Sides Construction Co. v. City of Scott City

581 S.W.2d 443
CourtMissouri Court of Appeals
DecidedMay 7, 1979
Docket10945
StatusPublished
Cited by5 cases

This text of 581 S.W.2d 443 (Sides Construction Co. v. City of Scott City) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sides Construction Co. v. City of Scott City, 581 S.W.2d 443 (Mo. Ct. App. 1979).

Opinion

GREENE, Judge.

Plaintiff, on September 24, 1973, entered into a construction contract with defendant city. The contract provided that plaintiff construct a swimming pool, bathhouse, and related items in a city park complex at Scott City, Missouri, for a price of $274,000. The contract specified that the work would be completed within 360 calendar days. The completion date was September 20, 1974.

Article IV of the contract provided that, “In conformity with the General Conditions and Special Conditions of the specifications the amount of liquidated damages for this contract shall be Fifty Dollars ($50.00) per day.”

General Condition 28(1) of the contract provided as follows: “Time is an essential element of the contract, and it is therefore important that the work be pressed vigorously to completion. Should the Contractor or, in the case of default, the surety fail to complete the work within the time specified in the Contract, or within such extra time as may be allowed in the manner set out in the preceding sections, a deduction of an amount as set forth in the Special Conditions will be made for each and every calendar day that such contract remains uncompleted after the time allowed for the completion. The said amount set forth in the Special Conditions is hereby agreed upon as liquidated damages for loss to the Owner and the public due to the obstruction of traffic, interference with use of existing or new facilities, and increased cost of engi *445 neering, administration, supervision, inspection, etc., after the expiration of the time stipulated in the Contract, and will be deducted from any money due to the Contractor under the Contract.” Special Condition 15 of the contract provided as follows: “15. Liquidated Damages: In accordance with the provisions of the ‘General Conditions’ the Contractor shall pay to the Owner, as and for liquidated damages and not as a penalty, the sum of Fifty Dollars ($50.00) for each and every calendar day that the Contractor shall be in default of the schedule set forth in the Contractor’s Proposal, unless extensions of time granted by the Owner specifically provide for the waiving of liquidated damages during and over such period of time extension or any part thereof. The Contractor shall set forth in the space provided in the proposal the completion period in calendar days which he considers necessary to satisfactorily complete the work included and described in these Plans and Specifications.”

A request for an extension of time to complete the project was made by plaintiff and granted by defendant. The agreed date for completion, as extended, was December 15, 1974. The work progressed, but was not completed, or accepted by the defendant until May 30, 1975. No further extension of time had been requested by plaintiff, or granted by defendant. Upon completion of the project, defendant withheld the sum of $8,300 from money due plaintiff, which sum allegedly represented liquidated damages due defendant under the contract, computed at the rate of $50 a day for 166 days.

Plaintiff then filed suit against defendant in the Circuit Court of Scott County seeking recovery of the $8,300 in question, plus interest. Plaintiff had previously demanded full payment from defendant, and was refused. Plaintiff, in its pleadings, contended that Article IY of the contract (the liquidated damages clause) was unenforceable and void, as not representing any true or realistic damages suffered by defendant; that defendant suffered no actual damages by plaintiff’s failure to complete the project by December 15, 1974; that defendant’s failure to bring in water and sewer lines to the swimming pool site, prior to May of 1975 caused the completion of the project to be delayed without fault of the plaintiff, and that the withholding of the $8,300 by defendant was arbitrary, capricious and improper since said amount was a penalty, and was not liquidated damages.

Defendant, in its pleadings, admitted that it had withheld the $8,300 but contended that it was entitled to such sum under the provisions of the contract and the General and Special Conditions that were a part of the contract. Defendant denied that it owed plaintiff any money whatsoever. Defendant did not plead that it had suffered any actual damages by failure of plaintiff to complete the contract by December 15, 1974.

The case was tried before the court without a jury. In addition to a stipulation regarding the contract’s execution, its completion dates, and the contract extension, some additional facts were introduced into evidence at the time of trial. Those facts were as follows. The pool in question was an open air unheated pool. Ninety-five to ninety-eight percent of the project was completed by January 1,1975, and the main items yet to be completed on that date were the painting of the inside of the pool, the finish grading of the road to the pool, the finish grading of the parking lot, and the filling of the pool with water to check out the mechanical system. The painting and the filling of the pool for purposes of checking the equipment could not be done during the winter months because the paint would not adhere to the concrete, and the water in the pool would freeze, causing damage to the water pipes and the pool itself. The water line to the swimming pool was put in by Herbert Mogdlin, a contractor from Scott City, under an independent contract with defendant. It was not completed until the month of April in 1975. Defendant’s architect, George Sailer of George E. Butler and Associates, advised plaintiff, by letter of February 7, 1975 (plaintiff’s exhibit 2) as follows: “We understand that the painting and the finish grading of the roads should *446 probably be completed in the Spring after the winter freezing and thawing has run its course. On the other hand, the finish grading of the parking area which would prevent storm water runoff from entering the bathhouse and pool areas should be completed at the present time in our judgment.” Nothing was said in the letter regarding another extension of time, or the waiver of liquidated damages.

James 0. Cauble, Jr., who was Mayor of Scott City from April of 1975 until April of 1976, and was a member of the city council prior to that time, testified that the installation of the playground equipment, which was a part of the project in question, was not done until after March of 1975; that defendant had to hire night watchmen to watch the playground equipment while the concrete for its installation was drying; that plaintiff had to lower the height of the parking lot after it was finished thereby causing a possible obstruction of traffic; and, that it was necessary for defendant to hire an additional engineer, Robert M. Harrison, to make additional inspections after December 15, 1974. These inspections were made in March of 1975. The engineer found that the finish grade of the parking lot was incorrect, which caused a drainage problem, and that the electrical and mechanical work was not finished.

On February 6, 1978, the trial court, citing Bloomfield Reorganized School Dist. No. R —14 v. Stites, 336 S.W.2d 95, 97 (Mo.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Luna v. Smith
861 S.W.2d 775 (Missouri Court of Appeals, 1993)
Rohlin Construction Co. v. City of Hinton
476 N.W.2d 78 (Supreme Court of Iowa, 1991)
Taos Construction Co. v. Penzel Construction Co.
750 S.W.2d 522 (Missouri Court of Appeals, 1988)
New Pueblo Constructors, Inc. v. State
696 P.2d 203 (Court of Appeals of Arizona, 1984)
Grand Bissell Towers, Inc. v. Joan Gagnon Enterprises, Inc.
657 S.W.2d 378 (Missouri Court of Appeals, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
581 S.W.2d 443, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sides-construction-co-v-city-of-scott-city-moctapp-1979.