Innovative Technologies, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJuly 26, 2023
Docket61686, 62185
StatusPublished

This text of Innovative Technologies, Inc. (Innovative Technologies, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Innovative Technologies, Inc., (asbca 2023).

Opinion

DOCUMENT FOR PUBLIC RELEASE. The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release. ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of - ) ) Innovative Technologies, Inc. ) ASBCA Nos. 61686, 62185 ) Under Contract No. HQ0028-07-D-0003 )

APPEARANCE FOR THE APPELLANT: Andrew P. Hallowell, Esq. Pargament & Hallowell, PLLC Washington, DC

APPEARANCES FOR THE GOVERNMENT: Leslie K Stolasz, Esq. General Counsel Thomas Trinti, Esq. Trial Attorney Defense Media Activity Riverside, CA

Christopher J. Hilborn, Esq. Air Force Senior Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE SMITH

These appeals concern the basis and amount of an equitable adjustment to which appellant, Innovative Technologies, Inc. (ITI), is entitled following performance of ITI’s 2006-2011 service contract with respondent, the Defense Media Agency (DMA). DMA acknowledges that ITI is entitled to an equitable adjustment but disputes the entitlement basis claimed by ITI. We are proceeding under Rule 11, supplemented by an oral argument, to determine entitlement. We agree that an equitable adjustment is due, but ITI’s entitlement is limited to a discrete and comparatively small element of its claim.

FINDINGS OF FACTS

Solicitation and Contract Structure

Solicitation No. HQ0028-06-R-0023 (the solicitation) 1 was issued on June 19, 2006, for a firm fixed price requirements contract (R4, tab 5 at 1, 54). The solicitation

1 We refer to both the solicitation, as amended, and the almost-identical contract (R4, tabs 5 and 11 respectively) as “the contract” and cite to R4 tab 11 unless there is DOCUMENT FOR PUBLIC RELEASE. The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release. was for an “engineering services contract” and each of the 40 Contract Line Item Numbers (CLINS) indicated that they were for “services” (id. at 2-25, 54).

The contract was awarded and administered by DMA to provide customer agencies in the Department of Defense with visual information/media system installation services and equipment based upon subsequent task descriptions, proposals and awarded task orders (TOs) that were also administered by DMA (R4, tab 3 at 2, tab 11 at 40, tab 540 at 1). The contract was patently for the furnishing of services in the United States through the use of service employees, so it was governed by the Service Contract Act (SCA), 41 U.S.C. §§ 6701-6707.

An earlier engineering service contract between the parties (the predecessor contract) had been performed between 2001 and 2006 (R4, tabs 1-2). And there is some indication, though no supporting evidence, that a still-earlier engineering service contract between the parties occurred between 1998 and 2001 (R4, tab 547 at 2).

The solicitation required contractors to propose fully burdened fixed hourly rates for several categories of labor (R4, tab 11 at 34). Offerors were instructed that “[p]roposed labor rates should be ‘loaded’ rates, that is including base hourly wages paid, all fringes and benefits as required by the Department of Labor; G&A, Overhead(s) and Profit” (R4, tab 11 at 35). During the source selection for the contract, DMA’s acquisition personnel were instructed to compare offerors’ proposed labor rates with applicable “Department of Labor rates” (R4, tab 3 at 11) which are defined by Department of Labor (DOL)-issued wage determinations (WDs).

The labor rates set by the contract constituted “the firm-fixed hourly labor rates at which all task order proposals for services must be submitted” (R4, tab 11 at 35). After award, the parties were to negotiate a firm fixed price for each task order (TO) (R4, tab 11 at 40).

Relevant Federal Acquisition Regulation (FAR) Clauses

The contract included FAR 52.222-42, STATEMENT OF EQUIVALENT RATES FOR FEDERAL HIRES (MAY 1989), which is required in SCA contracts by FAR 22.1006(b). FAR 52.222-42 provided several labor rates applicable to Federal employees that perform the functions expected to be performed by workers 2 for this contract (R4, tab 11 at 29-30).

a reason to distinguish one from the other in which case we refer to “the solicitation” (tab 5) and “the awarded contract” (tab 11). 2 We use the term “workers” to broadly include employees, independent contractors, subcontractor employees, etc.

2 DOCUMENT FOR PUBLIC RELEASE. The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

FAR 52.222-41 (the SCA clause) describes the wage determination process in contracts subject to the SCA and is required in service contracts. FAR 22.1006. But contrary to FAR 22.1006, the SCA clause was not included in full text or incorporated by reference in the contract – or in any of the post-award TOs (R4, tab 11, tab 540 at 1). DMA later described the omissions as “error” and “administrative oversight,” but could not provide details on these mistakes (R4, tab 550 at 10; app. mot. at ex. A, response to appellant’s Interrogatory Nos. 3, 11).

Our comparison of the predecessor contract with the contract here suggests that DMA’s administrative oversight was to omit from the current contract FAR 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS--COMMERCIAL ITEMS (AUG 2000), which lists 37 FAR clauses, including the SCA clause, that can be check-marked to incorporate them by reference (R4, tab 1 at 32-35). DMA included FAR 52.212-5 in the predecessor contract and checked 12 of the optional clauses, including the SCA clause (id.). The omission of FAR 52.212.5 may have been due to confusion between it and a similarly titled Department of Defense Supplement to the Federal Acquisition Regulation (DFARS) clause, 252.212-7001, which lists various DFARS clauses to be checked to incorporate them by reference (R4, tab 1 at 38-39, tab 11 at 35). Slightly different versions of DFARS 252.212-7001 were included in both the predecessor contract and this contract (R4, tab 1 at 38-39, tab 11 at 35).

Regardless of how it occurred, DMA’s omission of FAR 52.212-5, and its 12 checked clauses incorporated by reference, appears to be a considerable oversight. But there is no evidence that the omission was intentional or focused upon the SCA clause or any particular aspect of the SCA at all. 3 Instead, it appears to have been a bona fide administrative oversight in the assembly of the contract.

Attachments to the Contract and Wage Determination No. 35

The “EXHIBITS AND ATTACHMENTS” section of the contract indicated that “[t]he following documents, exhibits or other attachments, if any, form a part of this document” (R4, tab 11 at 29). It listed an Exhibit A, which was the performance work statement, and Attachments 1, 2, and 3. Id.

3 FAR 22.1006 also requires an agency to expressly indicate if a contract is exempt from the SCA via the inclusion of other FAR clauses that notify the parties of the exemption. See FAR 22.1006(a)(2). No exemption language was in the contract here.

3 DOCUMENT FOR PUBLIC RELEASE. The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Innovative Technologies, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/innovative-technologies-inc-asbca-2023.