Energy Matter Conversion Corporation

CourtArmed Services Board of Contract Appeals
DecidedDecember 18, 2018
DocketASBCA No. 61583
StatusPublished

This text of Energy Matter Conversion Corporation (Energy Matter Conversion Corporation) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Energy Matter Conversion Corporation, (asbca 2018).

Opinion

,,". ARMED SERVICES BOARD OF CONTRACT APPEALS

'-' Appeal of -- ) ) Energy Matter Conversion Corporation ) ASBCA No. 61583 ) Under Contract No. N68936-09-C-0125 )

APPEARANCE FOR THE APPELLANT: Dr. Jaeyoung Park President

APPEARANCES FOR THE GOVERNMENT: Arthur M. Taylor, Esq. DCMA Chief Trial Attorney Stephen M. Wilson, Esq. Defense Contract Management Agency Carson, CA

OPINION BY ADMINISTRATIVE JUDGE SWEET ON THE GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT

The government has moved for summary judgment. It argues that it is entitled () to judgment as a matter of law on the claims of pro se appellant Energy Matter Conversion Corporation (EMC2) that the government improperly imposed a penalty because EMC2 included expressly unallowable legal costs in its cost proposals, and EMC2 is not entitled to a waiver of that penalty. EMC2 argues that the legal costs are not expressly unallowable, and that it is entitled to a waiver. Forthe reasons discussed below, the motion is granted.

STATEMENT OF FACTS {SOF) FOR PURPOSES OF THE MOTION

1. Beginning in 2006, the U.S. Department of Justice (DOJ) investigated EMC2 for potential mischarges, in violation of the False Claims Act, 31 U.S.C. §§ 3729-3733 related to a different contract than the one subject to this appeal (app. supp. R4, tab 12). The DOJ sought $556,745.83 (app. supp. R4, tab 13 at 9).

2. On September 11, 2009, the Department of the Navy (Navy) awarded Contract No. N68936-09-C-0125 (0125 contract) to EMC2. The 0125 contract was a cost-plus-fixed-fee contract. (R4, tab 1) The 0125 contract included Federal Acquisition Regulation (FAR) clause 52 .216-7, ALLOW ABLE COST AND PAYMENT (DEC 2002), which incorporated FAR Part 31, Contract Cost Principles and Procedures (id. at 22). The 0125 contract also included FAR clause 52.242-3, PENALTIES FOR UN ALLOW ABLE COSTS (MAY 2001) (id. at 21 ). (j 3. On December 10, 2012, the Navy Acquisition Integrity Office (AIO) issued a show cause letter regarding questionable costs EMC2 charged to the Navy in fiscal year (FY) 2000 through FY 2005 related to different contracts than the one subject to this appeal (app. supp. R4, tab 1 at 1-2). 1 Among the questionable costs was the salary of Cortine McGowen. According to the show cause letter, Ms. McGowen told investigators that she worked as a housekeeper at the residence of EM C2 's prior owners, instead of at EMC2's offices. (Id. at 4) The show cause letter expressly stated that "[t]his evidence of cost mischarging indicates a serious lack of business integrity that may warrant the debarment ofEMC[2] from Government contracting pursuant to FAR 9.4" (id. at 2).

4. By letter dated January 7, 2013, EMC2 disputed the assertion that the costs for Ms. McGowen's salary were not allowable (app. supp. R4, tab 2 at 2).

