Constitution Indemnity Co. of Philadelphia v. Armbrust

25 S.W.2d 176
CourtCourt of Appeals of Texas
DecidedFebruary 6, 1930
DocketNo. 8337.
StatusPublished
Cited by23 cases

This text of 25 S.W.2d 176 (Constitution Indemnity Co. of Philadelphia v. Armbrust) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Constitution Indemnity Co. of Philadelphia v. Armbrust, 25 S.W.2d 176 (Tex. Ct. App. 1930).

Opinion

COBBS, J,

This suit was instituted by O. A. Armbrust and wife, Jeanette C. Armbrust, two of the appellees, against E. S. Kaler, doing business under the name of E. S. Kaler & Co., and appellant, Constitution Indemnity Company of Philadelphia.

The suit was for damages in the sum of $500, for failure on the part of Kaler to comply with the plans and" specifications in the construction of certain improvements, consisting of a house and outhouses for appellees in the city .of San Antonio, and for the further sum of $75 per month, for a period of ten months, being the alleged rental value of the premises for said period, during which the same were uncompleted according to the contract, and appellees were deprived of the use thereof. And appellees Mr. and Mrs. Arm-brust claimed that the Karren-Tobias Lumber Company had been damaged in the sum of $3,721.60, being the alleged cost of completing the house and improvements.

Attached to plaintiffs’ pleadings were voluminous invoices of items by number and amount, and also a copy of the contract made on September 15, 1927.

The provision in the contract concerning the payment of the contract price, which was typewritten into a printed contract form, was as follows: “Payable in three notes- of $2509.-00 each as first lien, and one note of $3000.00 as a second lien, evidenced by mechanics lien contract of record dated September 14th, 1927.” And the printed provision in the hond stated: “In any event, whether provided in the contract or not, ten percent of the contract price must be retained until after the completion of the contract.” The printed contract also has typewritten the word “three” in that portion of the contract wherein it provides that final payment to the contractor shall he made within “three” days after the completion and acceptance of the work included in the contract, except ten per cent, which is to be held for thirty days. These were offered in evidence by appellees to show conflict or ambiguity.

The pleadings allege a contract between Mr. and Mrs. Armbrust and O. E. Freeman for the completion of the improvements abandoned b-y E. S. Kaler & Co., in accordance with the plans and specifications ; the agreed compensation for the undertaking being an amount equivalent to the actual cost of the labor and materials necessary therefor plus ten per cent, of said amount.

And the pleadings set out the contract made by and between G. A. Armbrust and .wife and the appellee Karren-Tobias Lumber Company, which contract contains the following: “It is the intention of the parties hereto that the said Karren-Tobias Lumber Company shall advance and pay to the said C. E. Freeman the cost of completing said improvements and that they are to be reimbursed for such cost by the said Jeanette Corrine Arm-brust and C. A. Armbrust only in the event of a recovery against the said E. S. Kaler & Company or its surety, and then only to the extent of such recovery, and the said Jeanette Corrine Armbrust and C. A. Armbrust shall in no event be liable for the repayment to the said Karren-Tobias Lumber Company of the money advanced and paid by it to C. E. Freeman in excess of any amount recovered by the said Armbrusts against the E. S. Kaler & Company or the surety on its bond.”

*178 The defendant E. S. Kaler & Co. filed responsive pleadings.

The evidence of E. S. Karren, president of the Karren-Tobias Lumber Company, showed that ten per cent, of the contract price was not retained and that he, for his company, had advanced the sum of $10,329.09 out of the agreed contract price of $10,500 to Kaler before Kaler abandoned the contract. Also, it was shown that the notes set out in the contract were made payable to the Karren-To-bias Lumber Company for security for advances made to Kaler, and that a commitment was obtained before the work was started, for the three notes of $2,500 each, which ■ commitment was procured by appellees Arm-brusts, of which fact appellant claims it had no actual notice. It was further shown that the $3,000 note was indorsed by the Karren-Tobias Lumber Company, and they received the sum of $3,000 therefor.

It was shown that all the money provided for. in the contract price, except the sum of $500 architects’ fee, was paid out without any certificates of any kind from the architect.

