Gsc Construction, Inc. v. Secretary of the Army

Court of Appeals for the Federal Circuit·Decided May 2, 2022·No. 21-1803·Unpublished

Opinion

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit

GSC CONSTRUCTION, INC.,

Appellant

v.

SECRETARY OF THE ARMY,

Appellee

2021-1803

Appeal from the Armed Services Board of Contract Appeals in Nos. 59402, 59601, Administrative Judge John J. Thrasher, Administrative Judge Michael N. O'Connell, Administrative Judge Timothy Paul McIlmail.

Decided: May 2, 2022

PATRICK BERNARD KERNAN, Kernan and Associates Law Group, Washington, DC, argued for appellant.

ASHLEY AKERS, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington , DC, argued for appellee. Also represented by, BRIAN M. BOYNTON, WILLIAM JAMES GRIMALDI, MARTIN F. HOCKEY, JR., PATRICIA M. MCCARTHY; LAUREN M.

2 GSC CONSTRUCTION, INC. v. SECRETARY OF THE ARMY

WILLIAMS, Office of Counsel, United States Army Corps of Engineers, Tulsa, OK.

Before LOURIE, PROST, and CHEN, Circuit Judges.

LOURIE, Circuit Judge.

GSC Construction, Inc. contracted with the United States Army Corps of Engineers (“the Army”) to build two warehouses. After GSC failed to meet several deadlines, the Army terminated the contract for default. GSC appealed to the Armed Services Board of Contract Appeals (“the Board”). The Board denied GSC’s appeal. Appeals of GSC Constr., Inc., ASBCA Nos. 59402, 59601, 21-1 B.C.A. (CCH) ¶ 37751 (A.S.B.C.A. Nov. 24, 2020), J.A. 1–80 (“Decision ”). We affirm the Board’s decision for the reasons explained below.

BACKGROUND

GSC is a contractor that specializes in building military structures. See Appellant’s Br. 3–4. In 2011, the Army awarded GSC a contract to build two warehouses (“the SSA Warehouses”). Decision, slip op. at 2. Under the contract, GSC was required to start construction on September 26, 2012, and finish by February 3, 2014. Id.

After beginning construction, GSC encountered several obstacles that prevented it from completing the project. Two of those obstacles are particularly relevant to this appeal .

First, GSC began a dispute with the Army over the contract ’s scope. The dispute occurred when GSC selected a “waffle mat” foundation, which required removal of existing soil and replacement with “select fill.” Id., slip op. at 6. Despite selecting a waffle mat foundation, GSC did not remove and replace the soil; in its view, another contractor— Harper Construction, Inc.—was responsible for that task. Id., slip op. at 7. At that time, Harper was working on a

GSC CONSTRUCTION, INC. v. SECRETARY OF THE ARMY 3

separate project (“the TEMF Project”) in the same location. For the TEMF Project, Harper was required to demolish and construct several other buildings. Id., slip op. at 4. To ensure proper coordination between the two projects, the Army provided GSC with the contract specifications for the TEMF project “for information” purposes only. Id., slip op. at 6–7; J.A. 4194.

After several months of discussion, the contracting officer formally directed GSC to remove and replace the soil, explaining that it was not Harper’s responsibility. Decision , slip op. at 8. In support of his determination, the contracting officer pointed to § 6.3.1.1(e) of GSC’s contract, which provides that GSC is “responsible for any specific site preparation required to accommodate the foundation design.” Id., slip op. at 5–8; J.A. 5202. In response, GSC agreed to begin the work under protest. Once GSC began excavating, however, it found the soil to be “heavy” and “very wet,” which would require it to perform additional, specialized work. Decision, slip op. at 8. Ultimately, Harper , which had specialized equipment to address that issue, stepped in to remove and replace the soil. Id.

