Kellogg Brown & Root Services v. Secretary of the Army

973 F.3d 1366
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 1, 2020
Docket19-1683
StatusPublished
Cited by14 cases

This text of 973 F.3d 1366 (Kellogg Brown & Root Services v. Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kellogg Brown & Root Services v. Secretary of the Army, 973 F.3d 1366 (Fed. Cir. 2020).

Opinion

Case: 19-1683 Document: 52 Page: 1 Filed: 09/01/2020

United States Court of Appeals for the Federal Circuit ______________________

KELLOGG BROWN & ROOT SERVICES, INC., Appellant

v.

SECRETARY OF THE ARMY, Appellee ______________________

2019-1683 ______________________

Appeal from the Armed Services Board of Contract Ap- peals in Nos. 57530, 58161, Administrative Judge Mark A. Melnick, Administrative Judge Owen C. Wilson, Adminis- trative Judge Richard Shackleford. ______________________

Decided: September 1, 2020 ______________________

EDWARD SANDERSON HOE, Covington & Burling LLP, Washington, DC, argued for appellant. Also represented by RAYMOND B. BIAGINI, HERBERT L. FENSTER; ALEJANDRO LUIS SARRIA, JASON NICHOLAS WORKMASTER, Miller & Chevalier Chartered, Washington, DC.

DAVID W. TYLER, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washing- ton, DC, argued for appellee. Also represented by ETHAN P. DAVIS, RUSSELL B. KINNER, WILLIAM JAMES GRIMALDI, ROBERT EDWARD KIRSCHMAN, JR., PATRICIA M. MCCARTHY, Case: 19-1683 Document: 52 Page: 2 Filed: 09/01/2020

2 KELLOGG BROWN & ROOT SERVICES v. SECRETARY OF THE ARMY

MICHAL L. TINGLE, ANDY J. MAO, PATRICK KLEIN, II; CAROL MATSUNAGA, Defense Contract Management Agency, Car- son, CA; KARA KLAAS, Chantilly, VA. ______________________

Before NEWMAN, DYK, and WALLACH, Circuit Judges. Opinion for the court filed by Circuit Judge DYK. Dissenting opinion filed by Circuit Judge NEWMAN. DYK, Circuit Judge. Kellogg Brown and Root Services, Inc. (“KBR”) con- tracted with the government to provide trailers to house coalition personnel at military camps in Iraq. KBR claimed that the government breached the contract by failing to provide “force protection” to the trucks delivering the trail- ers to the military camps. KBR sought to recover payments made to its subcontractor, First Kuwaiti Co. of Kuwait (“Kuwaiti”), for costs caused by the government’s alleged breach. The administrative contracting officer in large part denied the claim, and KBR appealed to the Armed Ser- vices Board of Contract Appeals (“Board”). The Board found that KBR was not entitled to any additional recovery and denied its appeal. We affirm the Board’s decision on the ground that the Board properly determined that KBR’s costs had not been shown to be reasonable, and we do not reach the question whether the government breached the “force protection” provision of the contract. BACKGROUND In 2001, the United States Army awarded Contract No. DAAA09-02-D-0007 (“Contract 0007”) in the U.S. Army’s Logistics Civil Augmentation Program (“LOGCAP III”) to KBR. Among other things, the contract required KBR to provide logistical support in the form of goods (such as trailers used for temporary housing) for the government Case: 19-1683 Document: 52 Page: 3 Filed: 09/01/2020

KELLOGG BROWN & ROOT SERVICES v. SECRETARY OF THE 3 ARMY

pursuant to a series of task orders. LOGCAP III contained a provision (“the Force Protection Clause”) requiring that the Army provide “force protection” for the contractor’s con- voys for providing these goods and services. It stated: H-16 Force Protection While performing duties [in accordance with] the terms and conditions of the contract, the Service Theatre Commander will provide force protection to contractor employees commensurate with that given to Service/Agency (e.g. Army, Navy, Air Force, Marine, DLA) civilians in the operations area unless otherwise stated in each task order. J.A. 242. In June 2003, the government executed Task Order 59, a cost-plus-fixed-fee order for KBR to provide support to operations in Iraq. This case concerns the government’s October 10, 2003, modification to Task Order 59 (“Change 5”), which required KBR to “provide accommodations and life support services to [Command Joint Task Force 7 (“CJTF7”)] and coalition forces in various locations in Iraq.” J.A. 291. The “accommodations and life support services” were trailers for temporary housing of Army personnel. Change 5 states that “[i]t is the Commander’s intent to rap- idly bed down the remainder of CJTF soldiers, building within battalion sets, simultaneously as opposed to sequen- tially, in accordance with established and provided priori- ties.” Id. KBR was originally required to furnish the trailers by December 15, 2003. The trailers were to be manufactured in Kuwait and then transported to Iraq by Kuwaiti in truck convoys. Sec- tion 1.10 of Change 5 again addressed the issue of force protection, stating that “[t]he government will provide for the security of contractor personnel in convoys and on site, commensurate with the threat, and [in accordance with] Case: 19-1683 Document: 52 Page: 4 Filed: 09/01/2020

