Cochran v. People's Railway Co.

21 S.W. 6, 113 Mo. 359, 1892 Mo. LEXIS 37
CourtSupreme Court of Missouri
DecidedDecember 31, 1892
StatusPublished
Cited by22 cases

This text of 21 S.W. 6 (Cochran v. People's Railway Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cochran v. People's Railway Co., 21 S.W. 6, 113 Mo. 359, 1892 Mo. LEXIS 37 (Mo. 1892).

Opinion

GrANTT, P. J.

This is a suit at law for a balance on a building contract. Plaintiff claimed $3,285 due him on a contract price of $17,785, for building defendant an office building for its cable railway in the city of St. Louis.

The defendant in its answer claimed certain deductions for omissions made by the architect, also damages by way of counter-claim for defective material and unskillful workmanship, and a counter-claim for a delay of sixty-five days in the completion of the building at the rate of $50 per day as ‘‘liquidated damages.”

The contract contained this stipulation:

‘‘And the party of the first part agrees to begin said work immediately, and push it so as to have it completed on or before the fifteenth day of December next ensuing. And the party of the first part agrees to pay to the party of the second part the sum of $50 per day for every day over the above specified time that the building shall be delayed from completion through the fault of the said party of the first part.”

During a trial before a jury the court held this clause to be a mere penalty and announced that it would try the case upon that theory, and compelled the defendant to show actual damages, to which ruling and announcement defendant excepted. Evidence was then introduced by both parties on the subject of the actual damages sustained by defendant by the delay, and ■defendant was by the court confined to the general rental value of the building without considering its special [362]*362value or use to defendant or defendant’s business, to-•which defendant likewise excepted. The court also refused an instruction asked by defendant to the effect that under the contract read in evidence defendant was entitled under its first counter-claim to $50 per day for every day which the jury might find from the evidence that the building was delayed from completion beyond the fifteenth day of December, 1889, through the fault of plaintiff; to which refusal defendant again excepted.

If the circuit court was wrong in its interpretation of the contract in this case, and the stipulation for $50 a day for each day the building was delayed was a. legitimate ascertainment of the damages that defendant would suffer by the delay, and not a penalty provided against a breach of the contract, then the other question as to measure of damages will become immaterial, otherwise important.

In this case the amount fixed is denominated in the contract neither as “penalty” or “liquidated damages.” The courts now generally agree that neither of these terms are conclusive in the construction to be placed on the agreement. To enable a court to determine whether the sum of $50 a day, which the contract provides plaintiff shall pay defendant, shall be regarded as liquidated damages, or as a penalty, must be gathered from the subject-matter of the contract, the language employed and the intention of the parties.

Various rules of interpretation have been adopted by the courts in their efforts to compensate the injured party for his loss, and at the same time avoid what they deem an unconscionable advantage over his adversary. The canons of construction applied by the courts are not arbitrary, nor has any respectable court assumed to deny to parties competent the right to make their own contracts. They have simply said that, reading [363]*363the whole contract with reference to its subject-matter and the circumstances of the parties, under one state of facts, the stipulation created merely a penalty for the faithful performance of the agreement; and, under other circumstances, that it was liquidated damage.

In Morse v. Rathburn, 42 Mo. 594, Judge Wagner announced the rule in this state to be, “where the parties to a contract, in which the damages to be ascertained growing out of a breach are uncertain in amount, mutually agree that a certain sum shall be the damages in case of a failure to perform, in language plainly expressive of such agreement, and when the intention is plain and palpable, there is no law * * * to justify the courts in giving the contract a different, construction or saying that the parties meant something else. Where the sum is greatly disproportionate to either, the actual or presumed damage, showing that one side was the victim of oppression, a court exercising equity powers would interfere.”

The element of uncertainty, the fact that the damage was incapable of exact ascertainment, has generally inclined the courts to construe the sum agreed upon as liquidated damages. Where, however, the amount stipulated to be paid by the defaulting party is disproportionate to the probable damage or to a readily ascertainable loss, the courts treat it as a penalty, in the nature of a security for performance. Many adjudicated cases in England, Ganada and the states of our Union uphold the right of parties to stipulate that, for delay in the performance of building contracts, the builder shall pay a certain amount per day or week for every day or week the completion of the contract is delayed beyond the time fixed. 1 Sedgwick on Damages [8 Ed.] sec. 419, and cases cited in note a. An examination of these cases, howev.er, confirms the [364]*364view that the amount so agreed upon as liquidated ‘damages must not be unreasonable and out of proportion to the probable damages.