Second, GSC encountered issues when designing the cold-formed metal framing for the exterior walls. To design that framing, GSC was required to comply with the Unified Facilities Criteria (“UFC”) 4-010-01, which establish the “[Department of Defense] Minimum Antiterrorism Standards for Buildings.” Id., slip op. at 12. As relevant here, there are different versions of the UFC: the 2007 version and the 2012 version. The 2012 UFC is more stringent than the 2007 UFC. Id., slip op. at 13. The Army notified GSC that it should design the framing in accordance with the 2007 UFC. Id. Despite that guidance, GSC mistakenly used the more stringent 2012 UFC when creating its shop drawings for the framing. Id. GSC’s quality control manager did not notice that mistake. Id. GSC then submitted its drawings to the Army. Id. The Army also did not detect GSC’s mistake. Rather, it observed that GSC prepared the 4 GSC CONSTRUCTION, INC. v. SECRETARY OF THE ARMY

drawings using the 2012 UFC and reviewed them under that standard. Id. Subsequently, the Army rejected several of GSC’s drawings for failing to meet the 2012 UFC. Id. Both parties agree that, had the Army caught GSC’s mistake and applied the less stringent 2007 UFC, it would have approved the drawings weeks earlier. Id.

Because of the soil dispute and the UFC oversight, GSC fell significantly behind schedule. Accordingly, on January 16, 2014, the contracting officer issued a notice to GSC stating that GSC was 145 days behind schedule and that the Army was considering terminating the contract for default . J.A. 8408. The notice also stated that the Army did not “condone any delinquency” or “waive any rights [it] has under the contract.” Id. GSC responded that it was “confident ” that it could complete the project by June 9, 2014. J.A. 8404. GSC, however, continued to fall behind schedule . As a result, on April 28, 2014, the contracting officer issued a second notice, again stating that GSC had failed to make sufficient progress, that the Army was considering terminating the contract, and that the Army does not forfeit any rights under the contract. J.A. 8398–99. GSC, in turn, responded that it “firmly believe[d]” it could complete the work by August 30, 2014. J.A. 8389. But again, GSC continued to fall behind schedule. Finally, on June 18, 2014, the contracting officer terminated GSC’s contract with the Army for default. Decision, slip op. at 3.

GSC appealed the contracting officer’s decision to the Board. According to GSC, it was entitled to a 321-day extension because of the soil removal dispute and the UFC oversight (among other allegedly excusable delays). Id. GSC also argued that it was entitled to $328,293.82 in damages and a conversion of the termination for default to one for the “convenience of the government.” Id.

The Board denied GSC’s appeal from the contracting officer’s decision. First, the Board held that the Army had met its initial burden of proving that the termination for

GSC CONSTRUCTION, INC. v. SECRETARY OF THE ARMY 5

default was justified. Id., slip op. at 24. The Board noted that the contract’s completion date was February 3, 2014, and that GSC, indisputably, “did not complete the work” by that date. Id., slip op. at 2, 24.

Next, the Board held that GSC failed to show it was entitled to a 321-day extension as a result of the delays. With respect to the soil removal dispute, the Board determined that, under the contract, GSC was required to perform the work rather than Harper. Id., slip op. at 25–27. In particular, the Board pointed to § 6.3.1.1(e) of the contract , which states that GSC is “responsible for any specific site preparation required to accommodate the foundation design.” Id., slip op. at 5, 25; J.A. 5202. With respect to the UFC version oversight, the Board found that, under the contract, it was GSC’s responsibility to ensure that it used the correct UFC version. Id., slip op. at 27–28. In support of its determination, the Board pointed to § 1.7 of the contract , which states that GSC “shall be responsible for . . . the coordination of all designs.” Id., slip op. at 28; J.A. 3349.

Free access — add to your briefcase to read the full text and ask questions with AI

Gsc Construction, Inc. v. Secretary of the Army, (Fed. Cir. 2022).

Gsc Construction, Inc. v. Secretary of the Army (Gsc Construction, Inc. v. Secretary of the Army) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Gates v. Raytheon Co.
584 F.3d 1062 (Federal Circuit, 2009)
LAI Services, Inc. v. Gates
573 F.3d 1306 (Federal Circuit, 2009)
Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Hercules Incorporated v. United States
292 F.3d 1378 (Federal Circuit, 2002)
Wallace Forman v. United States
329 F.3d 837 (Federal Circuit, 2003)
Laguna Construction Company v. Defense
828 F.3d 1364 (Federal Circuit, 2016)
Securiforce International America, LLC v. United States
879 F.3d 1354 (Federal Circuit, 2018)
Electric Boat Corporation v. Secretary of the Navy
958 F.3d 1372 (Federal Circuit, 2020)
Kellogg Brown & Root Services v. Secretary of the Army
973 F.3d 1366 (Federal Circuit, 2020)