City of Madison v. American Sanitary Engineering Co.

95 N.W. 1097, 118 Wis. 480, 1903 Wisc. LEXIS 72
CourtWisconsin Supreme Court
DecidedJuly 3, 1903
StatusPublished
Cited by27 cases

This text of 95 N.W. 1097 (City of Madison v. American Sanitary Engineering Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Madison v. American Sanitary Engineering Co., 95 N.W. 1097, 118 Wis. 480, 1903 Wisc. LEXIS 72 (Wis. 1903).

Opinion

Winslow, J.

The first serious question debated by the parties is whether the sum named in the bond in suit is a penalty, or whether it is liquidated damages. The plaintiff claims that it must be treated as liquidated damages, while the defendants maintain that it is strictly a penalty, and that although substantial breaches may have been shown the plaintiff cannot recover, because it has not shown the amount of damages resulting from such breaches.

It is well understood that the words “penal sum” in that part of a contract or bond providing for the consequences of a breach thereof are ordinarily to be construed strictly, and as meaning a penalty and nothing more, and that in such case actual damage must be shown, and it is also understood that this ordinary import may be overborne by other parts of the contract which demonstrate that the words were used as meaning “liquidated damages.” Yenner v. Hammond, 36 Wis. 277. So, also, if the sum be denominated “liquidated. dam[503]*503ages,” this fact will not be conclusive upon the courts; but if-the sum fined be largely in excess of actual damages, or it appear that the sum was fixed to evade usury laws or to cloak oppression, the courts will construe it as a penalty. Berrinkott v. Traphagen, 39 Wis. 219; Seeman v. Biemann, 106 Wis. 365, 84 N. W. 490. It is also said that where the sum fixed is excessive, and the damages are wholly uncertain and incapable of ascertainment by any known rule, the courts will consider the sum named as liquidated damages. See cases cited above; also Walsh v. Fisher, 102 Wis. 172, 78 N. W. 437; J. G. Wagner Co. v. Cawker, 112 Wis. 532, 88 N. W. 599.

Tested by these general principles, we are convinced that the sum named in the bond in the present case must be regarded as a penalty. In the first place, it is named as a “penal sum,” which is the appropriate language for the designation of a penalty, and this fact has considerable significance when the agreement or bond is drawn and scrutinized by lawyers before acceptance, as in the present case. In the second place the bond is given to insure the performance of “all the covenants, conditions, warranties, and agreements” contained in the principal contract, which are quite numerous, and some of which are trivial in their nature. It is very manifest that, in the absence of language to that effect, the penal sum named cannot be construed as liquidated damages for the breach of one covenant or agreement and a penalty only for the breach of others. The agreement provides that the company shall save the city harmless f ram all claims or injury or damages growing out of the same, also that before final payment the company shall satisfy all claims for labor, damages, or materials, also to furnish all ferozone for the operation of the plant for a year at cost,'and that the cost of fei’ozone thereafter shall not exceed a certain amount. Suppose that any one or all of these agreements be breached, the damages suffered would be readily ascertainable, and if such [504]*504damages only amounted to a few hundred or even a few thousand dollars could it be reasonably argued for a. moment that the entire penal sum of the bond must be recovered ? Plainly not, yet such must be the result if the damages are liquidated. Another fact seems very significant, if not controlling, upon the question of the intent of the parties. The agreement provides that if the plant be not completed within the time fixed (or the timers extended in writing) the company shall forfeit the sum of $25 per day as liquidated damages for such default. This demonstrates that the parties had in mind the difference between liquidated damages and penalty, and presumably used both terms advisedly. -Had the bond been given simply to insure the furnishing of a plant which would treat the city sewage with certain results, the argument that the sum named was intended as liquidated damages would have far greater force because the damages for breach of that agreement might be quite difficult of ascertainment, but given, as it was, to insure the performance of many different covenants and conditions, some of which are in their nature unimportant, and whose breach would inflict only trifling loss, we are compelled to construe the sum named in the bond as a penalty and 'nothing more.

