Tennessee Valley Authority v. Westinghouse Electric Corp.

429 F. Supp. 940, 1977 U.S. Dist. LEXIS 16468
CourtDistrict Court, E.D. Virginia
DecidedApril 8, 1977
DocketCiv. A. 75-0679-R
StatusPublished

This text of 429 F. Supp. 940 (Tennessee Valley Authority v. Westinghouse Electric Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee Valley Authority v. Westinghouse Electric Corp., 429 F. Supp. 940, 1977 U.S. Dist. LEXIS 16468 (E.D. Va. 1977).

Opinion

MEMORANDUM

MERHIGE, District Judge.

Plaintiff, Tennessee Valley Authority (TVA), brings this action against the defendant, Westinghouse Electric Corporation (Westinghouse), for an alleged breach of contract. The plaintiff seeks injunctive, declaratory and monetary relief. Jurisdiction is alleged pursuant to 28 U.S.C. § 1345. This action was originally filed in the United States District Court for the Eastern District of Tennessee and subsequently transferred to this Court by an Order of the Judicial Panel on Multidistrict Litigation. In re Westinghouse Electric Corporation Uranium Contracts Litigation, 405 F.Supp. 316 (Jud.Pan.Mult.Lit.1975).

The instant matter comes before the Court on the defendant’s motion to (1) enjoin TVA from pursuing administrative remedies initiated August 3, 1976 under a clause of an alleged contract; (2) modify the Court’s Order of February 3, 1976; and the plaintiff’s motion to vacate the Court’s Order of October 12, 1976 granting leave to Westinghouse to amend its answer. The issues have been briefed and argued by counsel and are ripe for disposition.

Westinghouse is alleged to have entered into contracts with a number of utility companies, including TVA, to supply uranium to be used as fuel in various nuclear power plants. These lawsuits were precipitated by a notice sent by Westinghouse on September 8, 1975 to the utilities stating that the uranium contracts were no longer “commercially practicable” due to unforeseen developments in the world uranium market and, therefore, Westinghouse would not be able to fully perform under those contracts. The plaintiff thereafter filed this action which, as heretofore noted, was transferred to this Court in December of 1975.

*942 TVA’s complaint, in part, involves the extent, if any, of the defendant’s obligation to supply uranium to be used in Sequoyah Unit 2 (Sequoyah Fuel Contract). This contract contains a “Disputes Clause” which requires any dispute arising under the contract to be resolved by TVA’s Contracting Officer. A limited appeal is available under the clause in issue. 1 Also relevant to the instant motions is the Court’s Order of February 3, 1976. That order, consented to by TVA, requires Westinghouse to deliver specified quantities of uranium to TVA “in accordance with the respective contracts or agreements alleged to exist with [TVA] at times and prices specified in each contract or agreement . . .. ”

Westinghouse has taken the position that under its contract with TVA, it is required to supply uranium only if the delivery date of this uranium is on or before September 1,1977. It is further alleged that under the contract the scheduled date of delivery is linked to the fuel loading date which, in turn, is dependent upon the completion of construction of Sequoyah Unit 2. 2 Prior to May 27, 1976, the scheduled delivery date, consistent with plant construction, was August 31, 1977. Thus, under the defendant’s interpretation of the contract, it was obligated to supply the uranium. By letter dated May 27, 1976, TVA advised the United States Nuclear Regulatory Commission that Sequoyah Unit 2 was experiencing construction delays and, therefore, the scheduled fuel loading date would be postponed until July of 1978. Thus, according to Westinghouse, the scheduled delivery date of the uranium under the contract would be pushed back until April or May of 1978. As the scheduled delivery date now falls beyond the September 1, 1977 deadline, Westinghouse submits that it is relieved of its obligation to supply uranium under the contract.

Westinghouse advanced this position to TVA’s Contracting Officer by a letter dated July 27, 1976. Needless to say, TVA does not share the defendant’s view as to its obligations. Acting pursuant to the Disputes Clause of the contract, the Contracting Officer determined that TVA — not Westinghouse — had the right to set the scheduled delivery date and that such date had been fixed at August 31, 1977. Westinghouse filed an appeal to preserve its *943 rights under the contract and then filed this motion to enjoin further administrative proceedings.

TVA maintains that this Court has no jurisdiction over the dispute concerning the scheduled delivery date for the Sequoyah Fuel Contract until the defendant has exhausted its administrative remedies available under the Disputes Clause. It is well settled that such a clause is valid and, where applicable, precludes judicial intervention into a controversy prior to the exhaustion of the appeal provisions of the contract. See S & E Contractors v. United States, 406 U.S. 1, 8-9, 92 S.Ct. 1411, 31 L.Ed.2d 658 (1972); Crown Coat Front Co. v. United States, 386 U.S. 503, 512, 87 S.Ct. 1177, 18 L.Ed.2d 256 (1967); United States v. Bianchi & Co., 373 U.S. 709, 713, 83 S.Ct. 1409, 10 L.Ed.2d 652 (1963); United States v. Joseph A. Holpuch Co., 328 U.S. 234, 239, 66 S.Ct. 1000, 90 L.Ed. 1192 (1946); United States v. Blair, 321 U.S. 730, 736, 64 S.Ct. 820, 88 L.Ed. 1039 (1944).

Rights secured under a contract, however, may be waived by the parties. Universal Fiberglass Corp. v. United States, 537 F.2d 393, 397 (Ct.Cl.1976); John C. Kohler Co. v. United States, 498 F.2d 1360, 1365, 204 Ct.Cl. 777 (1974); Kenneth Reed Construction Corp. v. United States, 475 F.2d 583, 590, 201 Ct.Cl. 282 (1973). Specifically, a government agency may waive its rights under a disputes clause. See, e. g., Edward Levy Metals, Inc., 199 Ct.Cl. 1019 (1972); Hegeman-Harris & Co. v. United States, 440 F.2d 1009, 1011, 194 Ct.Cl. 574 (1971); Nager Electric Co. v. United States, 396 F.2d 977, 981, 184 Ct.Cl. 390 (1968).

A waiver of the right to have an issue resolved pursuant to a disputes claim may be explicit as in Hegeman-Harris & Co. v. United States, supra, or implied by the agency’s conduct as in Edward Levy Metals, Inc., supra and Nager Electric Co. v. United States, supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Joseph A. Holpuch Co.
328 U.S. 234 (Supreme Court, 1946)
United States v. Carlo Bianchi & Co.
373 U.S. 709 (Supreme Court, 1963)
Crown Coat Front Co. v. United States
386 U.S. 503 (Supreme Court, 1967)
S&E Contractors, Inc. v. United States
406 U.S. 1 (Supreme Court, 1972)
Hegeman-Harris & Company, Inc. v. The United States
440 F.2d 1009 (Court of Claims, 1971)
In Re Westinghouse Electric Corp. Uranium Contracts Litigation
405 F. Supp. 316 (Judicial Panel on Multidistrict Litigation, 1975)
Hegeman-Harris & Co. v. United States
196 Ct. Cl. 807 (Court of Claims, 1971)
Edward Levy Metals, Inc.
199 Ct. Cl. 1019 (Court of Claims, 1972)
Kenneth Reed Construction Corp. v. United States
475 F.2d 583 (Court of Claims, 1973)
John C. Kohler Co. v. United States
498 F.2d 1360 (Court of Claims, 1974)
Universal Fiberglass Corp. v. United States
537 F.2d 393 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
429 F. Supp. 940, 1977 U.S. Dist. LEXIS 16468, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-valley-authority-v-westinghouse-electric-corp-vaed-1977.