Donald H. Rumsfeld, Secretary of Defense v. General Dynamics Corporation

365 F.3d 1380, 2004 U.S. App. LEXIS 8495, 2004 WL 905997
CourtCourt of Appeals for the Federal Circuit
DecidedApril 29, 2004
Docket03-1209
StatusPublished
Cited by10 cases

This text of 365 F.3d 1380 (Donald H. Rumsfeld, Secretary of Defense v. General Dynamics Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Donald H. Rumsfeld, Secretary of Defense v. General Dynamics Corporation, 365 F.3d 1380, 2004 U.S. App. LEXIS 8495, 2004 WL 905997 (Fed. Cir. 2004).

Opinion

MICHEL, Circuit Judge.

The government appeals from the final decision of the Armed Services Board of Contract Appeals (“Board”) insofar as it held that 10 U.S.C. § 2324(k) required the apportionment of legal costs for defending against different claims with different outcomes within a single proceeding. The Board concluded that such apportionment was necessary to properly accomplish Congress’ implicit goals of permitting recovery of such costs when a contractor was successful, while insuring that a contractor was not reimbursed for such costs regarding proven or conceded wrongdoing. Gen. Dynamics Corp., ASBCA No. 49,372, 2002-2 BCA (CCH) ¶ 31,888 (June 10, 2002). Because we conclude that the Board erred in holding that section 2324(k) requires such apportionment and allowability of costs for different claims in a single proceeding, and because the government has not appealed from that part of the Board’s decision reversing the contracting officer’s assessment of a penalty pursuant to regulation, we reverse-in-part.

*1382 Background

In the late 1970s, General Dynamics Corporation (“General Dynamics”) built two civilian vessels using a construction differential subsidy granted by the Maritime Administration pursuant to Title V of the Merchant Marine Act of 1936, 46 U.S.CApp. §§ 1151-1161. To demonstrate eligibility for the subsidies, General Dynamics was required to submit cost details and evidence that both the negotiated price and General Dynamics’ cost estimates were “fair and reasonable.” 46 U.S.CApp. § 1152(a). The detailed estimates that General Dynamics submitted to the Maritime Administration in connection with the subsidies were divided into six areas, one of which concerned sphere insulation and joiner work.

The subcontract for the sphere insulation and joiner work was awarded to the Frigitemp Corporation of New York City (“Frigitemp”). Mr. Davis, Senior Vice President of Frigitemp, and Mr. Veliotis, President and General Manager of General Dynamics’ Quincy Shipbuilding Division, among others, agreed to award the subcontract to Frigitemp in exchange for bribes and kickbacks to be paid to Veliotis and Mr. Gilliland, Veliotis’ principal assistant. United States v. Davis, 767 F.2d 1025, 1027 (2d Cir.1985). During 1973-1977, Frigitemp, at the behest of Mr. Davis, paid about $2.7 million in kickbacks to General Dynamics officers Veliotis and Gilliland, in return for being awarded the subcontracts. Id.; United States v. Davis, 803 F.Supp. 830, 859-60 (S.D.N.Y.1992).

In the early 1980s, Gerald Lee, Chief Executive Officer of Frigitemp, Davis, Vel-iotis, and Gilliland were indicted. Davis, 767 F.2d at 1027. Lee pled guilty, Davis was found guilty, and Veliotis and Gilliland fled the United States. Id.

In 1985, the United States Attorney commenced a civil proceeding in the United States District Court for the Southern District of New York. On October 27, 1992, the district court dismissed the government’s claims and found in favor of General Dynamics. Davis, 803 F.Supp. 830. General Dynamics claimed, and the district court ruled, that General Dynamics was not legally liable for the damages suffered by the Maritime Administration as a result of the Frigitemp kickbacks because the pre-1986 version of the Anti-Kickback Act did not apply to prime contractors. 1 Id. at 859, 871. Though the district court found that General Dynamics’ estimates for the five categories of costs other than the sphere insulation and joiner estimate were fair and reasonable, and that the government had not established fraud, the district court did not rule on the government’s allegation that General Dynamics had passed the costs of the Frigitemp kickbacks on to the Maritime Administration by including them in the sphere insulation and joiner estimate.

On March 17, 1994, the Second Circuit affirmed-in-part, reversed-in-part, and remanded the case to the district court. United States v. Gen. Dynamics Corp., 19 F.3d 770 (2d Cir.1994). The Second Circuit reversed the district court’s ruling that General Dynamics was not legally liable for the government’s damages suffered as a result of the inflated estimates for the sphere insulation and joiner work due to the Frigitemp kickbacks, and remanded to the district court. Id. The Second Circuit found that the Anti-Kickback Act did not *1383 preempt the False Claims Act, that the United States had stated valid claims under the False Claims Act and federal common law that should have been adjudicated, and that the government’s remedies would extend past the mere amount of the kickbacks to the amount that the cost estimates were inflated due to the collusive arrangement between Frigitemp and General Dynamics. Id. The Second Circuit affirmed the district court’s findings for General Dynamics on the other five portions of the costs estimate. Id. at 772. Because the government did not petition the Second Circuit for rehearing or the Supreme Court for writ of certiorari, the estimates claims were finally resolved in General Dynamics’ favor on June 15, 1994.

On remand, the government and General Dynamics entered into an agreement that provided for settlement of “all claims against General Dynamics included in the suit,” in consideration for the payment of $3.3 million by General Dynamics. The parties agreed that the “action shall be dismissed as against General Dynamics with prejudice and without costs or attorney’s fees to either party.” On July 21, 1994, the district court approved the parties’ settlement of the proceeding.

Shortly after the district court’s October 1992 decision in General Dynamics’ favor, General Dynamics notified a Department of Defense contracting officer that General Dynamics had revised its 1987 through 1991 corporate overhead proposals to include Davis-case costs that had previously been set aside in accordance with FAR 31.205-47(g). Following the 1994 settlement, General Dynamics submitted its certified revised overhead proposal for 1991, and included its Dams-case costs as overhead costs for which it sought payment by the Department of Defense. By letter dated August 26,1994, the contracting officer wrote General Dynamics, stating that all the Davis-case legal expenses were un-allowable pursuant to FAR 31.205-47(b)(4), and requested that General Dynamics “remove the expenses from certified claims for incurred costs and billings.” On September 9, 1994, General Dynamics submitted a revised certified 1991 overhead cost proposal which incorporated 80 percent of the Davis-case costs, including the proceeding costs associated with the Frigitemp cost estimate. By letter dated September 22, 1994, General Dynamics stated that, because it had substantially prevailed in the Davis proceeding, it was entitled to include 80 percent of all of its costs of the proceeding in its overhead proposals pursuant to regulation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CACI International, Inc.
Armed Services Board of Contract Appeals, 2026
Northrop Grumman Mission Systems
Armed Services Board of Contract Appeals, 2021
Raytheon Company and Raytheon Missile Systems
Armed Services Board of Contract Appeals, 2021
Energy Matter Conversion Corporation
Armed Services Board of Contract Appeals, 2018
Luna Innovations, Inc.
Armed Services Board of Contract Appeals, 2017
Raytheon Company
Armed Services Board of Contract Appeals, 2017
Sec. Of Energy v. The Boeing Co.
497 F. App'x 978 (Federal Circuit, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
365 F.3d 1380, 2004 U.S. App. LEXIS 8495, 2004 WL 905997, Counsel Stack Legal Research, https://law.counselstack.com/opinion/donald-h-rumsfeld-secretary-of-defense-v-general-dynamics-corporation-cafc-2004.