Starting from this basis, the question presented is whether the plaintiff proved without dispute that it suffered damage to the amount of $25,000. The plaintiff proved without dispute that the sewage disposal plant erected by the engineering company not only technically, but substantially, failed to comply with the terms of its contract. Neither the company nor the city was ever able to operate the plant so that it would treat the city’s sewage and obtain the guarantied results, or even an approximation of such results. The proof was conclusive and undisputed that the plant completely failed to dispose of the sewage of the city with the results contracted for. It was admitted that the city had paid the company $25,000 during the progress of the work. If, as claimed by the re[505]*505spondent, there has been an entire failure to perform, and tbe city bas in legal contemplation received nothing for its money, then damages to the extent of $25,000 .have been proven; otherwise not. This is really the main question in the case, and the decisive question so far as the defendant engineering company is concerned. The. appellants contend that the evidence shows that the plant was of some value, though some of the warranties may have been breached; that the proof also shows that the engineers were satisfied with the working of the plant October 16, 1899, and that it was then incumbent on the city under the contract to take the plant and give it nine months’ trial; that the city had no right under the contract to take possession of the plant in January, 1900, and operate it for nearly a year; that such use was outside of the contract entirely; and that the city has thus received some benefit from the plant by use thereof as well as from its permanent retention.

The contention that the engineers were satisfied with the plant October 16, 1899, and that it was then the duty of the city under the contract to take the plant and operate it, requires examination and construction of the terms of the contract. The contract, after providing that the work shall be completed in strict compliance with the plans and specifications, further provides that the engineering company shall operate the works for three months after the date of their completion, at their own expense, and if at the expiration of that time the plant is working “to the satisfaction of the said city engineers” the city shall assume control and shall operate the same for nine months before accepting the same. The contract then proceeds to specify the degree of purification which the company contracts to produce when the plant is working to its full capacity.

The appellants contend that the contract does not mean that the plant should be doing the full work guarantied at the end of the three months in order to justify the engineers [506]*506in pronouncing it satisfactory, but simply that tbe engineers should think it “good enough to try” at that time. In effect, the claim is that if it was mechanically satisfactory, and if the sewage was going through it in some shape, the engineers were entitled to pronounce it satisfactory for the purpose of the nine-months trial, and that they did in fact so pronounce it. We cannot agree with these contentions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Koenings v. Joseph Schlitz Brewing Co.
377 N.W.2d 593 (Wisconsin Supreme Court, 1985)
Wassenaar v. Panos
331 N.W.2d 357 (Wisconsin Supreme Court, 1983)
Milwaukee Enforcers, Inc. v. Ball
237 N.W.2d 715 (Wisconsin Supreme Court, 1976)
Nordin Construction Company v. City of Nome
489 P.2d 455 (Alaska Supreme Court, 1971)
Center Drainage District No. 1 v. Capitol Indemnity Corp.
147 N.W.2d 245 (Wisconsin Supreme Court, 1967)
State v. Northern Pacific Railway Co.
14 N.W.2d 232 (Supreme Court of Minnesota, 1944)
State v. Hackbarth
279 N.W. 687 (Wisconsin Supreme Court, 1938)
Klatte v. Franklin State Bank
248 N.W. 158 (Wisconsin Supreme Court, 1933)
City of Minneapolis v. Republic Creosoting Co.
201 N.W. 414 (Supreme Court of Minnesota, 1924)
County of Price v. Northwestern Casualty & Surety Co.
199 N.W. 60 (Wisconsin Supreme Court, 1924)
Dick v. Heisler
198 N.W. 734 (Wisconsin Supreme Court, 1924)
Minn Billiard Co. v. Schwab
190 N.W. 836 (Wisconsin Supreme Court, 1922)
County of Le Sueur v. Globe Indemnity Co.
184 N.W. 677 (Supreme Court of Minnesota, 1921)
Sheffield-King Milling Co. v. Jacobs
175 N.W. 796 (Wisconsin Supreme Court, 1920)
City of Nashville v. Nashville Traction Co.
142 Tenn. 475 (Tennessee Supreme Court, 1919)
Outagamie County v. Zuehlke
161 N.W. 6 (Wisconsin Supreme Court, 1917)
Sledge v. Arcadia Orchards Co.
137 P. 1051 (Washington Supreme Court, 1914)
Gottsegan Cicar Co. v. Levy
130 P. 780 (Utah Supreme Court, 1913)
President of Kilbourn City v. Southern Wisconsin Power Co.
135 N.W. 499 (Wisconsin Supreme Court, 1912)
Kunz v. Boll
121 N.W. 601 (Wisconsin Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
95 N.W. 1097, 118 Wis. 480, 1903 Wisc. LEXIS 72, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-madison-v-american-sanitary-engineering-co-wis-1903.