ECC International, LLC

CourtArmed Services Board of Contract Appeals
DecidedNovember 16, 2018
DocketASBCA No. 60484
StatusPublished

This text of ECC International, LLC (ECC International, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ECC International, LLC, (asbca 2018).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) ECC International, LLC ) ASBCA No. 60484 ) Under Contract No. W5J9LE-11-C-0045 )

APPEARANCES FOR THE APPELLANT: R. Dale Holmes, Esq. Michael A. Richard, Esq. Cohen Seglias Pallas Greenhall & Furman PC Philadelphia, PA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Sarah L. Hinkle, Esq. Matthew S. Tilghman, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE WOODROW ON THE PARTIES' CROSS-MOTIONS FOR SUMMARY JUDGMENT

Pending before the Board are the parties' cross-motions for summary judgment filed by appellant, ECC International, LLC (ECCI), and the United States Army Corps of Engineers (USACE or government). ECCI seeks summary judgment on entitlement to its monetary claim for costs arising out of the government's closure of the Friendship Gate, an access route to ECCI's construction site on Camp Shorab in Afghanistan. The government moves for summary judgment on the grounds that the government's closure of Friendship Gate was a sovereign act and ECCI assumed the risk of any changes to base access procedures or requirements.

We hold that the plain language of the contract states that the contractor bears the risk of changes to base access requirements and that the closure of Friendship Gate was not a constructive change to the terms of the contract. We further hold that the government did not create an implied warranty of access through Friendship Gate, and that ECCI's previous contracts at Camp Shorab in Afghanistan did not create an implied warranty of continued access to the project site through Friendship Gate.

We do not reach the government's affirmative defense that the closure of the Friendship Gate was a sovereign act, because we have concluded that there is no express or implied contractual right of access through the Friendship Gate and that the closure of Friendship Gate was not a constructive change.

Therefore, we grant the government's motion for summary judgment and deny the appeal.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS

A. The Contract

1. On June 29, 2011, USACE issued Solicitation No. W5J9LE-l l-B-0004 (solicitation) requesting proposals from prospective bidders for the site adapt, design and construction of the 215th compound expansion, Camp Shorab, Helmand Province, Afghanistan (R4, tab 3 at 1).

2. The solicitation contained the following provision relating to compliance with orders relating to force protection: ·

C3 CLAUSE 952.225-0002 ARMED PERSONNEL INCIDENT REPORTS (SEP 2010)

(a) All contractors and subcontractors in the United States Forces-Iraq (USF-I) or United States Forces-Afghanistan (USFOR-A) theater of operations shall comply with and shall ensure that their personnel supporting USF-I or USFOR-A forces are familiar with and comply with all applicable orders, directives, and instructions issued by the respective USF-I or USFOR-A Commanders relating to force protection and safety.

(R4, tab 3 at 50)

3. Section 01040 of the solicitation contained the following provision relating to security in a wartime contingency environment:

1.0 SPECIFIC CONTRACT SECURITY ASSESSMENT

The Contractor will construct the Project in an active war zone where International Security Assistance Forces (ISAF) may conduct offensive and defensive operations against a variety of hostile forces, to include members of the Taliban. The Contractor understands that it may not receive any

2 support whatsoever in securing the Project site and in securing the transportation of materials to the Project site.

(R4, tab 3 at 170)

4. Section O1040 of the solicitation further stated that the contractor is responsible for its own security and securing the transportation of materials to the project site. "Neither U.S. Government nor other ISAF forces are available to provide exclusive security for the Project. The Contractor is responsible for securing the Project site and in securing the transportation of materials to the Project site." (R4, tab 3 at 170)

5. The solicitation included the following language regarding the operations of ISAF or hostile forces:

The Contracting Officer possesses no ability to control the operations of either ISAF or hostile forces. The Government, acting in its sovereign capacity in its prosecution of its operations, may take actions which directly or indirectly affect the Contractor. These kinds of acts are general in application, not specifically directed at the Contractor. The Contractor recognizes that such actions may be taken, and that they will not entitle the Contractor to make claims for excusable or compensable delays.

6. The solicitation required the contractor to formulate its own security plan, taking into account the changing operational picture in the region.

The Contractor possesses sufficient information about the specific security situation at the site to enable it to formulate an appropriate security plan. The Contractor understands that the security situation at the Project is subject to significant transformation in a short time span based on the changing operational picture in the region. The Contractor's security plan will take this factor into account.

7. On July 30, 2011, ECCi submitted a proposal in response to the solicitation in the amount of $29,904,252 (R4, tab 36). The proposal included the following statement: "ECC International, LLC agrees with all terms, conditions, and provisions included in the

3 solicitation and agrees to furnish any or all items upon which prices are offered at the price set opposite each item" (id. at 1).

8. On August 11, 2011, USACE awarded Contract No. W5J9LE-11-C-0045 to appellant (R4, tab 37).

9. The contract incorporated by reference the terms of the solicitation (R4, tab 5 at 2).

10. Contract section 01010, Scope of Work, ,i 2.2, Security, provides that "[a] detailed security plan in accordance with Section O1040 SECURITY shall be approved by the Government before construction notice to proceed" (R4, tab 3 at 68, 71 ).

11. Contract section O1040, ,i 5.0, Security Plan, states:

The Security Officers will review and approve all current and future Contractor security plans prior to submittal approval by the authorized representative of the Contracting Officer. The Security Officers shall ensure that all Contractor security plans are in accordance with the Contract requirements. The security plans shall address movement of Contractor labor, material, and equipment. The Security Officers will lead the quality assurance program to ensure Contractors are executing their approved security plans. The Government will not allow the Contractor to start work on the Project site without an approved security plan.

(R4, tab 3 at 171)

12. During performance of the contract, ECCI prepared both a Security Plan and an Area Use Plan that contemplated use of the Friendship Gate for moving workers from its existing Life Support Area (LSA) on Camp Leatherneck to the project site on Camp Shorab (R4, tab 38).

13. ECCI's Security Plan and Area Use Plan contemplated use of the Friendship Gate for moving concrete from the concrete batch plants on Camp Leatherneck or Camp Bastion to the project site (R4, tab 38; app. mot., Canon aff. ,i 16).

14. ECCI's proposed Area Use Plan expressly stated that it "is a discussion document for further evaluation in cooperation with USACE management" (R4, tab 38 at 7).

4 15. The government approved ECCI's Area Use Plan and Security Plan (R4, tab 40).

16.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horowitz v. United States
267 U.S. 458 (Supreme Court, 1925)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
CONNER BROS. CONST. CO., INC. v. Geren
550 F.3d 1368 (Federal Circuit, 2008)
Pure Gold, Inc. v. Syntex (u.s.a.), Inc.
739 F.2d 624 (Federal Circuit, 1984)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
ECC International, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ecc-international-llc-asbca-2018.