City of Minneapolis v. Republic Creosoting Co.

201 N.W. 414, 161 Minn. 178, 1924 Minn. LEXIS 509
CourtSupreme Court of Minnesota
DecidedDecember 5, 1924
DocketNo. 24,072.
StatusPublished
Cited by16 cases

This text of 201 N.W. 414 (City of Minneapolis v. Republic Creosoting Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Minneapolis v. Republic Creosoting Co., 201 N.W. 414, 161 Minn. 178, 1924 Minn. LEXIS 509 (Mich. 1924).

Opinion

Stone, J.

Action on the contractor’s bond, against both contractor and surety, for breach of contract for the sale and delivery by defendant, Kepublic Creosoting Company, to plaintiff of paving blocks. After a directed verdict for plaintiff for $52,198.56, defendants moved for judgment notwithstanding or a new trial and appeal from the denial of that motion.

The contract bears date of December 31, 1919, and recites as consideration the release of the Creosoting Company (hereinafter referred to as defendant), and its surety from all liability under a former and similar contract and bond (for 1919 deliveries), where-under there had been default by defendant. We start then with the conceded fact that the controlling contract is based upon ample and executed consideration, moving from plaintiff to defendant.

The obligation of defendant, as expressed by the contract, was:

“to sell, furnish and deliver to said second party (plaintiff) * * * during the first six months of the year 1920, in such quantities not exceeding 1,500 square yards per day and at such times as the said City Engineer may order and direct, forty-two thousand (42,000) square yards, or any part thereof at the option of said second party, of 3J inch yellow pine creosoted wood paving blocks, for the sum and price of $2.10-))- per square yard, street measurement, all in strict conformity with the specifications for said paving blocks referred to and included in the 1919 contract hereinbefore referred to”

The 1919 specifications referred to were made a part of the contract, and provided as to deliveries that:

“The blocks shall be furnished in such quantities and at such times as the City Engineer may direct, and if so directed, the contractor shall furnish one per cent of his total contract, computed in square yards, per day, delivery to commence not later than 10 days from notice by.the City Engineer.”

*181 There was nothing in the contract excusing defendant from punctual performance because of strikes, lockouts, a car shortage or similar hazards beyond the control of defendant.

On April 28, 1920, the city engineer delivered to defendant, four “requisitions for delivery.” Each was signed by plaintiff’s purchasing agent and was for an authorized paving project. Together they directed delivery of the entire 42,000 square yards covered by the contract, and at the rate of 1,500 square yards per day, commencing May 10. Each requisition contained the necessary shipping directions, referred to the specified blocks as “applying on your (defendant’s) contract,” and carried this notation, “apply the material listed on your contract with the city of Minneapolis. This is not an order, but only a requisition for delivery on contract.”

Upon receipt of these requisitions, defendant informed plaintiff’s engineer and purchasing agent that deliveries as required were impossible, but that it was desirous of making them as rapidly as conditions permitted. The asserted impossibility of performance was referred exclusively to a country-wide car shortage. We assume that it did exist and did prevent defendant’s compliance with the requisitions. We assume also defendant’s willingness and ability to deliver as soon as a car supply enabled it to assemble the raw material, complete the processes of manufacture and get the finished product to Minneapolis. At best, in defendant’s case that would have taken some months after May 10, 1920. No part of the blocks was delivered or tendered by defendant. It declined' to make any effort to fill plaintiff’s requisitions, professing for the reason stated inability to do so. Plaintiff disregarded its offer of deliveries later and, as soon as railroad, service permitted, considered the contract irrevocably breached by defendant, procured the blocks elsewhere and at a higher price and commenced this suit for the damage arising from their increased cost.

