ECC International Constructors, LLC

CourtArmed Services Board of Contract Appeals
DecidedMay 17, 2021
DocketASBCA No. 59586
StatusPublished

This text of ECC International Constructors, LLC (ECC International Constructors, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ECC International Constructors, LLC, (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) ECC International Constructors, LLC ) ASBCA No. 59586 ) Under Contract No. W912ER-10-C-0054 )

APPEARANCES FOR THE APPELLANT: R. Dale Holmes, Esq. Michael H. Payne, Esq. Cohen Seglias Pallas Greenhall & Furman PC Philadelphia, PA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Sarah L. Hinkle, Esq. Geoffrey A. Mueller, Esq. Matthew Tilghman, Esq. Kathryn G. Morris, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE MCILMAIL ON GOVERNMENT’S MOTION TO DISMISS FOR LACK OF JURISDICTION

This appeal was consolidated (not merged) with ASBCA No. 59643, see generally Avant Assessment, LLC, ASBCA No. 58867, 16-1 BCA ¶ 36,436 at 177,601 (distinguishing consolidation from merger), and was heard with ASBCA No. 59643. In the interest of efficiency, we address the jurisdictional challenge to this appeal separately. The government moves for the dismissal of the appeal for lack of jurisdiction, saying that appellant, ECC International Constructors, LLC (ECCI), did not provide sums certain for what the government says are separate claims. This opinion addresses that issue. In addition, in post-hearing briefing both parties claim $940,274 in liquidated damages. That issue will be addressed in a separate opinion.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

In September 2010, the parties contracted for ECCI to design and construct a military compound in Afghanistan (R4, tab 5 at 2, 179 § 1.1). On February 12, 2014, ECCI submitted to the contracting officer a demand for $13,519,913.91 for 329 days of alleged government delay in three categories: (1) changes to address security requirements for the contract; (2) review of the 95% and 100% design submissions; and (3) other directives to perform additional work or to change the requirements of the contract (R4, tab 72 at 1). The submission breaks the $13,519,913.91 demand amount into cost elements (e.g., labor, labor overhead, equipment, etc.), but does not break it down by particular delay categories or events (R4, tab 72 at 270). Nor does the breakdown include any component for the return of liquidated damages (id.); indeed, the February 12, 2014 submission to the contracting officer does not request remission of liquidated damages.

In its claim to the contracting officer, ECCI explained the basis of its claim of alleged delays to the 95% and 100% design submissions:

While developing the initial design deliverables, ECCI began incurring delays resulting from longer than scheduled Government design review periods . . . . The most notable impact to our design schedule after 10 July 2011 was derived from excessive delays in the Government’s issuance of the “Utility Consolidation” or “Site Synchronization” modification, requiring significant changes to the design of site civil and utility infrastructure to accommodate and support the neighboring Aviation Compound project. It was on 19 October 2011, over seven months after ECCI originally priced the modification, and over three months after the cut-off date for the items addressed in the 65% Design Delay modification, when the “Utility Consolidation” or “Site Synchronization” modification was finally negotiated and issued. While the construction cost impacts were addressed by Modification P0004, the associated delay and delay costs were not addressed . . . . A line item summary of the delays related to design, construction submittals, and other over-reaching actions from the Government is provided in Attachment A.

(R4, tab 72 at 12) ECCI also identified the basis of its claim of alleged delays from alleged government directives to add work or to change contract requirements, consisting of (1) directives to add and change communications system; (2) government delay in HVAC design and construction submittal delay and direction to provide changed HVAC equipment; (3) government delay in approval of fire protection design and construction submittals; (4) changing direction regarding design and provision of Uninterruptible Power Supply (UPS); (5) unilateral kennel modification; (6) HVAC start up and commissioning technical expert banned from Camp Pratt; (7) electrical and fire alarm stop work order; and (8) dedicated communications rooms electrical panels (R4, tab 72

2 at 25-51). In addition, ECCI summarized the basis of its claim for alleged delays associated with directed security changes:

The Government imposed direct and significant changes to the security requirements of this contract, made countless revisions to their written policies that were not communicated to ECCI, and imposed numerous and ever-changing unpublished revisions, interpretations and additional requirements to those policies.

(R4, tab 72 at 58) Finally, the submission to the contracting officer includes a spreadsheet entitled Estimate Detail Report; that series of monthly project cost data does not identify the specific rates that apply to specific sub-claims (R4, tab 72 at 273-95).

Regarding the security requirements issue, on January 24, 2019, in ECC Int’l Constructors, LLC, ASBCA No. 59138 et al., 19-1 BCA ¶ 37,252 at 181,315, aff’d, 817 Fed. App’x 952 (Fed. Cir. 2020) (unpublished opinion), we entered summary judgment in the government’s favor, holding that, when the International Security Assistance Force (which is not an agency of the United States Government) encompassed the contract work site within its base security fence, and enforced its own base security procedures at the contract work site, there was no breach of a contract warranty, and no constructive change to the contract, that might have entitled ECCI to recovery from the government. Familiarity with that opinion is assumed. Because that decision, affirmed on appeal, is final, see generally Orlando Helicopter Airways, Inc. v. Widnall, 51 F.3d 258, 261 (Fed. Cir. 1995) (concluding that Board’s decision granting partial summary judgment was final for purposes of appellate review), the claim for the cost of delays arising from a change in security requirements is no longer before us.

Finally, ECCI filed this appeal on September 19, 2014, and the government filed its motion on June 23, 2020, during post-hearing briefing.

DECISION

ECCI has the burden of proving the Board’s jurisdiction by a preponderance of the evidence, including that it presented to the contracting officer a claim, which, in the case of a demand for money, must be stated in a sum certain. See Naseem Al-Oula Co., ASBCA No. 61321 et al., 20-1 BCA ¶ 37,490 at 182,148. Identifying what constitutes a separate claim is important. K-Con Bldg. Sys., Inc. v. United States, 778 F.3d 1000, 1005-06 (Fed. Cir. 2015). The jurisdictional standard must be applied to each claim, not an entire case; jurisdiction exists over those claims that satisfy the requirements of an adequate statement of the amount sought and an adequate statement of the basis for the request. Id. Congress did not intend the word “claim” to mean the whole case between the contractor and the Government, but, rather, that “claim” means each claim under the

3 Contract Disputes Act (41 U.S.C. §§ 7101-7109) for money that is one part of a divisible case. Joseph Morton Co. v. United States, 757 F.2d 1273, 1281 (Fed. Cir. 1985).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
ECC International Constructors, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ecc-international-constructors-llc-asbca-2021.