J. G. Wagner Co. v. Cawker

88 N.W. 599, 112 Wis. 532, 1902 Wisc. LEXIS 11
CourtWisconsin Supreme Court
DecidedJanuary 7, 1902
StatusPublished
Cited by15 cases

This text of 88 N.W. 599 (J. G. Wagner Co. v. Cawker) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. G. Wagner Co. v. Cawker, 88 N.W. 599, 112 Wis. 532, 1902 Wisc. LEXIS 11 (Wis. 1902).

Opinion

Bardeen, J.

One important stipulation in the written ■contract was that no alterations should be made in the work shown or described by the drawings and specifications except upon the written order of the architect. It seems to have been assumed on the trial that this stipulation was sufficiently broad to cover extra work, and was of such a character as that the architect might waive its provisions. There is no dispute but that extra work was performed, and the amount thereof was determined by the architect and included in the final certificate. It is not claimed that such work was done upon the written order of the architect, but it is claimed that defendants waived that provision of the ■contract. Whether the architect had any power to waive contract provisions of that kind is very doubtful; but, defendants having consented that the court should answer question 4 of the verdict without submission of the fact to the jury, that question is not now before us for decision. Permitting the court to answer that finding in the affirmative precludes the defendant from raising any objection to the finding at this time.

A much more serious question arises regarding the answer to the sixth question. There is absolutely no evidence in the case that the defendants have personally done anything [538]*538from which a waiver of the requirement regarding making claim for an extension of time can be argued. The contract provides that the plaintiff should complete the entire framework of the building by October 9th, and complete all work by November 15th. In case of failure so to do the plaintiff was to allow $50 per day as liquidated damages for every day after said last-mentioned date that the work remained unfinished. Should the plaintiff be delayed by the act, neglect, delay, or default of the owner, architect, or any other contractor, then the time fixed for the completion of the building was to be extended for a period equivalent to the time so lost, but no such allowance was to be made unless a claim in writing therefor was presented to the architect within twenty-four hours of the occurrence of such delay, and the duration of such delay was to be certified toby him, subject to an appeal to arbitration. It is admitted that no claim in writing for such delay was ever presented to the architect. It is also true that plaintiff had no communication with the defendants on the subject prior to the final completion of the building. The plaintiff rests its failure to comply with this condition of the contract upon a conversation had by its general manager with the architect during the progress of the work, in which the latter told him that it would not be necessary to give a written notice or demand for additional time. It seems to have been assumed on the trial that the architect had power to waive performance of these conditions of the contract.

The importance of this stipulation, as well as its purpose, is manifest. The very contest that has arisen in this case demonstrates the necessity of some such cautious provision. Disputes frequently arise between different pon tractors, or the owner and the architect, as to responsibility for delays in the work. Owners are very much in the power of contractors and architects. To avoid the uncertainty of verbal disputes, and to prevent the contractors from making claims [539]*539for delay after tbe building has been finished, is clearly the purpose of such provisions. They are for the benefit of both, especially for the owner. The plaintiff knew that it could have no claim for delay for any reason unless it made a claim in writing within twenty-four hours after jts occurrence. If, relying on the assurance of the architect, it chose to go on with the work without placing itself within the protection of the contract, it must bear the consequences, unless we can say the architect had authority to waive this condition.

