R. W. Farmer Construction Co. v. Carter

454 S.W.2d 30, 1970 Mo. LEXIS 1024
CourtSupreme Court of Missouri
DecidedApril 13, 1970
DocketNo. 54233
StatusPublished

This text of 454 S.W.2d 30 (R. W. Farmer Construction Co. v. Carter) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R. W. Farmer Construction Co. v. Carter, 454 S.W.2d 30, 1970 Mo. LEXIS 1024 (Mo. 1970).

Opinion

BARRETT, Commissioner.

This cause originated as a suit by a general contractor, R. W. Farmer Construction Company, (in fact Mr. R. W. Farmer) to recover damages for breach of a building contract, particularly for extra materials and work, and to establish a mechanic’s lien, against the owners, Frank B. Miller and George L. Carter, of the shopping center west of Liberty, known as the Liberty Landing Center. Originally Farmer sought to recover the total sum of $41,089.78 but, admittedly, Miller (throughout representing all defendants) was entitled to a credit of $2941.47 and in the end the court allowed Farmer $5595.27 and thus upon his appeal the jurisdictional amount involved is his claim of the total difference in demands — $32,553.04, the latter consisting of numerous items. As against Farmer’s claims for extras and for damages for breach of contract the defendant-respondents, personified in Miller, filed a counterclaim for damages, for unwork-manlike job, for failure to furnish pursuant to contract numerous items, 24 in number, liquidated damages and other claims, all said to total $43,748.86. Unlike one or more of the cases relied on by the appellant, the parties here waived a jury and at appellant’s special instance and request the Honorable Arthur W. Rogers, the circuit court judge of Carroll and Ray Counties, rather than one of the judges of Clay County, was agreed upon as a special judge to hear this cause. After a hearing involving, accounting for and questioning every step in the performance of the contract and very nearly every piece of work and material entering into a shopping-center complex allegedly costing $267,728.-49, the court, as stated, entered judgment in favor of the contractor for $5595.27, adding, due to an after-trial motion, $741.37 interest, and he alone has appealed. Whatever the original totals, the appellant-contractor admits that the defendant-owners paid $226,638.71 and thus on these computations he claimed additional damages and charges for extras totaling $41,089.78.

The first item challenged in detail, one readily separable from all other items, is the court’s allowance to respondents on their counterclaim of liquidated [32]*32damages at $130.00 per day for the period of April 1, 1966 (the specified date of completion) to May 1, 1966, of $3900.00. The appellant makes five attacks on this allowance, that under the terms of the contract the authority to invoke liquidated damages was in the architect only, that the provision was waived, that defendants failed to prove actual damages as a result of delayed completion, that there was no proof that liquidated damages were proportionate to the actual damages sustained and, finally, that he completed construction within the allotted time and therefore liquidated damages could not be assessed.

This five-part argument ignores the plain and unambiguous language of the contract as well as the court’s specific findings. Unlike the case relied on, Southwest Engineering Co. v. Reorganized School Dist. R-9, Mo.App., 434 S.W.2d 743, it is not claimed that the delay was due to the architect and the contract provision here was not dependent on invocation by the architect. Incidentally that case and Franken v. Carpenter, Mo.App., 364 S.W.2d IS, also relied on by the appellant, control and govern adversely virtually every claim made by the appellant. The contract here, in the plainest of language, after providing a completion date “within 180 days from date of signing of contract” provides that “In addition to the above sum specified, the owner will be entitled to $130.00 liquidated damages for every day’s delay beyond the time set for completion. Such sums to be deducted from any monies which may be due the Contractor on the contract.” (Emphasis supplied.) This is a valid provision, “(t)he language employed is aptly chosen to exclude the idea of a mere penalty,” the damages resulting, as in the case of a courthouse, are by no means easy of ascertainment by fixed rules and “(h)aving regard to all these matters this plaintiff voluntarily made a fair contract with defendant putting their own estimate on the damages. Let him keep his word by standing by his contract.” Thompson v. St. Charles County, 227 Mo. 220, 240-241, 126 S.W. 1044; Manufacturers Casualty Ins. Co. v. Sho-Me Power Corp., D.C., 157 F.Supp. 681, (there $100.00 a day liquidated damages for delay in constructing a power line). The court’s finding on this issue was not in the cryptic language of appellant’s briefed item 41 summarizing and listing the court’s findings. The court carefully analyzed this issue, and it may be noted, after deciding all other issues, this matter was decided in conclusion. The court corrected an erroneous impression (one easily fallen into on this record) as to the date of signing to October 2, 1965, and concluded as the Thompson case indicates “that the terms of the contract must be enforced.” The defendants claimed a much larger sum by showing the specific dates beyond the stipulated 180 days their tenants were able to occupy the various sections of the shopping center but the court did not accept this proof in its entirety. Instead the court found, as indicated by its prior findings, that “plaintiff had not fully complied with his contract to that date (April 1, 1966) and that in facts the plans have never been completely carried out; that there is ample credible evidence that defendants had not accepted sole possession until May 1, 1966, and that the delay was due to lack of full performance on the part of plaintiff; that the time of completion to that point was only because defendants took it upon themselves to complete work undone by plaintiff.” (Emphasis supplied.) The court therefore credited the respondents with $3900.00 damages for 30 days’ delay. In the Southwest Engineering case the contractor claimed and was denied 15 days’ liquidated damages for delay, but upon the cause and responsibility for delay and applicable here the court said “the evidence on this question was conflicting and close, and the trial court’s decision depended upon conflicting oral testimony and the credibility of witnesses. We cannot say that we are satisfied its finding should have been otherwise, and therefore we defer to its judgment.” (434 S.W.2d l. c. 748.) The provision here was unambiguous and so there is no place for the auxiliary rule that [33]*33the contract is to be construed against the party drafting it. Hahn v. Forest Hills Const. Co., Mo.App., 334 S.W.2d 383. The structure may have been, as appellant argues, “substantially complete” on April 1, 1966, but whatever “substantial” may mean this particular contractual provision, as the court applied it, plainly said as to liquidated damages, “Such sums to be deducted from any monies which may be due the Contractor on the contract.” Southwest Engineering Co. v. Reorganized Sch. Dist. R-9, supra. The finding is supported as will more certainly appear in considering appellant’s other claims, there was proof and offer of proof of actual damage, and there was no manifest error in the allowance of $3900.-00 liquidated damages. Thompson v. St. Charles County, supra; Annotation 34 A.L.R. 1336, 1341, 1350; 13 Am.Jur.2d (Building, Etc., Contracts), Sec. 86, p. 87.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Manufacturers Casualty Insurance v. Sho-Me Power Corp.
157 F. Supp. 681 (W.D. Missouri, 1957)
Hahn v. Forest Hills Construction Company
334 S.W.2d 383 (Missouri Court of Appeals, 1960)
Southwest Engineering Co. v. Reorganized School District R-9
434 S.W.2d 743 (Missouri Court of Appeals, 1968)
Thompson v. St. Charles County
126 S.W. 1044 (Supreme Court of Missouri, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
454 S.W.2d 30, 1970 Mo. LEXIS 1024, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-w-farmer-construction-co-v-carter-mo-1970.