Orlando Helicopter Airways, Inc. v. Sheila Widnall, Secretary of the Air Force

51 F.3d 258, 40 Cont. Cas. Fed. 76,763, 1995 U.S. App. LEXIS 5706, 1995 WL 121581
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 23, 1995
Docket94-1399
StatusPublished
Cited by15 cases

This text of 51 F.3d 258 (Orlando Helicopter Airways, Inc. v. Sheila Widnall, Secretary of the Air Force) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Orlando Helicopter Airways, Inc. v. Sheila Widnall, Secretary of the Air Force, 51 F.3d 258, 40 Cont. Cas. Fed. 76,763, 1995 U.S. App. LEXIS 5706, 1995 WL 121581 (Fed. Cir. 1995).

Opinion

BENNETT, Senior Circuit Judge.

Orlando Helicopter Airways, Inc. (OHA), seeks to recover excess costs it incurred on a firm fixed price contract when the government investigated it for safety violations and fraud. The Armed Services Board of Contract Appeals (Board) held that the sovereign acts doctrine barred recovery of costs which stemmed from the government’s criminal investigation, but that OHA might still recover costs for changes the contracting officer imposed. Orlando Helicopter Airways, Inc., ASBCA No. 45778, 94-2 BCA 126, 751, at 133,080. Because the Board did not err in exercising jurisdiction over this contract claim or in granting partial summary judgment on the sovereign acts affirmative defense, we affirm.

BackgRound

On May 14, 1987, the U.S. Army Missile Command (MICOM) awarded OHA a letter contract to produce fifteen working helicopter replicas. A firm fixed price contract superseded that letter contract on May 2, 1988. In October 1989, a whistle-blower accused OHA of flight safety violations and fraud in performing its contract. That accusation prompted the Defense Criminal Investigative Service and the Department of Justice to open a criminal investigation of OHA in late 1989. The criminal investigation closed in May 1992, when the U.S. attorney declined to bring charges. While those agencies pursued that investigation, the contracting officer independently issued a stop work order on February 21, 1990, and directed OHA to provide a detailed response to the whistle-blower’s accusations. The contract ing officer also participated in a technical review conducted between February 26, 1990, and March 1, 1990. The contracting officer allowed OHA to resume production on March 6, 1990, subject to certain conditions. On May 3, 1991, OHA submitted a claim for $10,722 to the contracting officer for costs incurred due to the stop work order and technical review. On June 26, 1991, the contracting officer denied that claim, but the decision letter omitted the notice of appeal rights required by the Contracts Disputes Act. 41 U.S.C. § 605(a) (1988 & Supp. V 1993), amended by Federal Acquisition Streamlining Act of 1994, Pub.L. No. 103-355, §§ 2351, 605(a), 108 Stat. 3243, 3322 (1994); 48 C.F.R. § 33.211(4)(v) (1994). OHA did not further pursue that claim.

On September 15, 1992, OHA submitted a claim for $945,310 for costs and expenses “related to the investigation of fraud charges.” In a December 3, 1992, decision the contracting officer denied the claim because OHA asserted entitlement under a cost accounting provision applicable only to cost reimbursement contracts, not to firm fixed *260 price contracts like OHA’s. OHA then amended its claim to predicate entitlement on the Changes clause. The contracting officer denied that claim in a final decision dated January 20,1993. On February 26,1993, the contractor filed its notice of appeal to the Board. The government moved for summary judgment before the Board. The Board held that law enforcement investigations not initiated by the contracting officer are sovereign acts, and therefore granted the government’s motion with respect to costs incurred in responding to the criminal investigation. However, the Board also held that the costs incurred due to the stop work order and the technical review might be recoverable under the Changes clause, and therefore denied the government’s motion as to those costs. On July 6, 1994, the contractor filed its notice of appeal with this court.

Analysis

As an initial matter, the court raises sua sponte the question of its own jurisdiction. See Booth v. United States, 990 F.2d 617, 620 (Fed.Cir.1993) (observing that an inquiry into jurisdiction is always timely). Pursuant to our jurisdictional statute, we review a decision of a Board of Contract Appeals only if that decision is final. 28 U.S.C. § 1295(a)(10) (1988 & Supp. V 1993); Garrett v. General Elec. Co., 987 F.2d 747, 751 (Fed.Cir.1993); Fairchild Republic Co. v. United States, 810 F.2d 1123, 1125 (Fed.Cir.1987). This doctrine of finality embodies the policy of avoiding piecemeal litigation and the delays attendant upon appellate review of nonfinal decisions. Teller Environmental Sys. v. United States, 802 F.2d 1385, 1388 (Fed.Cir.1986). The requirement of a final decision compels a party to raise all assignments of error in one appeal. The rule preserves the respect due administrative judges at the Board by minimizing appellate interference with their function. It deters litigants from harassing opponents and clogging the courts with expensive and time-consuming appeals. It is crucial to the efficient administration of justice. See, e.g., Flanagan v. United States, 465 U.S. 259, 263-64, 104 S.Ct. 1051, 1054, 79 L.Ed.2d 288 (1984); Teledyne Continental Motors v. United States, 906 F.2d 1579, 1581-82 (Fed. Cir.1990); Fairchild, 810 F.2d at 1125. Nevertheless, we do not impose on Board decisions a strict finality requirement in exact congruence with that imposed on district court decisions. General Motors Corp. v. Aspin, 24 F.3d 1376, 1380 (Fed.Cir.1994); Garrett, 987 F.2d at 751; Dewey Electronics Corp. v. United States, 803 F.2d 650, 654 (Fed.Cir.1986).

At oral argument, the government contended that this court could exercise jurisdiction under the principles set forth in Dewey. There the contracting officer denied entitlement on nine claims without considering quantum. Dewey, 803 F.2d at 652-53 & n. 2. On four of those claims the Board upheld the contracting officer, but on five it disagreed and remanded to the parties to negotiate quantum. Id. at 653. The contractor appealed to this court the four claims on which it had lost. This court asserted jurisdiction without awaiting a determination of quantum in the five claims not on appeal. Id. at 658. Dewey, however, is not on all fours with this case, because that case included multiple claims whereas this case contains only one. In the case at bar, the notice of appeal to the Board stated that OHA appealed from the contracting officer’s decisions of December 3, 1992, and January 22, 1993. Both of those decisions were entered on the single claim for $945,300 submitted September 15, 1992.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meltech Corporation, Inc.
Armed Services Board of Contract Appeals, 2026
ECC International Constructors, LLC
Armed Services Board of Contract Appeals, 2021
ECC International, LLC
Armed Services Board of Contract Appeals, 2018
JRS Management v. Lynch
621 F. App'x 978 (Federal Circuit, 2015)
CONNER BROS. CONST. CO., INC. v. Geren
550 F.3d 1368 (Federal Circuit, 2008)
City of Gettysburg v. United States
64 Fed. Cl. 429 (Federal Claims, 2005)
Carabetta Enterprises, Inc. v. United States
58 Fed. Cl. 563 (Federal Claims, 2003)
Coast Federal Bank v. United States
49 Fed. Cl. 53 (Federal Claims, 2001)
Coast Federal Bank, FSB v. United States
48 Fed. Cl. 402 (Federal Claims, 2000)
Conoco Inc. v. United States
35 Fed. Cl. 309 (Federal Claims, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
51 F.3d 258, 40 Cont. Cas. Fed. 76,763, 1995 U.S. App. LEXIS 5706, 1995 WL 121581, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orlando-helicopter-airways-inc-v-sheila-widnall-secretary-of-the-air-cafc-1995.