Elzey v. City of Winterset

172 Iowa 643
CourtSupreme Court of Iowa
DecidedNovember 26, 1915
StatusPublished
Cited by4 cases

This text of 172 Iowa 643 (Elzey v. City of Winterset) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elzey v. City of Winterset, 172 Iowa 643 (iowa 1915).

Opinion

Weaver, J.

i Damages : liquidated damages or penalty : construction of stipulation : paving contracts. In May, 1912, the city of Winterset entered into a contract with the plaintiff for the paving of certain streets. For reasons unnecessary here to consider, the work was divided into two parts and separate written agreements executed and later, upon certain changes being agreed upon and an additional block included in the scheme of improvements, a third writing was made, covering a part of the work. The entire work, however, seems to have constituted a single improvement and it is, perhaps, not very material whether the various writings may fairly be considered parts of a single contract or are treated as several and distinct. As originally drawn, the work provided for in the first two writings was to be completed on or before October 1, 1912; while that described in the supplemental writing was to be completed on or before November 15, 1912. The several writings each contain a clause reading as follows:

‘ ‘ If the said party of the first part shall fail to complete said work by date specified herein, an amount equal to the sum of $25 per day, as liquidated damages for breach of this [645]*645contract, shall be payable to the city of "Winterset, for each day of delay thereafter, until completion of said work, and shall be deducted from the amount herein stipulated to be paid to the said party of the first part upon final settlement. ’ ’

There is nothing in the record to show how nearly the job was completed on October 1st or on November 15th; but the certificate of the city engineer is to the effect that the final completion of the work described in the first agreement was not effected until November 13, 1912, and that described in the other writings until January 3 or 4, 1913. There is also evidence tending to' show that, before any default was made, there was some oral agreement or arrangement by which the contract period was extended two weeks. After the work was done, the city proceeded to ascertain the full cost of the improvement on the basis of the contract price thereof, including also all engineering and’ other expenses incurred, and levied special assessments therefor upon the abutting property, making no reduction therefrom on account of the penalty or damages incurred by the contractor for failure to do the work within the contract period. These assessments were either collected in cash or provided for by certificates payable in installments. Before this suit was begun, the city paid the plaintiff, in money, bonds and certificates, the full amount of the contract price of the work, less the sum of $3,600, which it withheld and still withholds on the claim that, under the penalty or damage clause above quoted from the contract, it is entitled to retain as liquidated damages, the rate of $25 per day on each of the three written agreements.

The petition herein alleges full performance of his contract by plaintiff and demands recovery of the sum which the city withholds from the agreed price of his work. The city in answer admits the retention of the money, but alleges its right to do so substantially as above stated. Replying to the claim thus asserted, the plaintiff insists that the clause of the contract on which the city relies was intended to [646]*646provide for a penalty only, and not liquidated damages, and that no actual damages resulted to the city because of the delay. He further alleges that such delay as did occur was caused by the city itself in failing to do the preparatory work which it was required to do before the paving could be laid.

The trial court found that, under the language of the contract and the' circumstances attending the transaction, the damage clause is to be treated as providing a penalty only, and that, in the entire absence of any showing of actual damage, the city was bound to pay the full contract price. It found also that the progress of the work by plaintiff was in fact delayed by the failure of the city to grade the streets preparatory to paving and to put in the storm sewers and drains which were to precede the work, done under the contract; and that, even if the contract were to be construed as providing for liquidated damages, none could be equitably allowed under the circumstances. Judgment being entered for the plaintiff for $3,600, the defendant appeals.

Whether a given clause of a contract provides a penalty or liquidated damages for its breach is often a troublesome question; and more frequently than otherwise, its solution is made to turn upon the peculiar facts of the individual case rather than upon any controlling precedents. The fact that the contract uses the express words “penalty” or “liquidated damages” is not at all conclusive' as to the character of the stipulation. The court will look at the whole instrument and the subject-matter of the contract and give it such interpretation as, under all the circumstances, will effect the purpose which the parties intended to subserve. To this end, the court may consider evidence of extraneous facts and circumstances tending to explain or make clear the real nature of the stipulation. It is said by Mr. Pomeroy that, if the intent is at all doubtful, the tendency of the courts is in favor of the interpretation which makes the sum a penalty. 1 Pomeroy’s Equity Juris. (Bd Ed.), Sec. 440. Indeed, the court will not be bound by the expressed intent of the parties, if the stipulation shall, in view of the entire record, be found inequitable.

[647]*647The first consideration in sustaining a stipulation for liquidated damages appears to be the difficulty or impossibility, in some eases, of ascertaining and measuring the damages actually sustained by a breach of the contract. But this is not always sufficient. The tendency of the courts in recent years has been to look into all the circumstances and give effect to such an agreement only so far as equity and good conscience will permit; and if the'sum stipulated is out of reasonable proportion to the loss or injury actually sustained or reasonably to be anticipated, it will be treated as a penalty only. Bayse v. Ambrose, 28 Mo. 39; Jacquith v. Hudson, 5 Mich. 123; Schrimpf v. Tenn. Mfg. Co., 86 Tenn. 219; Seeman v. Biemann, 108 Wis. 365; Sanders v. Carter, 91 Ga. 450; Wilhelm v. Eaves, 21 Ore. 194; Cochran v. Peoples Ry. Co., 113 Mo. 359; Condon v. Kemper, 47 Kan. 126; Collier v. Betterton, 87 Tex. 440, 442; Wheedon v. American Bonding & Trust Co., 128 N. C. 69; Ward v. Hudson River Building Co., 125 N. Y. 230; Gillilan v. Rollins, 41 Neb. 540 (59 N. W. 893).

In Seeman v. Biemann, supra, the Wisconsin court, considering a stipulation very like the one now before us, saysj

“That brings us to the necessity of determining whether the parties agreed upon $10 a day as the amount to be allowed as damages for each day’s delay, or whether that clause in the contract was intended as a mere security for the completion of the building by the time agreed upon,'hence should be considered as a penalty and recoverable damages be limited to such as proof shows Farr actually sustained.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rohlin Construction Co. v. City of Hinton
476 N.W.2d 78 (Supreme Court of Iowa, 1991)
Engel v. Vernon
215 N.W.2d 506 (Supreme Court of Iowa, 1974)
Shockley v. Paul Davis Dry Goods Co.
205 N.W. 966 (Supreme Court of Iowa, 1925)
Independent School District v. Dudley
195 Iowa 398 (Supreme Court of Iowa, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
172 Iowa 643, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elzey-v-city-of-winterset-iowa-1915.