Allison Transmission, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJuly 17, 2014
DocketASBCA No. 59204
StatusPublished

This text of Allison Transmission, Inc. (Allison Transmission, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allison Transmission, Inc., (asbca 2014).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Allison Transmission, Inc. ) ASBCA No. 59204 ) Under Contract No. DAAE07-99-C-N031 )

APPEARANCES FOR THE APPELLANT: Scott E. Pickens, Esq. William M. Jack, Esq. Barnes & Thornburg LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: E. Michael Chiaparas, Esq. DCMA Chief Trial Attorney Arthur M. Taylor, Esq. Samuel W. Morris, Esq. Trial Attorneys Defense Contract Management Agency Manassas, VA

OPINION BY ADMINISTRATIVE JUDGE DELMAN PURSUANT TO BOARD RULE 12.2

In this appeal Allison Transmission, Inc., (appellant or Allison) disputes the government's entitlement to compound interest on an acknowledged liability to pay increased costs arising out of a voluntary cost accounting change. Appellant elected to prosecute the appeal under Board Rule 12.2, 1 Expedited Procedures, and both parties have agreed to waive oral hearing and to submit their positions on the record. 2 The Board has jurisdiction under the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109.

1 The Contract Disputes Act, implemented by Board Rule 12.2, provides that this decision shall have no value as precedent, and in the absence of fraud shall be final and conclusive and may not be appealed or set aside. 2 Allison's record submission is entitled "APPELLANT'S MOTION FOR JUDGMENT AND MEMORANDUM IN SUPPORT." The government's record submission is entitled "GOVERNMENT'S CROSS MOTION FOR SUMMARY JUDGMENT." Notwithstanding these captions, this appeal is being adjudicated on the record at the parties' request pursuant to Board Rule 11. SUMMARY FINDINGS OF FACT

1. Contract No. DAAE07-99-C-N031 (Contract N03 l) was awarded by the U.S. Army Tank Automotive Command (government) to Allison on 12 July 1999. This contract contains the following CAS-related contract clauses in the FAR which are incorporated by reference at Section I of the contract: FAR 52.230-2, COST ACCOUNTING STANDARDS (APR 1998); FAR 52.230-3, DISCLOSURE AND CONSISTENCY OF COST ACCOUNTING PRACTICES (APR 1998); and FAR 52.230-6, ADMINISTRATION OF COST ACCOUNTING STANDARDS (APR 1996). 3 (R4, tab 1)

2. By letter dated 30 April 2007, Allison submitted to the Defense Contract Management Agency (DCMA) a notification of a change to its cost accounting practices, effective 1 January 2008. The change eliminated Allison's Engineering Cost Center Group 4C, previously disclosed in Allison's CAS Disclosure Statement. Allison advised the government as follows:

The departments within this cost center group [4C] will become part of burden center group 4 Y and will no longer write time tickets to be charged direct. The functions currently being performed in 4C are to be allocated over the remaining cost center groups based on charge-out labor.

Appellant requested the "concurrence" of the DCMA Administrative Contracting Officer (ACO) with the change. The ACO signed his name on the concurrence line of this letter on 30 May 2007. (App. supp. R4, tab 14; gov't reply br., ex. G-8, Stout decl. if 3)

3. By letter to the ACO dated 9 October 2008, Allison submitted to DCMA a cost impact proposal related to the cost accounting practice change. Allison determined that as a result of the change, the government paid increased costs in the amount of $599,019.79. (App. supp. R4, tab 15)

4. On 25 March 2010 the Defense Contract Audit Agency (DCAA) issued a memorandum to the ACO returning the impact proposal to appellant for failing to follow the prescribed format (gov't mot., ex. G-4). Allison was so advised by letter of that same date (gov't mot., ex. G-5).

3 The parties have stipulated that the April 1998 CAS clause cited herein is the controlling CAS clause in this appeal, and that the 2012 CAS clause cited by appellant in its motion is not materially different insofar as pertinent here. The parties have also stipulated that FAR Subpart 30.6, effective 8 April 2005, may be consulted and used by the Board as appropriate. (App. reply, attach. 1, Stipulation)

2 5. By letter to DCMA dated 15 April 2010, Allison resubmitted its cost impact proposal related to this cost accounting practice change. Again, Allison determined that as a result of the change the government paid increased costs in the amount of $599,019.79. (App. supp. R4, tab 16)

6. By memorandum to the ACO dated 17 January 2013, DCAA provided a Rough Order of Magnitude (ROM) estimate on the cost impact to the government resulting from the cost accounting practice change. DCAA described the change as a unilateral change. The ROM covered the cost impact to one prime contract between Allison and the government, Contract N031, and two subcontracts awarded to Allison by prime contractor General Dynamics (projects "P920" and "P929"). DCAA concluded that Allison overstated the cost impact by $443,904.79, and therefore the total increased costs paid by the government were $155,115.00. DCAA linked the overstated cost impact figure to several errors committed by Allison in its cost impact calculation methodology. (R4, tab 2)

7. By letter to appellant dated 7 March 2013, the ACO stated that "ATI owes a net overstatement amount of$155,115.00." The ACO also stated that, "[i]n accordance with FAR 52.230-2(a)(5), interest will be applicable to the final negotiated amount." (R4, tab 3)

8. By letter to the ACO dated 12 March 2013, Allison agreed to pay the government the principal amount of $155,115. With respect to interest, appellant stated: "The interest shall start to accumulate 30 days from the receipt of the demand letter .... ATI has not received a demand letter so the estimated interest would be $0." (R4, tab 4)

9. By letter to Allison dated 27 September 2013, the ACO advised that she had "privity" over Contract N031, but not over the two subcontracts. Based upon revised calculations, the ACO agreed to settle Contract N031 for $165,424. 4 Again, the ACO stated, "[i]n accordance with FAR 52.230-2(a)(5), interest will be applicable to the final negotiated amount." (R4, tab 5)

10. By letter to the ACO dated 11 October 2013, Allison agreed to pay the principal amount of $165,424. With respect to interest, appellant stated as follows:

2. ATI will pay interest on the $165,424 starting on October 1, 2013 in the amount of $408.38. This calculation is based on the interest starting to accumulate

4 This upward adjustment is attributable to the removal of the subcontracts "P920" and "P929" from the original cost impact calculation.

3 effective October I, 2013 until October 31, 2013 when we anticipate payment would be made.

Allison attached a 2009 letter from an ACO on an unrelated 2004 cost accounting change in support of its position on interest. (R4, tab 6)

11. On 23 December 2013, the ACO issued a contracting officer's final decision (COFD) to Allison, asserting a government claim of$199,101.00, inclusive of interest to the date of the decision, for the cost impact to the government resulting from Allison's cost accounting practice change. The COFD identified Contract N03 l as the representative contract. The government's claim of$199,101.00 was comprised of the principal amount of $165,424.00, plus compound interest in the amount of $33,676.62 covering the period of time between the estimated government overpayment of the increased costs (30 June 2008), through the date of the final decision. (R4, tabs 7-8)

12. Insofar as pertinent, the COFD stated:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Allison Transmission, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/allison-transmission-inc-asbca-2014.