Thompson v. St. Charles County

126 S.W. 1044, 227 Mo. 220, 1910 Mo. LEXIS 97
CourtSupreme Court of Missouri
DecidedMarch 31, 1910
StatusPublished
Cited by27 cases

This text of 126 S.W. 1044 (Thompson v. St. Charles County) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thompson v. St. Charles County, 126 S.W. 1044, 227 Mo. 220, 1910 Mo. LEXIS 97 (Mo. 1910).

Opinion

LAMM, P. J.

Plaintiff contracted in writing to build a courthouse for the county of St: Charles for the suin of $37,349; to be paid in instalments. The last instalment was to be $5349. Alleging full performance and claiming the last instalment with certain items of extra work, plaintiff sued in one count on the contract and in another on a quantum meruit for $5541.84. The latter count and the extras were finally abandoned and the suit stood as one for said last contract instalment, viz., $5349. Verdict and judgment for $2019. Plaintiff appeals.

The answer admits the contract, but denies performance, etc., and pleads a provision requiring the work completed by December 31, 1901, and that for a default in that regard plaintiff should pay defendant “as liquidated damages” ten dollars for each and every day from that date until the building was completed; that plaintiff was' given an extension of time, viz., of 26 days from December 31, 1901, to January 26, 1902, but breached the contract in that he did not complete the work.until December 26, 1902, and that the liquidated damages for such failure were $3330; [225]*225that the balance dne plaintiff was $2019; and that on February 9, 1903, defendant tendered plaintiff said sum and has ever since been ready to pay the same and now brings it into court.

By reply plaintiff puts a construction on the contract, vis., that the “liquidated damages” were merely a penalty, that the real damages from default in time are susceptible of easy calculation and ascertainment with certainty, etc. It then, in a dozen specifications, makes allegations explaining how time was lost. One was to the effect that 55 days were lost because defendant neglected to give plaintiff possession of the premises and the lines and level of the building on the 1st day of March, 1901, as provided in the sixth clause of the contract (presently to be set forth). The seventh clause of the contract, as will be seen in a little while, provided for an extension of time in certain contingencies by written claim therefor at the time with an award by the superintendent certifying the amount of the additional time, or, on failure, to agree, an arbitration as provided in the third clause of the contract.

.The reply did not plead a claim made for additional time, either oral or in writing, or a waiver of a written claim or of the arbitration clause, or any attempt to arbitrate, or to obtain an allowance from the superintendent, or any fraud, mistake, caprice, or wrongful or arbitrary conduct on the part of the superintendent in that regard. In fact, it says nothing about a claim, award or arbitration. It merely sets forth- that because of certain errors, extra work, changes and alterations. and because of a failure to approve plaintiff’s bond, 289 days were lost, for which plaintiff should be allowed

The contract bore date February 11, 1901. The clauses material here are the third, sixth and seventh.

The third provides for changes, omissions, etc., [226]*226and it was thereby agreed that the superintendent should make a fair and reasonable valuation of the work added or omitted and the contract price should be increased or diminished thereby as the case may be. In case such valuation was not agreed to, the contractor should go on under the written order of the superintendent and do the work and the valuation 'to be added or subtracted should be referred to three disinterested arbitrators, one to be appointed by each •party and the two to choose a referee — a decision of any two to be final and binding, the expenses to be share and share alike.

The sixth and seventh follow:

“Sixth: The contractor shall and will proceed with the said work, and every part and detail thereof, in a prompt and diligent manner, and shall and will wholly finish the said work according to' the said drawings and specifications, and this contract, on or before the thirty-first day of December, in the year one thousand nine hundred and one (provided, that possession of the premises be given the contractors, and lines and levels of the building furnished him on or before the first day of March, in the year one thousand nine hundred and one), and in default thereof the contractor shall pay to the owner ten dollars for every day thereafter that the said work shall remain unfinished as and for liquidated damages.
“Seventh: Should the contractor be obstructed or delayed in the prosecution or completion of the work by the neglect, delay or default of any other contractor; or by any alteration which may be required in the said work; or by any damages which may happen thereto by fire, or by the usual action of the elements, or otherwise; or - by the abandonment of the work by the employees through no fault of the contractor, then there shall be an allowance of additional time beyond the date set for the completion of said work; but no such allowance shall be made [227]*227unless a claim is presented in writing at the time of such obstruction or delay. The superintendent shall award and certify the amount of additional time to be allowed; in which case the contractor shall be released from the payment of the stipulated damages for the additional time so certified andl no more. The contractor may appeal from such award to arbitrators, constituted as provided in article 3 of this contract.”

