Beechwood Gun Club, Inc. v. City of Beacon

153 Misc. 358, 275 N.Y.S. 249, 1933 N.Y. Misc. LEXIS 1846
CourtNew York Supreme Court
DecidedDecember 29, 1933
StatusPublished
Cited by4 cases

This text of 153 Misc. 358 (Beechwood Gun Club, Inc. v. City of Beacon) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beechwood Gun Club, Inc. v. City of Beacon, 153 Misc. 358, 275 N.Y.S. 249, 1933 N.Y. Misc. LEXIS 1846 (N.Y. Super. Ct. 1933).

Opinion

McLaughlin, J.

The plaintiff was the owner of property in the vicinity of the defendant which was needed by the latter for a water reservoir. The evidence is that a Mr. Kelly, the city attorney of the defendant, began negotiations with the plaintiff which, on August 4, 1930, resulted in the former deeding certain of its property with a building on it, and the defendant agreed to build another [359]*359clubhouse for the plaintiff and to install in it a water system sufficient to meet the requirements of the plaintiff. It is conceded that the defendant did build a new clubhouse and that it was destroyed by fire on May 30, 1932. There appeared to be no dispute as to the kind of building the defendant built, for the plaintiff went into possession and accepted it without objection. Its sole complaint here is that a proper water system was never installed. Plaintiff comes into court and says that although it was in possession of this building, the defendant should be assessed in damages not oifiy for the value of the building but also for the value of the goods and materials placed in it by the plaintiff. Had this building been destroyed before the plaintiff occupied it, then the defendant would •undoubtedly have been responsible for the loss of the building but not what plaintiff placed therein and would be obliged to rebuild the building at its own cost and expenses.

In case of contracts for the construction of a building or the like it is the accepted general rule that the risk of the accidental destruction of the building before its completion is on the contractor, and its accidental destruction, without his fault, is no excuse for his failure to perform the contract, and in such a case the contractor not only cannot recover for the work, labor and materials furnished, but is liable for damages for his failure to perform.” (Clark N. Y. Law of Cont. § 976; Tompkins v. Dudley, 25 N. Y. 272; Norton v. Fancher, 92 Hun, 463.)

If, however, in the case of the construction of a building the contract has been fully performed and the building accepted or approved by the owner’s architect or engineer, the loss, if any, is with the owner. (De Remer v. Brown, 36 App. Div. 634; affd., 165 N. Y. 410.) This point was not raised in the Court of Appeals.

The facts show conclusively that the plaintiff had taken over the possession of the building and was using it, having placed its furniture and ammunition in it. It would appear that there was nothing left to be done under the contract except for the defendant to furnish either by tap or pipe line, sufficient waters as may be required by the second party in its building or shack upon its said properties.”

When the plaintiff took over the possession of this building and placed its goods there, then a different situation was presented. Had the plaintiff not been in possession, then the defendant would be bound to build another house and install another water system. There is no contradiction of the testimony of the plumber’s employees to the effect that water was running in these premises just before the fire and that the installation had been completed, and this of itself would establish the fact that the contract was [360]*360completed in its entirety and the loss by fire or other accident not due to the fault of the defendant must fall upon the plaintiff. (Sewell v. Underhill, 197 N. Y. 168.)

This acceptance and occupancy by the plaintiff of the house was a waiver of any possible breach by the defendant by reason of any delay in installing a proper water system and such delay was thereby excused. It is true that no time for performance is fixed in the contract but that carries with it the idea of reasonable time. (Taylor v. Goelet, 142 App. Div. 467; affd., 208 N. Y. 253.) The proof in this case shows that water could not be put in the reservoir until August 22, 1931. (Defendant’s Exhibits “A” and B.”) Even after that time, which is in reality an extension of the time originally contemplated by the parties, the defendant had a reasonable time to install a water system. (Darrow v. Cornell, 12 App. Div. 604.) Let us assume that there was unreasonable delay after this date. Still there was no default or breach of contract on the part of the defendant by reason of the delay. Even if the time had been fixed in the contract (and the rule applies equally to this case), before the plaintiff could put the defendant in default so as to cause a breach on its part, it is incumbent on it to demand performance within a certain time. Where a fixed time has ceased to be an element in the contract, neither party can put the other in default without some notice or demand of performance.” (Lawson v. Hogan, 93 N. Y. 39, at p. 44.) I cannot find any breach of this contract on the part of the defendant. The action is based upon a written agreement dated August 4, 1930. This instrument is but part of a transaction whereby the defendant obtained from the plaintiff some land and the building on it and among other things agreed to erect a building on the remaining portion of the plaintiff’s land and to supply it water in accordance with the terms of this instrument. At first blush it would appear doubtful if the agreement is complete as to its terms. Further thought brings but one conclusion, and that is that the instrument is complete as to its terms except the time when the water system was to be installed. Parol evidence would be proper to show the time for performance but no more. A fire has occurred and the court is asked to permit parol testimony concerning the protection of this building against fire so that insurance might be obtained. The plaintiff now says that at the time the contract was made such an agreement was made orally and that on several subsequent occasions the same matters were spoken of and complaints made by reason of the failure of the defendant to install a water system. This must be rejected because it adds something new to the written agreement. Sufficient water as may be required in the building [361]*361is certainly a far different thing than is ordinarily required for fighting fire and thus give the right to insurance. This was something so different from the language of the instrument that its proof by parol evidence must be rejected. It is the law in this State that the court should exclude all extrinsic evidence which is offered to show an additional term of the contract which the parties might have inserted in the written instrument but which was not included in it. (Edison El. Ill. Co. v. Thacher, 229 N. Y. 172; Interstate Chem. Corp. v. Duke, 176 App. Div. 684; affd., 226 N. Y. 610; Loomis v. N. Y. C. & H. R. R. R. Co., 203 id. 359.) The plaintiff argues that this parol evidence is admissible to show the surrounding circumstanced attending or surrounding and up to or inducing the execution of the written contract. In this the plaintiff is in error. To show such circumstances by parol evidence there must be a doubtful meaning in the writing. It is admissible only when there is no possible way to gather and to ascertain the intention of the parties from the instrument itself. (Middleworth v. Ordway, 191 N. Y. 404; U. S. Printing & Lithograph Co. v. Powers, 233 id. 143; Williams v. Gridley, 110 App. Div. 525; affd., 187 N. Y. 526; Dent v. North American Steamship Co., 49 id. 390; Dady v. O’Rourke, 172 id. 447; Murdock

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Central Trust Co. v. Eastman Development Corp.
54 A.D.2d 609 (Appellate Division of the Supreme Court of New York, 1976)
Slevin v. Siegel
65 Misc. 2d 3 (New York Supreme Court, 1970)
Southern Railway Company v. City of Birmingham
122 So. 2d 599 (Supreme Court of Alabama, 1960)
Potts v. City of Utica
86 F.2d 616 (Second Circuit, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
153 Misc. 358, 275 N.Y.S. 249, 1933 N.Y. Misc. LEXIS 1846, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beechwood-gun-club-inc-v-city-of-beacon-nysupct-1933.