Ward v. Haren

167 S.W. 1064, 183 Mo. App. 569, 1914 Mo. App. LEXIS 507
CourtMissouri Court of Appeals
DecidedJune 2, 1914
StatusPublished
Cited by10 cases

This text of 167 S.W. 1064 (Ward v. Haren) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ward v. Haren, 167 S.W. 1064, 183 Mo. App. 569, 1914 Mo. App. LEXIS 507 (Mo. Ct. App. 1914).

Opinion

ALLEN, J.

This is the second appearance of this case in this court. The opinion on the former appeal will be found reported in 139 Mo. App. 8,119 S. W. 446. The action is one for a balance due upon a building contract by which the plaintiff agreed to erect for the defendant a certain temporary building, in the city of St. Louis, in consideration of the sum of $8120, to be .paid him by defendant. • The contract was entered into on February 23, 1904, and the building was intended to be rented; for business purposes during the period of the Louisiana Purchase Exposition, or “World’s Fair,” held in said city; the lot upon which it was to be located being near the main entrance to said exposition grounds.

The opening of the exposition was on April 30', 1904, and the contract contained a stipulation that if the building was not completed by plaintiff on the 15th day of April, 1904, and the possession thereof delivered to the defendant on said day, then for each and every day thereafter during which the completion thereof should be delayed, the plaintiff should ‘ ‘forfeit and pay” to the defendant the sum of $120 for each and every day that plaintiff remained in default.

During the progress of the work certain changes were made in the plans and specifications, necessitating a longer time for the completion of the work, as well as additional expense on plaintiff’s part. The additional compensation to be paid plaintiff was agreed upon; and there is no question- here respecting the amount asserted by him to be the balance due upon [576]*576the contract. The only controversy in the case is in respect to the defendant’s claim to liquidated damages for the period during which the completion of the work was delayed.

The petition avexs that the total compensation which plaintiff was entitled to receive was $8821.35; that he had received on account thereof from defendant $6935.76, leaving a balance due of $1885.59, for which he prayed judgment.

The “answer and counterclaim” set up the provisions of the contract relative to a default in the completion of the building by the time specified, and averred that the plaintiff was in default for a period of twelve days in completing the same, and prayed for liquidated damages, under the contract, at the rate of $120 per day, the total of the counterclaim being $1440.

The plaintiff, in his reply, admitted that the building was not completed and delivered to the defendant at the time agreed upon, but averred that said provision in the contract had been waived by reason of the above mentioned changes in or deviations from the original plans and specifications, referring as well to other matter alleged in the petition as excuse for full compliance on plaintiff’s part.

Upon the first trial the court below accepted plaintiff’s theory that the time clause in the contract had been waived, and denied defendant a recovery on his counterclaim; the latter having theretofore unsuccessfully moved to strike out those portions of plaintiff’s reply which set up defendant’s alleged waiver of this provision of the contract. When the cause reached this court on the former appéal, the trial court was said to have been in error in holding that the defendant had waived his right to insist upon the enforcement of the time clause in the contract.

As to that question this court, among other things, said: “Plaintiff having failed to request additional [577]*577time, he must he deemed to have waived his right thereto and continue his obligation to complete the building within the time originally prescribed. He will not be permitted to claim that his time was extended or waived by the operation of law when he failed to abide the obligation of his contract and present his claim for consideration at the time required. ’ ’

Respondent vigorously assails the construction thus placed upon the contract on the former appeal. But that question should not be reopened in this case, for the decision on the former appeal is the law of the case, with respect to such matters as were then before the court and actually adjudicated.

But it may be here said that on the former appeal there was no question in the case as to whether the amount stipulated to be paid by plaintiff in case of default in completing the building, to-wit, $120 a day was to be regarded as liquidated damages or as a penalty. The question had not been raised below, and the case was considered here upon the theory that the amount thus stipulated to be forfeited and paid was conceded to be liquidated damages. [See Ward v. Haren, 139 Mo. App. 11, 119 S. W. 446.]

After the cause was remanded for a new trial, plaintiff, by leave of court, filed an amended reply, the amendment consisting of the addition to the original reply of certain allegations to the effect that the building in question was erected for the purpose of being rented to tenants during the World’s Fair period, and that it was only necessary that it be ready for occupancy by April 30, 1904; that the stipulation • respecting the said amount per day to be paid by plaintiff in case he were in default in completing the building was intended by the parties “as a penalty only to insure the completion of the building within the time necessary for the purposes for which it was erected; and not as liquidated damages; that the amount of [578]*578such, penalty was grossly in excess of any damages which could have been sustained by defendant by reason of the failure to complete the building within the time, the amount of such damages being readily ascertainable; that the building “was completed and ready for the occupancy of tenants prior to the opening of said World’s Pair and that defendant was not damaged in any amount whatsoever by reason of any failure, if failure there was, on the part of plaintiff to complete said building on April 15, 1904.”

Upon the filing of this amended reply, the defendant moved to strike out all ■ thereof, except the matter added by the amendment. This motion the court overruled. And the cause coming on to be heard, a jury having been waived, the court, having-heard the evidence, made a special finding of facts, in accordance with the request of plaintiff’s counsel, found for plaintiff in the sum of $2753.90, and for the defendant on his counterclaim in the sum of $1.46, entering judgment in favor of plaintiff for $2752.44. Prom this judgment the defendant prosecutes the present appeal.

The findings of the trial court above referred to are quite lengthy, and it is unnecessary to set them out here in full. Among other things the court found that the building in question was intended for use during the Worlds Pair period, beginning April 30, 1904; and that there was a compelling necessity for having it ready for occupancy, not only' on April 30, 1904, “but for a sufficient time prior thereto to enable tenants and owners to make all the preparations necessary for commencing business on that day. The court further found that on March 1, 1904, the defendant entered into a contract with one Yaccarazza, whereby the latter agreed to become defendant’s tenant in what is called the east store of said building, and paid defendant the sum of $2500.00 in cash, agreeing to pay in addition thereto twenty per cent of the gross [579]*579receipts of Ms business over and above $10,000.00, during the six months period of the exposition; and that on or about the same day defendant rented the “west store” of said building, the amount of the rental not appearing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anthony Arcese v. Daniel Schmitt & Company
504 S.W.3d 772 (Missouri Court of Appeals, 2016)
Grand Bissell Towers, Inc. v. Joan Gagnon Enterprises, Inc.
657 S.W.2d 378 (Missouri Court of Appeals, 1983)
Corrigan Co. Mechanical Contractors, Inc. v. Fleischer
423 S.W.2d 209 (Missouri Court of Appeals, 1967)
Franken v. Carpenter
364 S.W.2d 15 (Missouri Court of Appeals, 1963)
Harry Cooper Supply Co. v. Gillioz, 5560 (mo.banc 6-16-1937)
107 S.W.2d 798 (Supreme Court of Missouri, 1937)
Schwarz v. Lee
287 S.W. 519 (Court of Appeals of Texas, 1926)
Baker v. Lyell
242 S.W. 703 (Missouri Court of Appeals, 1922)
Barrett v. Stoddard County
197 S.W. 914 (Supreme Court of Missouri, 1917)
Rainier v. Masters
154 P. 426 (Oregon Supreme Court, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
167 S.W. 1064, 183 Mo. App. 569, 1914 Mo. App. LEXIS 507, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ward-v-haren-moctapp-1914.