As we have already said, the purpose of this stipulation was to protect the defendants from stale claims for delay, which might be based upon oral understandings, and made when it might be difficult to prove the facts in relation thereto. The giving of the notice was a condition precedent to any authority on the part of the architect to act. The latter was not a general agent of defendants. He had only such authority as was given him under the contract. Thus, in California an architect, without special authority conferred by the written contract, was not authorized to receive notice of an assignment ‘of a building contract. Renton, H. & Co. v. Monnier, 77 Cal. 449. He has no power to bind the owner for extra work unless it is done as the contract prescribes. Baltimore C. Co. v. Coburn, 7 Md. 202; Starkweather v. Goodman, 48 Conn. 101. See Condon v. Jersey City, 43 N. J. Law, 452; Sutherland v. Morris, 45 Hun, 259; Fitzgerald v. Moran, 141 N. Y. 419. Where the contract provided that no claim for extra work should be allowed “ unless the same should he done in pursuance of a written order from the engineer in charge, and the claim made at the first settlement after the work was executed,” it was held that the engineer had no power to alter or change the contract, and no allowance for extra work could be made without proof of performance of the conditions precedent in the contract. Woodruff v. R. & P. R. Co. 108 N. Y. 39. In [540]*540Thayer v. V. C. R. Co. 24 Vt. 440, as between tbe company .•and their contractors, the contract seems to have expressly denied the power of the engineer to bind the company for extra work, except in a particular mode, in writing, and then th^claim to be presented and adjusted in a prescribed time and mode. It was held there was nothing in the general duties of the engineer to authorize him to vary the contract and employ others to do such work. Vanderwerker v. V. C. R. Co. 27 Vt. 125, was a similar case, in which the court said:

“No one could for a moment be led into any misapprehension as to the extent of the engineer’s authority to ■charge the company by varying the existing conditions or making new ones. The engineers were there for no such purpose, and they had no such agency, except under specific limitations and restrictions, and they did not, as to this item, assume to do any such thing.”

See, also, Vanderwerker v. V. C. R. Co. 27 Vt. 130; Lewis v. Slack, 27 Mo. App. 119. In Dodge v. McDonnell, 14 Wis. 553, where one had employed an architect to make plans for a house and do such other acts as architects usually do as such, and had engaged a contractor to do the work and furnish the materials, and had placed money in the architect’s hands to be paid on the contractor’s order, it was held that this did not warrant a finding that the architect was the general agent of his employer, and he had no authority to bind him by new contracts for materials with other persons. See Campbell v. Day, 90 Ill. 363. In Starkweather v. Goodman, 48 Conn. 101, a builder made a written contract to furnish the materials and build a house for defendant according to definite plans and specifications and for a fixed sum, all the materials and work to be accepted by an architect named, who Avas to superintend the construction. The builder, under the direction of the architect, did certain work variant from, and in addition to, the specifications, which increased the cost and value of the house. Held that [541]*541the ordering of the work was beyond the scope of the architect’s agency, and that the defendant was not liable to the-builder for it. 1 Hudson, Building Cont.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southwest Engineering Co. v. Reorganized School District R-9
434 S.W.2d 743 (Missouri Court of Appeals, 1968)
Austin-Griffith, Inc. v. Goldberg
79 S.E.2d 447 (Supreme Court of South Carolina, 1953)
Roberts v. Security Trust & Savings Bank
238 P. 673 (California Supreme Court, 1925)
Minn Billiard Co. v. Schwab
190 N.W. 836 (Wisconsin Supreme Court, 1922)
Leigland v. Rundle Land & Abstract Co.
208 P. 1075 (Montana Supreme Court, 1922)
Sheffield-King Milling Co. v. Jacobs
175 N.W. 796 (Wisconsin Supreme Court, 1920)
Wm. P. Jungclaus Co. v. Ratti
118 N.E. 966 (Indiana Court of Appeals, 1918)
Grant Marble Co. v. Marshall & Ilsley Bank
165 N.W. 14 (Wisconsin Supreme Court, 1918)
Sterling Engineering & Construction Co. v. Berg
152 N.W. 851 (Wisconsin Supreme Court, 1915)
Wait v. Stanton
147 S.W. 446 (Supreme Court of Arkansas, 1912)
Wells v. Western Union Telegraph Co.
123 N.W. 371 (Supreme Court of Iowa, 1909)
Ward v. Haren
119 S.W. 446 (Missouri Court of Appeals, 1909)
Davis v. La Crosse Hospital Ass'n
99 N.W. 351 (Wisconsin Supreme Court, 1904)
City of Madison v. American Sanitary Engineering Co.
95 N.W. 1097 (Wisconsin Supreme Court, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
88 N.W. 599, 112 Wis. 532, 1902 Wisc. LEXIS 11, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-g-wagner-co-v-cawker-wis-1902.