Airco, Inc. v. United States

504 F.2d 1133, 20 Cont. Cas. Fed. 83,421, 205 Ct. Cl. 493, 1974 U.S. Ct. Cl. LEXIS 18
CourtUnited States Court of Claims
DecidedOctober 23, 1974
DocketNo. 160-73
StatusPublished
Cited by7 cases

This text of 504 F.2d 1133 (Airco, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Airco, Inc. v. United States, 504 F.2d 1133, 20 Cont. Cas. Fed. 83,421, 205 Ct. Cl. 493, 1974 U.S. Ct. Cl. LEXIS 18 (cc 1974).

Opinion

Davis, Judge,

delivered the opinion of the court:

In August 1971 the Air Force agreed to purchase from plaintiff Aireo, Inc., through the Aireo division which is engaged in selling industrial gases, some 4,250 pounds of propellant hydrogen (in liquid form) at a price of $80,217.50. The contract also established a rental charge of $12 per day for the contractor-furnished containers, this charge to begin on the 31st day of the Government’s possession of the container. Delivery of the gas was to be made f.o.b., after receipt of a delivery schedule from the Government, to two facilities, one in Phoenix, Arizona, and the other in Saugus, California. The contract provided: “Delivery schedules may 'be issued at the sole option of the Government during period of performance set forth on the applicable Commitment Document.” The “effective period” for the contract was stated to be August 13, 1971 through November 15, 1971. During this three-month time-span plaintiff received orders for less than 200 pounds of the hydrogen, which was delivered.

On January 28, 1972, Aireo wrote the contracting officer recalling that the contract obligated defendant to purchase 4,250 pounds at the price of $30,217, but that only a small fraction of that amount had been ordered by the end of the contract period. The letter continued:

Inasmuch as the Government has defaulted on its obligation to purchase the quantity as stipulated in the contract, we are billing you for the balance due. The [496]*496attached invoice has been prepared for the amount due of $30,091.50.
Aireo continues to hold in reserve status the two each 1000 liter liquid hydrogen dewars [containers] and with no advice to the contrary, will continue to hold these in reserve status for the Government at the agreed rental of $12 per day per container. Charges for the rental have been included in the invoice through December 31,1971.

Next, the Government sent, on February 17,1972, a telegram (followed by a letter to the same effect on February 24th) terminating the contract as of February 17th under its convenience-termination clause. In May 1972 plaintiff submitted a termination settlement claim, on the Defense Department form for termination settlement proposals, requesting a total of $8,962. There followed an exchange of communications and a negotiation conference, but apparently no accord was reached.

Early in December 1972 the Government wrote that the Termination Contracting Officer intended to render a unilateral determination of the amount due for the termination. Plaintiff was asked to present any further written evidence supporting its claim. In apparent response, plaintiff, toward the end of December, asked for $13,711 as “our damages for the Government’s breach” of the contract, rejecting the termination notice of February 1972 as too late, and declaring that its settlement proposal (and the ensuing-settlement effort) had been submitted and carried on in an unsuccessful attempt to compromise damages for breach of contract, and not under the termination clause. This letter from Aireo was followed very shortly by a unilateral determination by the contracting officer that only $503.21 was due the contractor.

Aireo did not appeal to the Armed Services Board of Contract Appeals. Instead it began this suit for breach of contract, asserting (as it had in its letter of December 1972 to the contracting officer) that the Government had already committed a material breach, and the contract was therefore at an end, well before the termination notice in February 1972. Contending that the termination was valid when issued [497]*497and that plaintiff has failed to exhaust its administrative remedy through appeal to the ASBCA, defendant has moved to dismiss the petition.

On the basis of the record we have before us on this motion to dismiss, we would have to say that the plaintiff was free, if such a move was timely made after November 15th, to declare expressly, or indicate in effect, that it considered the contract materially breached, and at an end, because of the Government’s gross failure to order by November 15th the quantity of gas it undertook to buy.1 Cf. Nolan Bros. v. United States, 186 Ct. Cl. 602, 609 n.5, 405 F. 2d 1250, 1255 n.5 (1969) ; Clement Bros. v. United States, 190 Ct. Cl. 50, 418 F. 2d 1356 (1969) ; Northern Helex Co. v. United States, 197 Ct. Cl. 118, 455 F. 2d 546 (1972) ; William Green Constr. Co. v. United States, 201 Ct. Cl. 616, 477 F. 2d 930 (1973), cert. denied, 417 U.S. 909 (1974). The question for decision is whether plaintiff actually took that course, or whether it elected, instead, to treat the contract as still viable and continuing in operation.

Airco’s post-November 15th conduct, and its exchanges with the Government, impel us to conclude that it chose the latter route. Its first contact with the defendant after November 15th was the letter of January 28, 1972 (quoted supra, in pertinent part) the contents of which are inconsistent with plaintiff’s current view that at that time it deemed the agreement totally breached and at an end. If that had been Airco’s stand, in January 1972, it would have asked for breach damages, i.e. the contract price less the amount it could obtain elsewhere for the gas. Instead, it billed the Air Force for the full balance of the contract price, just as one would do if he had decided to treat the contract as continuing to subsist and remain in effect. The plain implication was that the gas would still be delivered if the Air Force ordered it.

Moreover, and very significantly, plaintiff told the defendant in the same letter that it was holding two con-[498]*498tamers for the Government’s use “at the agreed rental of $12 per day per container”, and that “[c]harges for the rental have been included in the invoice through December 31,1971.” If Aireo had deemed the contract ended in the preceding November, there would have been no rental charge for December and no advice that Aireo was keeping the containers “in reserve status” for the Government. The letter must be read, rather, as an express indication that plaintiff considered the contract to be still alive and operative.

When it received the defendant’s termination notice, some three weeks later, Aireo continued to act under and within the confines of the contract, by appearing to accept the termination as fully valid and by following the procedures established for termination claims. In May 1972, the contractor sent to the Termination Contracting Officer a settlement proposal on a printed form to be used in settlement of “a fixed price terminated contract when total charges claimed are less than $10,000.” In the space asking for the “Effective Date of Termination”, plaintiff inserted “2/17/72”, i.e. the date of the Government’s termination notice. The amount sought was $8,962.2 When the contracting officer asked for justification of this claim, Aireo responded with its specific answers and without any indication that it considered the termination to have been improper, ineffective, or invalid. Later, after oral conversations with the federal representatives about the amoimt of the claim, Aireo gave, in written form, further information on the points still at issue, again without any intimation that it viewed the termination as inoperative.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Godley v. United States
38 Cont. Cas. Fed. 76,386 (Court of Claims, 1992)
Aleutian Constructors v. United States
37 Cont. Cas. Fed. 76,203 (Court of Claims, 1991)
Government Systems Advisors, Inc. v. United States
36 Cont. Cas. Fed. 75,937 (Court of Claims, 1990)
Samuel T. Isaac & Associates, Inc. v. United States
3 Cl. Ct. 528 (Court of Claims, 1983)
Shermco Industries, Inc. v. United States
30 Cont. Cas. Fed. 70,355 (Court of Claims, 1982)
Cities Service Helex, Inc. v. United States
543 F.2d 1306 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
504 F.2d 1133, 20 Cont. Cas. Fed. 83,421, 205 Ct. Cl. 493, 1974 U.S. Ct. Cl. LEXIS 18, Counsel Stack Legal Research, https://law.counselstack.com/opinion/airco-inc-v-united-states-cc-1974.