Defendant’s first position is that the contract was “merely a contract for an option” and that “unless and until exercised lawfully and in accordance with its terms imposed no obligation upon the Creosoting Company to deliver, or upon the city to take and pay for any blocks whatsoever.” Admitting a contract, the argu *182 ment is that it is not a contract of sale, binding one to deliver goods and another to take and pay for them; that the latter contract never came into existence because the act required to bring it into being, the contractual assent of the city of Minneapolis, was never, in any lawful fashion, expressed or notified to defendant. The contention depends upon the proposition, urged as controlling by defendant, that its engineer and purchasing agent have no power to bind plaintiff by a contract, such as this, for the purchase of construction materials in large quantities. That is true, for under the charter and ordinances of Minneapolis contracts for the purchase of materials in large quantities must be made or expressly authorized by the city council. In this case, the agreement of December 31, 1919, was so made or authorized, but the city council did not expressly authorize or take any particular action with respect to the requisitions for delivery, defendant’s failure to comply with which resulted in this action.

It is clear, however, that four authorized paving projects were under way; that they were under the immediate official and administrative control of the city engineer, one of whose duties was to determine when and how much material was needed, and to direct deliveries accordingly; and finally, and most important, defendant was bound by contract — call it “option” or anything else — to honor orders, under the contract, from the city engineer. Likewise, plaintiff was contractually bound to abide any orders of its engineer for the delivery of blocks under the contract, whether or not it used them, and to pay for the blocks so ordered at the “option” price. There is nothing in statute, charter or ordinance, preventing plaintiff from contracting to accept and pay for, at fixed prices and during a specified reasonable period, such paving blocks as may be ordered, under the contract, by its city engineer.

The argument that contracts cannot be made for plaintiff by its engineer is refined too much by urging, as defendant does, that the engineer cannot determine when to order or how much. The impossible alternative is that the city council would have to sit more or less constantly for the purpose of sanctioning requisitions for ma *183 terials needed, day by day, in the numerous public works always under way in any city of truly metropolitan pretensions. .

Of course it is well understood that:

“An option is a privilege given by the owner of property to another to buy the property at his election. It secures the privilege to buy and is not of itself a purchase. The owner does not sell his property; he gives to another the right to buy at his election.” Western Union Tel. Co. v. Brown, 253 U. S. 101, 40 Sup. Ct. 460, 64 L. ed. 803.

While an option is not of itself a purchase of the property in question, it is literally the purchase of a right to buy property if the optionee elects to do so. Staples v. O’Neil, 64 Minn.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CooperVision, Inc. v. Inter Integration Technologies, Inc.
7 Misc. 3d 592 (New York Supreme Court, 2005)
M. L. Gordon Sash & Door Co. v. Mormann
271 N.W.2d 436 (Supreme Court of Minnesota, 1978)
Barbarossa & Sons, Inc. v. Iten Chevrolet, Inc.
265 N.W.2d 655 (Supreme Court of Minnesota, 1978)
St. Paul Dredging Co. v. State
107 N.W.2d 717 (Supreme Court of Minnesota, 1961)
Wurdemann v. Hjelm
102 N.W.2d 811 (Supreme Court of Minnesota, 1960)
Vogt v. Ganlisle Holding Co.
15 N.W.2d 91 (Supreme Court of Minnesota, 1944)
Oleson v. Bergwell
283 N.W. 770 (Supreme Court of Minnesota, 1939)
Casper v. Regional Agricultural Credit Corp.
278 N.W. 896 (Supreme Court of Minnesota, 1938)
Wilson MacHinery & Supply Co. v. Fidelity & Casualty Co. of New York
110 S.W.2d 1075 (Court of Appeals of Kentucky (pre-1976), 1937)
Danielski v. Pioneer Building Co.
242 N.W. 342 (Supreme Court of Minnesota, 1932)
Drew v. Skeena Lumber Co. Ltd.
230 N.W. 819 (Supreme Court of Minnesota, 1930)
Green v. City of Rock Hill
147 S.E. 346 (Supreme Court of South Carolina, 1929)
Robb v. Parten
220 N.W. 610 (Supreme Court of Minnesota, 1928)
City of St. Paul v. Bielenberg
204 N.W. 544 (Supreme Court of Minnesota, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
201 N.W. 414, 161 Minn. 178, 1924 Minn. LEXIS 509, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-minneapolis-v-republic-creosoting-co-minn-1924.