The court, at the conclusion of the evidence, submitted the two following issues to the jury:

“1. Was it the intention of the parties to the contract and bond, that ten percent of the contract price should be retained, by the owners, until the improvements were completed and accepted in accordance with the plans and specifications?
“Answer ‘Yes’ or ‘No.’
“We the jury, answer No.
“If you answer the foregoing question ‘no’ then you need not answer the following question, but if you answer the same ‘yes’ then answer the following question:
“2. Did Jeanette O. and C. A. Armbrust retain ten percent of the contract.price until after the completion and acceptance of the. improvements?
“Answer ‘Yes’ or ‘No.’
“We the jury, answer-

Since issue No. 1 was answered in the negative, issue No. 2 needed no answer by the jury.

Whereupon the court rendered a verdict against appellant in favor of appellees C. A. Armbrust and wife for the sum of $315 and in favor of the appellee Karren-Tobias Lumber Company for the sum of $4,211.85, with interest from February 1, 1927.

We do not think the court erred in submitting the issue to the jury as to what was the intention of the parties in respect to the provision as to retaining ten per cent, of the contract price until the improvements were completed. It will be observed that the contract between the parties was prepared on a printed form, and that in the blank, as to the manner of payment, was typewritten the following provisions: “Payable in three notes of $2500 each, as first lien, and one for $3,000.00, as a second lien, evidenced by mechanic’s lien contract of record, dated September 14,1927.” These provisions conflict with those recited in the printed contract, as follows: “The final payment shall be made within three (3) days after the completion and acceptance of the work included in this contract except ten percent which will be held for thirty (30) days unless satisfactory evidence is furnished that all claims of every nature have been paid.” And the bond provides: “The obligee shall retain that portion of the contract price which such contract specifies the obligee shall or may retain of the value of all work performed or materials furnished in the prosecution of the contract until the complete performance by the principal of all the terms, covenants and conditions of said contract on the principal’s part to be performed.”

Really it was not necessary for the court to submit the issue, because under the well-known established principles of law tie typewritten provisions of the contract superseded the inconsistent printed provisions, and the intention of the parties was established by such typewritten provisions; however, there was no injury to appellant in the submission of the issue. And there is no injury shown. Jones v. Roche (Tex. Civ. App.) 244 S. W. 227; Magnolia Petroleum Co. v. Connellee (Tex. Com.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Green Meadow Oil & Gas Corp. v. EOG Resources, Inc.
390 S.W.3d 625 (Court of Appeals of Texas, 2012)
State of Tennessee v. William Toby Johnson
Court of Criminal Appeals of Tennessee, 2011
State of Tennessee v. Ashley Mai Cook
Court of Criminal Appeals of Tennessee, 2011
Interfirst Bank Dallas, N.A. v. United States Fidelity & Guaranty Co.
774 S.W.2d 391 (Court of Appeals of Texas, 1989)
Huckabee v. Lomas & Nettleton Co.
550 S.W.2d 371 (Court of Appeals of Texas, 1977)
McBroome-Bennett Plumbing, Inc. v. Villa France, Inc.
515 S.W.2d 32 (Court of Appeals of Texas, 1974)
Northwestern National Insurance Co. v. Kirchoff
427 S.W.2d 638 (Court of Appeals of Texas, 1968)
Harry F. Frey & Company v. Wd Lacy Feed Company
272 S.W.2d 765 (Court of Appeals of Texas, 1954)
Hancock v. Sammons
267 S.W.2d 252 (Court of Appeals of Texas, 1954)
Lynch v. Crockett Independent School Dist.
244 S.W.2d 564 (Court of Appeals of Texas, 1951)
Kidd v. Hickey
237 S.W.2d 389 (Court of Appeals of Texas, 1950)
Page v. Hancock
200 S.W.2d 421 (Court of Appeals of Texas, 1947)
Brand Inv. Co. v. United States
58 F. Supp. 749 (Court of Claims, 1944)
Southern Underwriters v. Hodges
141 S.W.2d 707 (Court of Appeals of Texas, 1940)
Texas Indemnity Ins. Co. v. Hubbard
138 S.W.2d 626 (Court of Appeals of Texas, 1940)
Stevenson v. Wilson
130 S.W.2d 317 (Court of Appeals of Texas, 1939)
Employers' Liability Assur. Corp. v. Eckert
46 S.W.2d 464 (Court of Appeals of Texas, 1932)
Armour & Co. v. Tomlin
42 S.W.2d 634 (Court of Appeals of Texas, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
25 S.W.2d 176, Counsel Stack Legal Research, https://law.counselstack.com/opinion/constitution-indemnity-co-of-philadelphia-v-armbrust-texapp-1930.