Coen & Conway v. Birchard
This text of 100 N.W. 48 (Coen & Conway v. Birchard) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
There is no doubt that the building was not completed' on February 15th, as agreed; but it is contended on behalf of plaintiffs that, on account of a dispute as to the character óf the hardware to be used in the building, defendant extended the time until March 1st, and that on that date the building was turned over to the defendant in a substantially complete condition. This claimed extension is denied by the defendant, and this presents the first issue of fact' in the case. Without setting forth the evidence, it is sufficient to say that we are constrained to hold that plaintiffs’ contention in this respect is fully sustained. The only complaint defendant made on the first of March regarding the condition of the building was that the rubbish about it had not been cleaned [396]*396up, of a hole in the wall under a cellar door frame, the pointing up of the outside cellar wall, some changes about the windows, and defects in the painting and puttying. As to outside work, it is practically agreed that that was dependent on the condition of the weather. The cleaning up of- the rubbish, the painting, and the puttying were all outside work; and the evidence shows that some of the claimed defects were; due to weather conditions. The hole in the wall was due to the setting of the outside cellar door frame higher than the brick masons had intended, necessitating the filling in of the hole under the door sill and between it and the wall. The-, grading was not to be done by plaintiffs, and the evidence shows that this filling in could not be done until the level of the outer wall was determined by the grade, which was to have been established by the defendant. The matter was promptly fixed by plaintiffs as soon as it was called to their attention. The weather interfered with the pointing up of the outside cellar wail, and also- with the reglazing and outside painting; and this was done as soon as it could be. None of these things interfered with the occupancy of the house; for they all related to outside matters. Indeed, the evidence shows that the tenant to whom defendant had rented the house did not take possession thereof solely because of sickness in his family,' and not because of the incompleteness of the building. The building was substantially completed on March 1st, and the defects therein were remedied within a reasonable time. The architect, who was. made -a sort of arbiter between the parties, testified that the only complaints made by the defendant on March 1st were as to the putty on the windows, which had fallen off in some places because of weather conditions; painting of a window sill; and the closing of the opening under the door sill to which we have referred. This witness said, in effect, that the building was substantially completed at that time, and that plaintiffs did go back in a short time and remedy these defects. So that, whether the stipulation as to forfeiture for noncompletion be [397]*397held liquidated damages or a penalty, defendant is not entitled to recover because of plaintiffs’ delay in- complying with their contract.
The decree, in so far as it is complained of, seems to be correct, and it is affirmed.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
100 N.W. 48, 124 Iowa 394, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coen-conway-v-birchard-iowa-1904.