Mr. Legg was architect and superintendent of the building. On behalf of plaintiff there was some evidence tending to show that the lines and level to be given by defendant (see the sixth clause of the contract supra) were not given until sometime in April, 1901, instead of before March 1st, as stipulated. Contra, defendant’s, testimony tended to show they were given strictly in accordance with the sixth clause, i. e., before March 1, 1901. That issue was well put to the jury and found against plaintiff.

During a long running colloquy between court and counsel upon the legal effect of said clause seven, it was suggested by the court that plaintiff would be allowed to prove any delay caused by any action of superintendent Legg outside of the terms of the contract, the court saying, inter alia, “Now if there are other delays, resulting from any affirmative interference on the part of the owner or on the part of the superintendent, who under the terms of this contract represents the owner, delays that do not fall within the terms of this section (clause 7) bufare caused in other ways and for other reasons, then the contract would simply be silent in that regard, and the contractor would be entitled to show those delays, I think, under the general provisions of common law, that where there is a contract to do a certain thing within a certain time that contract would always be construed with reference to his course of operation being uninterrupted by the other party.” • Plaintiff did not accept the offer made by the court to show any de[228]*228lays not falling -within the terms of clause seven, but did make offers to show delays caused by alterations, extras, etc., contemplated by that clause. These offers were refused unless plaintiff promised to bring himself within the provisions of that clause relating to a claim of allowance of additional time in writing made to the superintendent, to be followed by an award from him or by arbitration in case of a difference as set forth in that clause.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lee v. Peters
250 S.W.3d 783 (Missouri Court of Appeals, 2008)
Luna v. Smith
861 S.W.2d 775 (Missouri Court of Appeals, 1993)
Sides Construction Co. v. City of Scott City
581 S.W.2d 443 (Missouri Court of Appeals, 1979)
State Ex Rel. Bonzon v. Weinstein
514 S.W.2d 357 (Missouri Court of Appeals, 1974)
R. W. Farmer Construction Co. v. Carter
454 S.W.2d 30 (Supreme Court of Missouri, 1970)
Basore v. Allstate Insurance Company
374 S.W.2d 626 (Missouri Court of Appeals, 1963)
Croker v. Consolidated Service Car Co.
365 S.W.2d 524 (Supreme Court of Missouri, 1963)
Gasparini Excavating Co. v. Pennsylvania Turnpike Commission
187 A.2d 157 (Supreme Court of Pennsylvania, 1963)
Capital City Motors, Inc. v. Thomas W. Garland, Inc.
363 S.W.2d 575 (Supreme Court of Missouri, 1962)
Manufacturers Casualty Insurance v. Sho-Me Power Corp.
157 F. Supp. 681 (W.D. Missouri, 1957)
Francis v. Saleeby
282 S.W.2d 167 (Missouri Court of Appeals, 1955)
Wilt v. Waterfield
273 S.W.2d 290 (Supreme Court of Missouri, 1954)
Dugan v. Trout
271 S.W.2d 593 (Missouri Court of Appeals, 1954)
United States v. Henke Const. Co.
157 F.2d 13 (Eighth Circuit, 1946)
Arbitration of Pope Construction Co. v. State Highway Commission
92 S.W.2d 974 (Missouri Court of Appeals, 1936)
Henry Shenk Co. v. Erie County
178 A. 662 (Supreme Court of Pennsylvania, 1935)
Duval County v. Charleston Engineering & Contracting Co.
134 So. 509 (Supreme Court of Florida, 1931)
Goffe v. National Surety Co.
9 S.W.2d 929 (Supreme Court of Missouri, 1928)
Davis v. Jasper County
300 S.W. 493 (Supreme Court of Missouri, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
126 S.W. 1044, 227 Mo. 220, 1910 Mo. LEXIS 97, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thompson-v-st-charles-county-mo-1910.