Luling Oil & Manufacturing Co. v. Gohmert

110 S.W. 772, 50 Tex. Civ. App. 606, 1908 Tex. App. LEXIS 637
CourtCourt of Appeals of Texas
DecidedMay 8, 1908
StatusPublished
Cited by1 cases

This text of 110 S.W. 772 (Luling Oil & Manufacturing Co. v. Gohmert) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Luling Oil & Manufacturing Co. v. Gohmert, 110 S.W. 772, 50 Tex. Civ. App. 606, 1908 Tex. App. LEXIS 637 (Tex. Ct. App. 1908).

Opinion

BEESE, Associate Justice.

This is a suit by the Luling Oil & Manufacturing Company against William Gohmert and John Stratton upon a builder’s contract, and a bond executed by Gohmert as principal and Stratton as surety. The work contracted to be done by Gohmert was the erection complete of an oil mill in the town of Luling for plaintiff. To secure the performance of the work in accordance with the contract Gohmert entered into a bond with Stratton as surety in the sum of $5000. The contract price of the mill was $54,850. It was alleged that the mill was not built for the contract price, but that plaintiff had to pay out, in order to complete the mill and clear off debts and. liens contracted by Gohmert, the sum of $5615.15, in addition to the contract price. It was further alleged that the contract provided for the payment of $25 per day as liquidated damages for the delay if the work was not completed by a day named, that there was a ' delay of 60 days whereby defendants became liable for the additional sum of $1500. Plaintiff prayed for judgment against Gohmert for $7115.15, and against Stratton for $5000, being the amount of his bond.

Stratton pleaded that, without his knowledge or consent, there had *607 been certain changes made in the contract by plaintiff and Gohmert whereby additional and more expensive work was required by plaintiff and agreed to by Gohmert’s agent, Palmie, such changes in the construction being specifically set out. It was also pleaded that the contract had been violated in the time and manner of payments made to Gohmert by plaintiff, and that these deviations from the contract and changes in the terms thereof released Stratton, the surety, from obligation upon the bond.

Gohmert also answered, but as he is not a party to this appeal it is not necessary to refer further to his answer.

The case was tried by the court without a jury and judgment rendered in favor of Stratton, the court finding that the changes in the contract released him from liability. From this judgment plaintiff, the Oil "Company, appeals. There was judgment against Gohmert for $5615.15, from which no appeal was taken.

The question presented is the correctness of the judgment releasing Stratton as surety on the bond.

The first and second assignments of error are addressed to the action of the court in permitting counsel for appellee to ask certain questions of witnesses. In each case the witness answered that he did not know. The assignments are without merit.

The third assignment is also overruled as without merit.

The fourth assignment is as follows: “The court erred in overruling plaintiff’s amended motion for new trial in this case on the 2d day of July, 1907, for each and every ground set up in said motion.” The assignment is followed by the proposition that it is the duty of the court to grant a new trial when errors are called to its attention, which are sustained by the record. For statement from the record to sustain this assignment and proposition there is copied the grounds set up in the motion for new trial.

Mindful of what has been lately said by the Supreme Court in Cobb v. Johnson (101 Texas, 440) we have looked to the argument following the so-called statement and can not get out of it anything that would pass muster as such “a brief statement, in substance, of such proceedings, or parts thereof, contained in the record, as will be necessary and sufficient to explain and support the proposition, with reference to the pages of the record” as is required by rule 31. A proper consideration of the assignment would require that, without guide or index from the statement, we examine the entire statement of facts. There is no reference in either statement, or argument, to any evidence of appellee, and neither pretends to contain even a reference to all of the evidence material to the assignment. In addition, the assignment is multifarious and embraces several entirely distinct propositions, and is followed by the single very general proposition above stated. For these reasons the assignment will not be considered.

For the same reason the fifth assignment will not be considered.

The sixth assignment of error is overruled. The testimony of appellee’s witnesses shows that the changes in the work were directed to be made by Zedler, one of the building committee, who was shown to have had entire charge of the supervision of the work as the representative of the Oil Company. This testimony further tends to show that some *608 of the changes were made hy Palmie, Gohmert’s agent, under protest, and only after strenuous objection.

The seventh assignment assails the finding of fact of the trial court, that there had been changes in the contract, plans, and specifications thereunder by Gohmert and the Oil Company; and the conclusion of law that thereby appellee had been released from obligation on the bond. The statement is made in the assignment that there is no evidence authorizing the finding. The statement thereunder contains no reference to the testimony in the record, if there be any, in support of the finding of the court. With the assistance of appellee’s brief we have examined the statement of facts, with the result that we find that there is sufficient evidence to show that during the progress of the work the following changes were made in the work, upon the demand of appellant, all of which were distinct deviations from the plans and specifications, as shown by the testimony, and of which appellee had no knowledge.

By agreement between the building committee and Palmie, after the boilers had been put in to burn coal or wood, they were changed so as to burn oil. This required considerable work taking out the old work and putting in the new. One witness testified that the delay in the completion of the mill on this account amounted to, approximately, three or four weeks. The extra cost of the installation of the oil burning apparatus was paid for by appellant.

The original plan called for a seed house 60 x 250 feet in the shape of an L, that is, it was to be built 60 x 150 feet with an addition or L, 60x100 feet, according to the blue prints, as testified by the witness. After the first part was finished appellant acquired a lot which they did not have before, which enabled them to change the plan of the seed house and build it straight, 60 x 25D feet. It was found that the ground for the foundation of this extension, on the lot just acquired, was in an old tank filled with trash of various kinds and this required a good deal of extra work in digging for the foundation of the building, for which they had to go, in some places, nine feet. The cost of this extra Work was about $75 and involved a delay of about 14 days in the completion of the work. The floor in the engine room was changed from pine to maple, which involved an additional cost, the exact amount of which is not stated, further than that the pine flooring cost $28 per thousand and the maple flooring $70 per thousand. This change caused a delay of about a week. There was a change made in the main shafting, the exact nature of which can only be shown by giving the testimony of the witness, as follows: “The main shafting was changed in the meal room. After the shafting had been completed Mr. Zedler came and said that he did not want any cross-belt in these and Mr. Palmie told him that was all the contract called for; Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walsh v. Methodist Episcopal Church South, of Paducah
173 S.W. 241 (Court of Appeals of Texas, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
110 S.W. 772, 50 Tex. Civ. App. 606, 1908 Tex. App. LEXIS 637, Counsel Stack Legal Research, https://law.counselstack.com/opinion/luling-oil-manufacturing-co-v-gohmert-texapp-1908.