5. In 2013, EMC2 resolved the DOJ and AIO investigations (collectively, investigations) by refunding the Navy $249,850.90. The compromise did not expressly provide that the costs incurred in connection with the investigations were allowable. (Compl. ,i 3(c); app. supp. R4, tabs 14-15)

6. EMC2 submitted Final Indirect Cost Rate Proposals (FICRPs) for FY 2010 and 2011 related to the 0125 contract (2010/2011 FICRPs). The 2010/2011 FICRPs are not in the Rule 4 file. EMC2 alleges that the 2010/2011 FICRPs included as 0 ' allowable costs legal costs EMC2 incurred in connection with the investigations (legal costs). (Compl. ,i l(c))

7. On June 30, 2016, EMC2 submitted FICRPs for FY 2012 and FY 2013 (2012/2013 FICRPs). The 2012/2013 FICRPs included as allowable costs over $10,000 oflegal costs. (R4, tab 4 at 94, 108-09, 116)

8. The Defense Contract Audit Agency (DCAA) audited the 2010/2011 FICRPs (2010/2011 audit), allegedly between January 10, 2017 and January 24, 2017. The final audit report for the 2010/2011 audit is not in the Rule 4 file. (Compl. ,i l(a)-(b)) However, there is evidence that the DCAA concluded that EMC2 should be penalized for including expressly unallowable costs. Nevertheless, the contracting officer (CO) waived the penalties for including expressly unallowable costs in EMC2's 2010/2011 FICRPs pursuant to FAR 42.709-5(c). (App. supp. R4, tab 10)

9. On January 10, 2017, DCAA commenced an audit of the 2012/2013 FICRPs (2012/2013 audit) (app. supp. R4, tab 5). The 2012/2013 audit resulted in an August 17, 2017 audit report (2012/2013 audit report). The 2012/2013 audit report

1 The AIO originally sent the show cause letter on November 5, 2012, but the letter did not reach EMC2 due to a change of address. The AIO then sent the letter to

C the new address on December 10, 2012. (App. supp. R4, tab 1 at 1-2) 2 £\ questioned the allowability of the legal costs under FAR 31.205-4 7 (b )( 4 ). EMC2 did

I"" not withdraw the 2012/2013 FICRPs prior to the DCAA audit. (R4, tab 4)

10. On January 9, 2018, the CO issued a final decision (COFD), assessing a

I penalty in the amount of$53,614, including interest, due to the inclusion of the legal costs in the 2012/2013 FICRPs. The COFD also rejected EMC2's request for a waiver of

I the penalty for the 2012/2013 FICRPs. (R4, tab 5)

11. This appeal followed. t DECISION

I. The Standards for Summary Judgment

Summary judgment will be granted if a moving party has shown that there are no genuine issues of material fact, and it is entitled to judgment as a matter of law. Celotex Corp. v. Catrett, 477 U.S. 317,322 (1986). A non-movant seeking to defeat summary judgment by suggesting conflicting facts must set forth specific facts showing that there is a genuine issue for trial. Anderson v. Liberty Lobby, Inc., 477 U.S. 242,248 (1986). In deciding summary judgment motions, we do not resolve controversies, weigh evidence, or make credibility determinations. Liberty Lobby, 477 U.S. at 255. Moreover, we draw all reasonable inferences in favor of the non-movant. Id.

II. Penalty

The government is entitled to judgment as a matter of law on EMC2' s claim that the government improperly imposed the penalty because there is no genuine issue of material fact but that the legal costs were expressly unallowable. "If the head of the agency determines that a cost submitted by a contractor in its proposal for settlement is expressly unallowable under a cost principle ... , the head of the agency shall assess a penalty." 10 U.S.C. § 2324(b); see also FAR 42.709-3. An expressly unallowable cost is "a particular item or type of cost which, under the express provisions of an applicable law, regulation, or contract, is specifically named and stated to be unallowable." FAR 31.001. It is the government's burden to show that it was unreasonable under all of the circumstances for a person in the contractor's position to conclude that the cost was allowable. Luna Innovations, Inc., ASBCA No. 60086, 18-1 BCA iJ 36,919 at 179,871; Gen. Dynamics Corp., ASBCA No. 49372, 02-2 BCA ,i 31,888 at 157,570, rev 'din part on other grounds, Rumsfield v. Gen. Dynamics Corp., 365 F.3d 1380 (Fed. Cir. 2004).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Energy Matter Conversion Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/energy-matter-conversion-corporation-asbca-2018.