Gsc Construction, Inc. v. Secretary of the Army

CourtCourt of Appeals for the Federal Circuit
DecidedMay 2, 2022
Docket21-1803
StatusUnpublished

This text of Gsc Construction, Inc. v. Secretary of the Army (Gsc Construction, Inc. v. Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gsc Construction, Inc. v. Secretary of the Army, (Fed. Cir. 2022).

Opinion

Case: 21-1803 Document: 50 Page: 1 Filed: 05/02/2022

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit ______________________

GSC CONSTRUCTION, INC., Appellant

v.

SECRETARY OF THE ARMY, Appellee ______________________

2021-1803 ______________________

Appeal from the Armed Services Board of Contract Ap- peals in Nos. 59402, 59601, Administrative Judge John J. Thrasher, Administrative Judge Michael N. O'Connell, Ad- ministrative Judge Timothy Paul McIlmail. ______________________

Decided: May 2, 2022 ______________________

PATRICK BERNARD KERNAN, Kernan and Associates Law Group, Washington, DC, argued for appellant.

ASHLEY AKERS, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washing- ton, DC, argued for appellee. Also represented by, BRIAN M. BOYNTON, WILLIAM JAMES GRIMALDI, MARTIN F. HOCKEY, JR., PATRICIA M. MCCARTHY; LAUREN M. Case: 21-1803 Document: 50 Page: 2 Filed: 05/02/2022

WILLIAMS, Office of Counsel, United States Army Corps of Engineers, Tulsa, OK. ______________________

Before LOURIE, PROST, and CHEN, Circuit Judges. LOURIE, Circuit Judge. GSC Construction, Inc. contracted with the United States Army Corps of Engineers (“the Army”) to build two warehouses. After GSC failed to meet several deadlines, the Army terminated the contract for default. GSC ap- pealed to the Armed Services Board of Contract Appeals (“the Board”). The Board denied GSC’s appeal. Appeals of GSC Constr., Inc., ASBCA Nos. 59402, 59601, 21-1 B.C.A. (CCH) ¶ 37751 (A.S.B.C.A. Nov. 24, 2020), J.A. 1–80 (“De- cision”). We affirm the Board’s decision for the reasons ex- plained below. BACKGROUND GSC is a contractor that specializes in building mili- tary structures. See Appellant’s Br. 3–4. In 2011, the Army awarded GSC a contract to build two warehouses (“the SSA Warehouses”). Decision, slip op. at 2. Under the contract, GSC was required to start construction on Sep- tember 26, 2012, and finish by February 3, 2014. Id. After beginning construction, GSC encountered several obstacles that prevented it from completing the project. Two of those obstacles are particularly relevant to this ap- peal. First, GSC began a dispute with the Army over the con- tract’s scope. The dispute occurred when GSC selected a “waffle mat” foundation, which required removal of exist- ing soil and replacement with “select fill.” Id., slip op. at 6. Despite selecting a waffle mat foundation, GSC did not re- move and replace the soil; in its view, another contractor— Harper Construction, Inc.—was responsible for that task. Id., slip op. at 7. At that time, Harper was working on a Case: 21-1803 Document: 50 Page: 3 Filed: 05/02/2022

GSC CONSTRUCTION, INC. v. SECRETARY OF THE ARMY 3

separate project (“the TEMF Project”) in the same location. For the TEMF Project, Harper was required to demolish and construct several other buildings. Id., slip op. at 4. To ensure proper coordination between the two projects, the Army provided GSC with the contract specifications for the TEMF project “for information” purposes only. Id., slip op. at 6–7; J.A. 4194. After several months of discussion, the contracting of- ficer formally directed GSC to remove and replace the soil, explaining that it was not Harper’s responsibility. Deci- sion, slip op. at 8. In support of his determination, the con- tracting officer pointed to § 6.3.1.1(e) of GSC’s contract, which provides that GSC is “responsible for any specific site preparation required to accommodate the foundation design.” Id., slip op. at 5–8; J.A. 5202. In response, GSC agreed to begin the work under protest. Once GSC began excavating, however, it found the soil to be “heavy” and “very wet,” which would require it to perform additional, specialized work. Decision, slip op. at 8. Ultimately, Har- per, which had specialized equipment to address that issue, stepped in to remove and replace the soil. Id. Second, GSC encountered issues when designing the cold-formed metal framing for the exterior walls. To design that framing, GSC was required to comply with the Unified Facilities Criteria (“UFC”) 4-010-01, which establish the “[Department of Defense] Minimum Antiterrorism Stand- ards for Buildings.” Id., slip op. at 12. As relevant here, there are different versions of the UFC: the 2007 version and the 2012 version. The 2012 UFC is more stringent than the 2007 UFC. Id., slip op. at 13. The Army notified GSC that it should design the framing in accordance with the 2007 UFC. Id. Despite that guidance, GSC mistakenly used the more stringent 2012 UFC when creating its shop drawings for the framing. Id. GSC’s quality control man- ager did not notice that mistake. Id. GSC then submitted its drawings to the Army. Id. The Army also did not detect GSC’s mistake. Rather, it observed that GSC prepared the Case: 21-1803 Document: 50 Page: 4 Filed: 05/02/2022

