federal Claims, 2009)
Gates v. Raytheon Co.
584 F.3d 1062 (Federal Circuit, 2009)
General Electric Co. v. United States
84 Fed. Cl. 566 (Federal Claims, 2008)
Dorsey v. United States Secretary of Agriculture
32 Ct. Int'l Trade 785 (Court of International Trade, 2008)
General Motors Corp. v. United States
78 Fed. Cl. 336 (Federal Claims, 2007)
AT & T Corp. v. United States
76 Fed. Cl. 297 (Federal Claims, 2007)
Viacom, Inc. v. United States
70 Fed. Cl. 649 (Federal Claims, 2006)
Lockheed Martin Corp. v. United States
70 Fed. Cl. 745 (Federal Claims, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
47 F.3d 1134, 40 Cont. Cas. Fed. 76,748, 1995 U.S. App. LEXIS 2485, 1995 WL 54028, Counsel Stack Legal Research, https://law.counselstack.com/opinion/william-j-perry-secretary-of-defense-v-martin-marietta-corporation-cafc-1995.