Alcatraz Masonic Hall Ass'n v. United States Fidelity & Guaranty Co.

3 Cal. App. 338
CourtCalifornia Court of Appeal
DecidedMarch 28, 1906
DocketCiv. No. 161
StatusPublished
Cited by3 cases

This text of 3 Cal. App. 338 (Alcatraz Masonic Hall Ass'n v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alcatraz Masonic Hall Ass'n v. United States Fidelity & Guaranty Co., 3 Cal. App. 338 (Cal. Ct. App. 1906).

Opinion

HARRISON, P. J.

The plaintiff entered into a contract -with one L. U. Grant, October 19, 1899, for the construction by the latter of a building upon its land at the agreed price ■of $16,300, and at the same time the said Grant as principal and the defendant as surety executed to the plaintiff a bond if indemnity in the sum of $4,075, conditioned that Grant .should faithfully perform the said contract and deliver the building to the plaintiff within the contract time for its completion, free from all liens, demands and claims, and should pay to the persons performing labor or furnishing materials for the construction of the building the value thereof. The ■contract provided that the building should be completed with[340]*340in one hundred arid fifty working days from the date thereof, and that the payment of the contract price should he made in installments as the work progressed, in sums equal to seventy-five per cent of the value of the work done and materials furnished, as estimated on the first and fifteenth days of each month, and the balance,-to wit, twenty-five per cent of the contract price of $16,300 ($4,075) thirty-five days after the completion and acceptance of the work. After the execution and recording of the contract the plaintiff and Grant made certain alterations and changes therein, by which the cost of the building was increased in the sum of $315, and agreed that the said additional cost should be paid at the same times and in the same manner as payments under the original contract. During the progress of the work payments were made to Grant upon certificates of the architect on account of installments due on the contract, amounting to $12,138.85. Before the building was completed Grant abandoned the contract, and the plaintiff completed the construction of the building and expended therefor $641.23. After its completion certain parties, who had furnished materials and performed labor for Grant in its construction, filed claims of lien therefor, amounting to about $7,500, and subsequently brought actions in the superior court for their enforcement. These actions were, by an order of court, consolidated, and the plaintiff filed its answer thereto, alleging that the building was not subject to liens exceeding in the aggregate $3,834.92, and offering to deposit that sum in court for their satisfaction. Upon the trial of the cause the court found that that was the amount due from the plaintiff to Grant upon the contract at the commencement of the action; and upon its order the sum was deposited in court for the said claimants, and the court thereupon rendered its judgment that the said liens were thereby fully satisfied. In this litigation the plaintiff employed certain attorneys, for whose services he paid $500, and incurred certain costs, amounting to $27. The present action is brought to recover these amounts from the defendant. A demurrer to the complaint was sustained, and from the judgment entered thereon the plaintiff has appealed.

[341]*341The bond of the defendant makes no reference to the provisions of section 1203, Code of Civil Procedure, and the rulings of the supreme court in reference to that section, upon which the objection to the validity of the bond was based, are inapplicable. It is unnecessary to consider the effect of the provision in the bond for the payment by Grant to the laborers and materialmen, since the complaint herein is limited to the rights of the plaintiff alone. The condition of the defendant’s obligation is the failure of Grant to faithfully perform his contract and deliver the building to the plaintiff free from all liens, claims and demands. Although it is alleged that Grant did not complete the building, but abandoned his contract when it was uncompleted, and the plaintiff was compelled to complete the same, the plaintiff does not show that it has sustained any damage thereby, or make any claim against the defendant therefor. The total amount of the contract price for the building and for the extra work is $16,615. Deducting from this $12,138.85 paid to Grant upon the certificates of the architect as the work progressed, and $3,834.92 determined by the court to be in the plaintiff’s hands applicable for the discharge of the liens upon the building, there remains $641.23, the amount paid by the plaintiff for the completion of the building, thus showing that the plaintiff sustained no pecuniary damage by reason of Grant’s failure to complete his contract. The basis of the defendant’s obligation which the plaintiff presents in support of its right of action is the failure of Grant to deliver the building free from liens, and upon this point it alleges that upon the completion of the building the sum of $3,834.92 was chargeable against the building for liens and claims-thereon; and it also alleges that upon the trial of the action to enforce the liens the court found that the lien claimants were entitled to this amount of money, and that upon depositing that amount in court for the discharge of said liens the court rendered its judgment that the liens were fully satisfied.

1. The alteration of the contract as set forth in the complaint had the effect to release the surety from its contract of indemnity. There is no allegation in the complaint supporting the suggestion in the brief of the appellant that the original contract contained a provision authorizing changes [342]*342to be made therein; nor is it alleged that the changes were made with the consent of the defendant. For the purpose of determining the sufficiency of the complaint as against the demurrer we can consider only matters therein set forth. There is no principle of law better settled than that a surety has the right to stand upon the very terms of his contract, and that any alteration in the terms of the principars contract, made by the parties thereto without his assent, will have the effect to discharge him from all liability. By such alteration the contract ceases to be the one for which he became surety, and the extent of such alteration, or whether his lia- • bility will be increased or diminished thereby, is immaterial. Having the right to determine in the first instance whether he will become such surety or not, he has the right to be consulted upon the terms proposed for any variation of his obligation, and if made otherwise his obligation is extinguished, The principle of this rule is discussed in Brandt on Suretyship, section 106. (See, also, Miller v. Stewart, 9 Wheat. (U. S.) 680; Bethune v. Dozier, 10 Ga. 235.) In this state the legislature has declared in section 2819, Civil Code, that if by any act of the creditor without his consent the original obligation of the principal is altered in any respect he is exonerated. That the alterations in the contract agreed upon between the plaintiff and Grant had the effect to alter the obligation of the surety is apparent. A greater length of time was thereby required within which to finish the building, and a greater amount of labor and of expenditure incident thereto than that for which the defendant had agreed to indemnify the plaintiff. Because of these alterations the defendant ceased to be liable on its contract. (Judah v. Zimmerman, 22 Ind. 388; O’Neal v. Kelley, 65 Ark. 550, [47 S. W. 409]; Eldridge v. Fuhr, 59 Mo. App. 44; Beers v. Wolff, 116 Mo. 179, [22 S. W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Congregational Church of Christ v. Lowrey
165 P. 440 (California Supreme Court, 1917)
Watterson v. Owens River Canal Co.
143 P. 90 (California Court of Appeal, 1914)
Growall v. Pacific Surety Co.
131 P. 73 (California Court of Appeal, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
3 Cal. App. 338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alcatraz-masonic-hall-assn-v-united-states-fidelity-guaranty-co-calctapp-1906.