Wolverine Tube, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJanuary 22, 2026
Docket63877
StatusPublished

This text of Wolverine Tube, Inc. (Wolverine Tube, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wolverine Tube, Inc., (asbca 2026).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - ) ) Wolverine Tube, Inc. ) ASBCA No. 63877 ) Under Contract No. FA8534-21-D-0002 )

APPEARANCE FOR THE APPELLANT: Bret S. Wacker, Esq. Clark Hill PLC Detroit, MI

APPEARANCES FOR THE GOVERNMENT: Caryl A. Potter, III, Esq. Air Force Deputy Chief Trial Attorney Christopher J. Hilborn, Esq. Hector M. RiveraHernandez, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE LAUFGRABEN ON THE PARTIES’ CROSS-MOTIONS FOR SUMMARY JUDGMENT ON ENTITLEMENT

This case arises from the convenience termination of an Air Force contract to supply air cargo pallets. Appellant, Wolverine Tube, Inc. (Wolverine), brought this appeal to recover convenience termination costs that were denied by the Air Force because they were incurred after Wolverine received a stop-work order. Wolverine contends that the costs are allowable because the stop-work order expired before Wolverine incurred them. Both parties have filed cross-motions for summary judgment on entitlement. For the reasons set forth below, we grant Wolverine’s summary judgment motion, in part, and deny it, in part. We deny the Air Force’s cross-motion.

STATEMENT OF FACTS FOR PURPOSES OF THE CROSS-MOTIONS

I. The Pallet Contract

1. On May 18, 2021, the Air Force awarded Contract No. FA8534-21-D-0002 (Pallet Contract) for the manufacture and delivery of air cargo pallets to Wolverine (jt. stip. of facts (JSF) ¶ 2). The Pallet Contract is an Indefinite Delivery Requirements contract under FAR 16.503 (R4, tab 1 at 3). The Pallet Contract included a Base Contract Period with an 18-month performance period followed by eight 12-month options and one 6-month option (app. stmt. of facts (SOF) ¶ 4).

2. The Pallet Contract required Wolverine to manufacture and deliver six “first articles” for testing by the Air Force within 365 days of award—i.e., by May 18, 2022 (R4, tab 1 at 68 (incorporating in full FAR 52.209-4, FIRST ARTICLE APPROVAL – GOVERNMENT TESTING (SEP 1989))). The purpose of a first article test is to ensure “that the contractor can furnish a product that conforms to all contract requirements for acceptance.” FAR 9.302.

3. In accordance with FAR 52.209-4(h), the Pallet Contract cautioned Wolverine against purchasing materials or components for production before obtaining approval of its first articles:

Before first article approval, the acquisition of materials or components for, or the commencement of production of, the balance of the contract quantity is at the sole risk of the Contractor. Before first article approval, the costs thereof shall not be allocable to this contract for (1) progress payments, or (2) termination settlements if the contract is terminated for the convenience of the Government.

(R4, tab 1 at 68)

4. The Pallet Contract structured performance requirements by a series of contract line-item numbers (CLINs) (id. at 3-57). CLIN 0001 and CLIN 0002 related to first article testing. Under CLIN 0001, the Pallet Contract specified that the Air Force would pay $3,000 for each first article delivered for a total of $18,000. Under CLIN 0002, Wolverine would be paid $17,391,000 for Non-Recurring First Article Costs “ONLY AFTER approval of first article.” (Id. at 4-5) (emphasis in original)

5. For orders placed under the Pallet Contract, the Pallet Contract included a Best Estimated Quantity (BEQ) for each option period, which represented “the estimated quantity the Government expects to order” during that period (R4, tab 1 at 3). The BEQs ranged from 10,000–15,000 pallets per year (id. at 8 11, 23, 29, 34, 40, 46, 52).

6. The Pallet Contract also provided that, “[i]n accordance with DFARS 252.217-7001(a)(l), Surge Option (Dec 2018), the Government has the option to increase the quantity of supplies or services called for under this contract IAW SOW paragraph 3.6.1.2.3, Surge Requirements” (R4, tab 1 at 3). Thus, starting in the second option period, Wolverine “shall be able to attain capacity for a surge order quantity of up to 50,000 pallets per year, with the expected delivery of all units within 365 days from the date of order” (id. at 16).

7. The Pallet Contract incorporated by reference two FAR provisions that permitted the government to stop work: FAR 52.242-15 and FAR 52.233-3 (id. at 59, 84). The first provision, FAR 52.242-15, STOP-WORK ORDER (AUG 1989), provides:

2 (a) The Contracting Officer may, at any time, by written order to the Contractor, require the Contractor to stop all, or any part, of the work called for by this contract for a period of 90 days after the order is delivered to the Contractor, and for any further period to which the parties may agree. The order shall be specifically identified as a stop-work order issued under this clause. Upon receipt of the order, the Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period of work stoppage. Within a period of 90 days after a stop-work order is delivered to the Contractor, or within any extension of that period to which the parties shall have agreed, the Contracting Officer shall either—

(1) Cancel the stop-work order; or

(2) Terminate the work covered by the order as provided in the Default, or the Termination for Convenience of the Government, clause of this contract.

(b) If a stop-work order issued under this clause is canceled or the period of the order or any extension thereof expires, the Contractor shall resume work.

FAR 52.242-15(a)-(b).

8. The second provision, FAR 52.233-3, PROTEST AFTER AWARD (AUG 1996), applies to stopping work in connection with a bid protest:

Upon receipt of a notice of protest (as defined in FAR 33.101) or a determination that a protest is likely (see FAR 33.102(d)), the Contracting Officer may, by written order to the Contractor, direct the Contractor to stop performance of the work called for by this contract. The order shall be specifically identified as a stop-work order issued under this clause. Upon receipt of the order, the Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period of work stoppage. Upon receipt of the final decision in the protest, the Contracting Officer shall either—

3 (1) Cancel the stop-work order; or

(2) Terminate the work covered by the order as provided in the Default, or the Termination for Convenience of the Government, clause of this contract.

FAR 52.233-3(a).

9. The Pallet Contract also incorporated by reference FAR 52.249-2, TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 2012) (R4, tab 1 at 86). The provision encourages the parties to agree on the terms of a convenience termination settlement; however, if the parties cannot reach an agreement, FAR 52.249-2 provides that contractor is entitled to the following costs:

(1) The contract price for completed supplies or services accepted by the Government (or sold or acquired under paragraph (b)(9) of this clause) not previously paid for, adjusted for any saving of freight and other charges.

(2) The total of--

(i) The costs incurred in the performance of the work terminated, including initial costs and preparatory expense allocable thereto, but excluding any costs attributable to supplies or services paid or to be paid under paragraph (g)(1) of this clause;

(ii) The cost of settling and paying termination settlement proposals under terminated subcontracts that are properly chargeable to the terminated portion of the contract if not included in subdivision (g)(2)(i) of this clause; and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Diebold, Inc.
369 U.S. 654 (Supreme Court, 1962)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Kellogg Brown & Root Services, Inc. v. United States
728 F.3d 1348 (Federal Circuit, 2013)
Kellogg Brown & Root Services v. Secretary of the Army
973 F.3d 1366 (Federal Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
Wolverine Tube, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/wolverine-tube-inc-asbca-2026.