drawings using the 2012 UFC and reviewed them under that standard. Id. Subsequently, the Army rejected sev- eral of GSC’s drawings for failing to meet the 2012 UFC. Id. Both parties agree that, had the Army caught GSC’s mistake and applied the less stringent 2007 UFC, it would have approved the drawings weeks earlier. Id. Because of the soil dispute and the UFC oversight, GSC fell significantly behind schedule. Accordingly, on Janu- ary 16, 2014, the contracting officer issued a notice to GSC stating that GSC was 145 days behind schedule and that the Army was considering terminating the contract for de- fault. J.A. 8408. The notice also stated that the Army did not “condone any delinquency” or “waive any rights [it] has under the contract.” Id. GSC responded that it was “con- fident” that it could complete the project by June 9, 2014. J.A. 8404. GSC, however, continued to fall behind sched- ule. As a result, on April 28, 2014, the contracting officer issued a second notice, again stating that GSC had failed to make sufficient progress, that the Army was considering terminating the contract, and that the Army does not for- feit any rights under the contract. J.A. 8398–99. GSC, in turn, responded that it “firmly believe[d]” it could complete the work by August 30, 2014. J.A. 8389. But again, GSC continued to fall behind schedule. Finally, on June 18, 2014, the contracting officer terminated GSC’s contract with the Army for default. Decision, slip op. at 3. GSC appealed the contracting officer’s decision to the Board. According to GSC, it was entitled to a 321-day ex- tension because of the soil removal dispute and the UFC oversight (among other allegedly excusable delays). Id. GSC also argued that it was entitled to $328,293.82 in damages and a conversion of the termination for default to one for the “convenience of the government.” Id. The Board denied GSC’s appeal from the contracting officer’s decision. First, the Board held that the Army had met its initial burden of proving that the termination for Case: 21-1803 Document: 50 Page: 5 Filed: 05/02/2022

GSC CONSTRUCTION, INC. v. SECRETARY OF THE ARMY 5

default was justified. Id., slip op. at 24. The Board noted that the contract’s completion date was February 3, 2014, and that GSC, indisputably, “did not complete the work” by that date. Id., slip op. at 2, 24. Next, the Board held that GSC failed to show it was entitled to a 321-day extension as a result of the delays. With respect to the soil removal dispute, the Board deter- mined that, under the contract, GSC was required to per- form the work rather than Harper. Id., slip op. at 25–27. In particular, the Board pointed to § 6.3.1.1(e) of the con- tract, which states that GSC is “responsible for any specific site preparation required to accommodate the foundation design.” Id., slip op. at 5, 25; J.A. 5202.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gates v. Raytheon Co.
584 F.3d 1062 (Federal Circuit, 2009)
LAI Services, Inc. v. Gates
573 F.3d 1306 (Federal Circuit, 2009)
Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Hercules Incorporated v. United States
292 F.3d 1378 (Federal Circuit, 2002)
Wallace Forman v. United States
329 F.3d 837 (Federal Circuit, 2003)
Laguna Construction Company v. Defense
828 F.3d 1364 (Federal Circuit, 2016)
Securiforce International America, LLC v. United States
879 F.3d 1354 (Federal Circuit, 2018)
Electric Boat Corporation v. Secretary of the Navy
958 F.3d 1372 (Federal Circuit, 2020)
Kellogg Brown & Root Services v. Secretary of the Army
973 F.3d 1366 (Federal Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
Gsc Construction, Inc. v. Secretary of the Army, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gsc-construction-inc-v-secretary-of-the-army-cafc-2022.