Badger Lumber Co. v. W. F. Lyons Ice & Power Co.

160 S.W. 49, 174 Mo. App. 414, 1913 Mo. App. LEXIS 122
CourtMissouri Court of Appeals
DecidedOctober 6, 1913
StatusPublished
Cited by9 cases

This text of 160 S.W. 49 (Badger Lumber Co. v. W. F. Lyons Ice & Power Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Badger Lumber Co. v. W. F. Lyons Ice & Power Co., 160 S.W. 49, 174 Mo. App. 414, 1913 Mo. App. LEXIS 122 (Mo. Ct. App. 1913).

Opinion

TRIMBLE, J.

Suit to enforce a mechanic’s lien for lumber and materials sold by appellant to the W. F. Lyons Ice & Power Company for the purpose of, and used in, constructing an ice manufacturing and meat packing plant. A jury was waived and the case was tried by the court. Appellant obtained judgment for $2918.45 on the account sued on, but was denied a lien.

It is clear, from the finding of facts preserved in the record, that the only reason a lien was refused was because the court thought the last two items in the account were sold under a different contract from that under which the rest were sold. If the two last items were sold under a separate contract, they could not be considered as a part of the original account, and if they were not a part of it, then the lien was not filed within six months after the account accrued. All other requirements of the statute for the establishment of a lien were -complied with.

[416]*416The first item in the account is dated September 3,1908, and from this time the account continues down to and including May 3, 1909. From this date until October 9, 1909, there are no items charged and no materials were sold. But, on this date, an item of 4000 square feet of insulating paper was sold, and on October 12, 1909, an item of sixteen pieces of two inch by six inch No. 1 yellow pine lumber twenty-two feet long, was sold to the company and used by it in the building. The lien claim was filed January 29, 1910. If the two items above mentioned were sold under a separate and distinct-contract from that under which the rest of the account was sold, then, of course, the account did not accrue on October 12, 1909, but accrued on May 3,1909, which was more than six months prior to the'filing of the lien claim. If, however, the last items were sold under the same' general contract as the others were, then the lien was filed in time and should be enforced. So that the only question in the. case is whether or not the materials bought and used in October, 1909, were furnished under such circumstances as to show they were sold, with the others, under one entire general contract, so as to give appellant six months from October 12,1909, instead of from May 3, 1909, in which to file a lien claim.

Where the evidence is conflicting, or where the circumstances are such as that different inferences may be reasonably drawn from the same facts, such a question is one for the jury. [Darlington Lumber Company v. Smith Building Company, 134 Mo. App. 316; Cole v. Barron, 8 Mo. App. 509.] This rule is well established and is not disputed. The contention •of appellant is-that the evidence shows that all of the items, including the last two, were sold under one entire general contract, and that there is no evidence upon which can be based the trial court’s finding that the last items were furnished under a different one. If this contention is true, it is within our power to [417]*417review the trial court’s finding. If it is not true, that is, if there is any evidence supporting such finding, then it is a matter beyond our ken since we cannot weigh the evidence. To ascertain the truth of the matter requires a very careful examination of the entire record and of all 'the inferences to be drawn therefrom. As a result of such examination, it can be said that there is practically no dispute as to the facts which govern this final and ultimate question of whether the items in the account were furnished under one general contract or under two. So that, after all, in this particular case, the question whether the materials were furnished under one or two contracts resolves itself into, what inference the law will draw from what the parties to the contract did. As said in Page v. Bettes, 17 Mo. App. 375: “The jury are to find what the'contract in fact was; and whether the contract thus found is entire and continuing, is a question of law for the’court.” If, therefore, the undisputed evidence shows what the contract was, and that the materials were furnished thereunder according to that contract, then the question whether the contract is entire is a question of law. [Phillips on Mechanic’s Liens, sec. 325.] And if the trial court has' erred in its view as to what constitutes an entire contract, then it is our duty to correct that error.

It should be borne in mind that, so far as the contract is concerned, the only requirements demanded by the statute are that the materials for which a lien is sought must be furnished “under and by virtue of a contract with the owner” ('See. 8212, R. S. Mo. 1909). Of course, this means that all the items in one lien account must have' been furnished under the same contract. But if the evidence shows that all the items were furnished “under and-by virtue of” one contract, then the vendor is entitled to his lien although there may' be-‘facts and circumstances showing that they [418]*418were furnished at different times and were rendered necessary by different conditions. A running account is deemed an entire contract, and for the purpose of fixing the time for filing the account to perfect a mechanic’s lien, each item- of the account relates to the last item delivered. [Stine v. Austin, 9 Mo. 558; Phillips on Mechanic’s Liens, sec. 325; Big Horn Lumber Co. v. Davis, 14 Wyo. 455.] There is no doubt but that the account in this case was a running account. It was a mutual account between buyer and seller in which was charged from time to time, as ordered, the materials sold, and on which was entered the various credits to which the seller was entitled by reason of payments made and articles returned. [7 Words and Phrases, 6277.] Of course, if the materials were sold under separate and distinct contracts, then the mere fact' that -they were all charged in the form of a running account would not make them lienable under one contract. But, unless there is evidence to show a separate and distinct contract as to the last items, the account will be taken and considered, as it appears -to be, a running account arising under and by virtue of the contract out of which the account originally grew.

In discussing the question when materials are to be considered as having been furnished under an entire or under separate and distinct contracts, Phillips on Mechanic’s Liens, section 229, mentions several circumstances as marks to determine the matter. If the work is distinct in its nature, and is performed at different times, or, if two distinct contracts are in fact made, for different parts of the work, these are marks to show that there was not one entire general contract covering the whole account. “But when material is furnished, all going to the same general purpose, as the building of a house- or any of its parts, though such work he done or ordered at different times, yet if the several parts form an entire whole, or are so [419]*419connected together as to-show that the parties had it in contemplation- that the whole should form but one, and not distinct matters of settlements, the whole account must be treated as a unit, or as being but a single contract.” [Phillips on Mechanic’s Liens, sec. 229.] And in Bruns v. Braun, 35 Mo. App. 337, l. c.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Manning Construction Co. v. MCI Partners, LLC
419 S.W.3d 134 (Missouri Court of Appeals, 2013)
Midwest Floor Co. v. Miceli Development Co.
304 S.W.3d 243 (Missouri Court of Appeals, 2009)
Byron J. Myers, Inc. v. Bradbury
595 S.W.2d 724 (Missouri Court of Appeals, 1980)
A. E. Birk & Son Plumbing & Heating, Inc. v. Malan Construction Co.
548 S.W.2d 611 (Missouri Court of Appeals, 1977)
JR Meade Co. v. Forward Construction Company
526 S.W.2d 21 (Missouri Court of Appeals, 1975)
Trout's Investments, Inc. v. Davis
482 S.W.2d 510 (Missouri Court of Appeals, 1972)
Dobyns Lumber Co. v. Schoonover
479 S.W.2d 206 (Missouri Court of Appeals, 1972)
Tull v. Fletcher
196 S.W. 436 (Missouri Court of Appeals, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
160 S.W. 49, 174 Mo. App. 414, 1913 Mo. App. LEXIS 122, Counsel Stack Legal Research, https://law.counselstack.com/opinion/badger-lumber-co-v-w-f-lyons-ice-power-co-moctapp-1913.