4 KELLOGG BROWN & ROOT SERVICES v. SECRETARY OF THE ARMY

the applicable Theater Anti-Terrorism/Force Protection guidelines.” J.A. 292. On October 17, 2003, KBR and Kuwaiti entered into a firm-fixed-price subcontract (“the Subcontract”) for the pro- curement and delivery of 2,252 trailers to Camp Anaconda in fulfillment of part of KBR’s obligations under Change 5. In accordance with Change 5, the Subcontract required Ku- waiti to complete performance by December 15, 2003, with “[a]llowances” in the event of “delays in KBR convoy coor- dination and support.” J.A. 1153. The Subcontract pro- vided that if KBR ordered any changes to performance that resulted in an increased cost of performance to Kuwaiti, Kuwaiti would be entitled to request an equitable adjust- ment. On December 13, 2003, KBR issued another change order, directing Kuwaiti to deliver and install an additional 1,760 trailers to a second Army camp in Iraq, Camp Vic- tory. The Army’s failure to provide force protection in Iraq became an issue between the government and KBR, and another such dispute resulted in a previous Board decision finding that the Army failed to meet its force protection ob- ligations. See Sec’y of the Army v. Kellogg Brown & Root Servs., Inc., 779 F. App’x 716, 718 (Fed. Cir. 2019). As rel- evant here, the Board found that by late November of 2003, “dangerous conditions in Iraq” and “limitations upon the military’s resources to escort convoys” and the prioritiza- tion of other Army needs resulted in the failure to provide necessary force protection and convoy delays. J.A. 7. Kuwaiti alleged that the delays resulted in delivery de- lays and a backup of trailers at the Kuwait/Iraq border. It alleged that it was eventually required to store the trailers on rented land (a “laydown yard”) in Kuwait and incurred Case: 19-1683 Document: 52 Page: 5 Filed: 09/01/2020

KELLOGG BROWN & ROOT SERVICES v. SECRETARY OF THE 5 ARMY

costs for double handling, i.e., unloading and then reload- ing the trailers onto its trucks. 1 J.A. 7. On August 1, 2004, and August 4, 2004, KBR and Ku- waiti executed two change orders adding a total of $48,754,547.25 in equitable adjustments for idle truck costs due to the backup of trailers at the border and double- handling costs. As would be expected, KBR, as the prime contractor, then filed two requests for equitable adjustments with the government, asserting that it was entitled to recover the payment to Kuwaiti because the delay and double-han- dling costs were due to the government’s failure to provide the required force protection. The final amount sought by KBR, which included the $48,754,547.25 paid to Kuwaiti as well as indirect costs and the award fee, 2 totaled $51,273,482. On July 29, 2011, the administrative contracting of- ficer issued a final decision allowing $3,783,005 in costs as- sociated with the land leased to store the trailers (including indirect costs and award fees) but rejecting the remainder of KBR’s requested costs for delay and double handling.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wolverine Tube, Inc.
Armed Services Board of Contract Appeals, 2026
Fluor Federal Solutions, Inc.
Armed Services Board of Contract Appeals, 2022
Agarwal v. Morbark, LLC
Federal Circuit, 2022
ECC International Constructors, LLC
Armed Services Board of Contract Appeals, 2022
Harry Pepper and Associates, Inc.
Armed Services Board of Contract Appeals, 2021
Bannum, Inc. v. United States
Federal Claims, 2021
GSC Construction, Inc.
Armed Services Board of Contract Appeals, 2020

Cite This Page — Counsel Stack

Bluebook (online)
973 F.3d 1366, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kellogg-brown-root-services-v-secretary-of-the-army-cafc-2020.