United States of American, ex Rel. v. Manhattan Hunt, A Joint Venture

CourtDistrict Court, D. Maryland
DecidedMarch 31, 2021
Docket8:16-cv-02980
StatusUnknown

This text of United States of American, ex Rel. v. Manhattan Hunt, A Joint Venture (United States of American, ex Rel. v. Manhattan Hunt, A Joint Venture) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of American, ex Rel. v. Manhattan Hunt, A Joint Venture, (D. Md. 2021).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND Southern Division

*

UNITED STATES OF AMERICA ex rel., BUNTING GRAPHICS, INC *

Plaintiff, * Case No.: 16-cv-2980-PWG v. *

MANHATTAN HUNT, A JOINT * VENTURE, * Defendant. * * * * * * * * * * * * * *

MEMORANDUM OPINION Before the Court are the parties’ cross motions for summary judgement. This case originated out of a subcontract dispute between Plaintiff United States of America, ex. rel., Bunting Graphics, Inc. (“Bunting”) and Defendant Manhattan Hunt, A Joint Venture (“MHJV”). MHJV hired Bunting to perform metal fabrication and installation services during construction of a new Ambulatory Care Center and replacement Dental Clinic at Andrew’s Air Force Base in Prince George’s County, Maryland (“Project”). Compl. ¶ 13, ECF No. 6. The parties completed discovery on November 29, 2019 and proceeded to file cross motions for summary judgment. Bunting argues that MHJV cannot show that its decision to terminate Bunting from the Project for default, rather than for convenience, was legally justifiable. MHJV, on the other hand, argues that it is entitled to partial summary judgment on the issue of termination because its decision to terminate Bunting was indisputably justified under Maryland law. The parties fully briefed the motions (ECF Nos. 82, 85, 90, 91) and a hearing is not necessary. See Loc. R. 105.6 (D. Md. 2018). For the reasons that follow, Bunting’s motion is denied and MHJV’s motion is granted.

Factual Background Bunting, a Pennsylvania company based in Verona, PA, entered into a contract with MHJV, which is based in Tulsa, Oklahoma, in July 2013 to perform miscellaneous metal fabrication and installation at the Andrews Air Force Base Project. Compl. ¶¶ 4, 5, 13. The contract’s value exceeded $3,000,000. Id. ¶ 13. Bunting claims that MHJV directed it to perform additional work and has yet to compensate Bunting for the value of that work, which exceeds $190,000. Id. at 24. In total, Bunting alleges MHJV owes Bunting $1,163,985.02. Id. ¶ 28. The non-payments were an issue during “Phase I” of the project when MHJV ceased making payments to Bunting, which resulted in Bunting sending MHJV a notice of default due to nonpayment on June 23, 2015. Id. ¶¶ 39, 40. Bunting continued its work and Phase I of the project reached “Beneficial Occupancy,” or BOD, on February 26, 2016. Id. ¶ 44. According to Bunting, all that

remained for it to complete was “very minor punchlist work.” Id. ¶ 46. Bunting alleges it had completed 99% of its subcontract work on March 17, 2016 when MHJV terminated the contract for default. Id. ¶ 47. Bunting brought this suit seeking to convert the termination for default to termination for convenience, which would entitle it to costs plus reasonable overhead and profit. Bunting’s complaint against MHJV asserts a breach of contract claim and an alternative claim for unjust enrichment. MHJV, on the other hand, views the facts quite differently. According to the statement of facts in MHJV’s cross motion, at the end of Phase 1, MHJV discovered that Bunting provided improper materials for several of its performance obligations under the terms of the parties’

agreement. Def.’s Opp. & Cross Mot. 4, ECF No. 85-1. According to MHJV, it confronted Bunting about the issues and, in accordance with the parties’ agreement, demanded that Bunting cure the issues MHJV discovered. Id. Bunting declined to do so, and MHJV terminated Bunting for default. Id.

The Parties’ Agreement The contract at issue here is attached as Exhibit A to Bunting’s motion for summary judgment. Throughout their briefs, the parties reference several important clauses of the contract, and I find it would be worthwhile to note those provisions here. Section 1.3, titled “The Work” describes the scope of Bunting’s obligations under the contract, such as its obligation to perform and furnish all supervision, labor, and materials “necessary for the construction and completion of the work . . . .” Ex. A to Pl.’s Mot. at 4, ECF