Applying to this case the ordinary tests, is it or not ■unreasonable as liquidated damages ? Viewing it from the point of an investment, the capital was $18,000, and for sixty-five days this capital yielded no income. Allowing ten per cent. — a large interest on so large a a sum — and we find $325 would compensate for the use of the money as a loan or mere investment. If we regard the testimony as to rental, the highest sum testified to by Mr. Green, the' president of defendant, was $2,500 a year. The loss in rental at this rate would be $451.38. By the laws of compensation then, it would appear that defendant could not have reasonably suffered in actual damages the amount it claims under this clause of the contract. At the rate stipulated the damages would have amounted in a year to a sum almost as large as the capital invested or total cost of the building.

We are constrained therefore to hold that this stipulation was intended as a penalty to compel the performance of this contract, and not an agreement for said sum as stipulated damages. Potter v. McPherson, 61 Mo. 240. This necessitates an examination into the ruling of the court that defendant could only recover the general rental value of this building and excluding the evidence of its rental value to the defendants. Now it seems evident that a mere general rental would not compensate this defendant for the loss of the use of this office building, which at a great outlay it had contracted to have built in order that it might have conveniences and security in the prosecution of its business. In the first^place, the witnesses all agree that no such buildings are generally erected for rent. There is no demand for such. Again this building was erccLud in [365]*365a portion of the city where rents are comparatively low; but being immediately adjoining defendant’s power-house and on its line, affords it every facility it desires; but its very locality would depreciate its rental value to others.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stubblefield v. Montgomery Ward & Co.
98 P.2d 14 (Oregon Supreme Court, 1940)
Blaine v. Huttig Sash & Door Co.
105 S.W.2d 946 (Missouri Court of Appeals, 1937)
First Nat. Bank of Elyria v. Equipment Co.
285 S.W. 779 (Missouri Court of Appeals, 1926)
Sabol v. St. Louis Cooperage Co.
282 S.W. 425 (Supreme Court of Missouri, 1926)
Stipel v. Piggott
269 S.W. 942 (Missouri Court of Appeals, 1925)
Simpson v. Wells
237 S.W. 520 (Supreme Court of Missouri, 1922)
Mount Vernon Car Manufacturing Co. v. Hirsch Rolling Mill Co.
227 S.W. 67 (Supreme Court of Missouri, 1920)
Elzey v. City of Winterset
172 Iowa 643 (Supreme Court of Iowa, 1915)
Ward v. Haren
167 S.W. 1064 (Missouri Court of Appeals, 1914)
Buchanan v. Louisiana Purchase Exposition Co.
149 S.W. 26 (Supreme Court of Missouri, 1912)
Winklebleck v. Butler County Bank
131 S.W. 905 (Missouri Court of Appeals, 1910)
Thompson v. St. Charles County
126 S.W. 1044 (Supreme Court of Missouri, 1910)
Ross v. Loescher
116 N.W. 193 (Michigan Supreme Court, 1908)
Warwick v. North American Investment Co.
87 S.W. 78 (Missouri Court of Appeals, 1905)
Coen & Conway v. Birchard
100 N.W. 48 (Supreme Court of Iowa, 1904)
Currell v. Hannibal & St. Joseph Railroad
71 S.W. 113 (Missouri Court of Appeals, 1902)
Radloff v. Haase
96 Ill. App. 74 (Appellate Court of Illinois, 1901)
Thorn & Hunkins Lime & Cement Co. v. Citizens Bank
59 S.W. 109 (Supreme Court of Missouri, 1900)
Parlin & Orendorff Co. v. Boatman
84 Mo. App. 67 (Missouri Court of Appeals, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
21 S.W. 6, 113 Mo. 359, 1892 Mo. LEXIS 37, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cochran-v-peoples-railway-co-mo-1892.