No. 82-2. Importantly, § 1.3 requires that the work described in the subcontract and all work “incidental thereto or reasonably inferable therefrom, [be] in strict accordance and in full compliance with the terms of the Contract Documents.” Id. Section 2.4.1 addresses the subcontractor’s liability and made Bunting responsible and liable for all work, supervision, labor, and materials. It charged Bunting with prosecuting “the Work in a good and workmanlike manner, with diligence and continuity.” Id. at 6. And, particularly relevant to the issues here, stated “[i]n the event of any loss, damage or destruction thereof from any cause, subcontractor shall be liable therefore, and shall repair, rebuild and make good said loss, damage or destruction at Subcontractor’s cost.” Id. at 6. The next section, § 2.4.2, made Bunting liable to MHJV for all costs MHJV incurred as a result of Bunting’s failure to

perform. Id. at 7. Section 2.13.1 is titled “Inspection and Acceptance.” It charged Bunting with promptly replacing or correcting “any Work or materials which MHJV or the Owner shall reject as failing to conform to the requirements of this Subcontract. If Subcontractor does not do so within the time required by the Contract Documents . . . MHJV shall have the right to do so and Subcontractor shall be liable to MHJV for the cost thereof.” Id. at 10. Section 3.3, “Continuing Contract Performance,” required Bunting to “proceed diligently

with performance of its Work and [to] follow any decision by MHJV with respect to the dispute until final resolution.” Id. at 11. Section 9.1 is perhaps the most important contract provision for the issues present here. It reads [i]f, in the opinion of MHJV, Subcontractor shall at any time (a) refuse or fail to provide sufficient properly skilled workers, adequate supervision or materials of the proper quality, (b) fail in any material respect to prosecute the Work according to MHJV’s current schedule, (c) cause, by any act or omission, the stoppage or delay of or interference with the Work of MHJV . . . (d) fail to comply with any provision of this Subcontract or the Contract Documents . . . then, after serving forty-eight (48) hour written notice . . . unless the condition specified in such notice shall have been eliminated within such forty-eight (48) hours, MHJV, at its option, without voiding the other provisions of this Subcontract and without notice to the sureties . . . may (i) take such steps as are necessary to overcome or correct the condition (including supplementing the work of Subcontractor), in which case the Subcontractor shall be liable to MHJV for the cost thereof [or] (ii) terminate for default Subcontractor’s performance of all or a part of the Subcontract Work . . . . Id. at 17. Section 9.2 barred any further payment to Bunting in the event MHJV exercised its rights under § 9.1 until the Work was fully completed and accepted by the Owner. Section 9.3 provided Bunting with a remedy in the event MHJV wrongfully exercised its option to terminate for default. Wrongful termination for default, under the contract, would be converted to termination for convenience, which would entitle Bunting to certain compensation specified in § 10. Id. That compensation would include “the reasonable value of the Work performed by [Bunting] prior to termination plus reasonable direct close-out costs, including job site overhead and profit on Work performed, but in no event [would] Subcontractor be entitled to unabsorbed overhead, anticipatory profit or damages of any kind or nature, direct or indirect, incidental or consequential.” Id. at 18.

Standard of Review Summary judgment is proper when the moving party demonstrates, through “particular parts of materials in the record, including depositions, documents, electronically stored information, affidavits or declarations, stipulations .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Ricci v. DeStefano
557 U.S. 557 (Supreme Court, 2009)
Oakley Baldwin v. City of Greensboro
714 F.3d 828 (Fourth Circuit, 2013)
George & Co. LLC v. Imagination Entertainment Ltd.
575 F.3d 383 (Fourth Circuit, 2009)
Regal Savings Bank v. Sachs
722 A.2d 377 (Court of Appeals of Maryland, 1999)
Shade v. State
509 A.2d 664 (Court of Appeals of Maryland, 1986)
Matzelle v. Pratt
332 F. Supp. 1010 (E.D. Virginia, 1971)
Continental Illinois Nat. Bank & Trust Co. v. United States
101 F. Supp. 755 (Court of Claims, 1952)
Equal Rights Center v. Archstone Smith Trust
603 F. Supp. 2d 814 (D. Maryland, 2009)
H & R BLOCK, INC. v. Garland
359 A.2d 130 (Court of Appeals of Maryland, 1976)
Clancy v. King
954 A.2d 1092 (Court of Appeals of Maryland, 2008)
Cole v. PRINCE GEORGE'S COUNTY, MD.
798 F. Supp. 2d 739 (D. Maryland, 2011)
Volos, Ltd. v. Sotera
286 A.2d 101 (Court of Appeals of Maryland, 1972)
Prescon Corp. v. Savoy Construction Co.
267 A.2d 222 (Court of Appeals of Maryland, 1970)
Rourke v. Amchem Products, Inc.
835 A.2d 193 (Court of Special Appeals of Maryland, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
United States of American, ex Rel. v. Manhattan Hunt, A Joint Venture, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-american-ex-rel-v-manhattan-hunt-a-joint-venture-mdd-2021.