Teller Environmental Systems, Inc. v. United States

802 F.2d 1385, 33 Cont. Cas. Fed. 74,613, 1986 U.S. App. LEXIS 20362
CourtCourt of Appeals for the Federal Circuit
DecidedOctober 1, 1986
DocketAppeal 85-2676
StatusPublished
Cited by35 cases

This text of 802 F.2d 1385 (Teller Environmental Systems, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Teller Environmental Systems, Inc. v. United States, 802 F.2d 1385, 33 Cont. Cas. Fed. 74,613, 1986 U.S. App. LEXIS 20362 (Fed. Cir. 1986).

Opinion

ARCHER, Circuit Judge.

DECISION

Teller Environmental Systems, Inc. (Teller) appeals from the decision of the Armed Services Board of Contract Appeals (ASBCA or board), ASBCA Docket No. 25550, holding Teller liable to the government for correcting defective repair work performed by Teller. Although the contracting officer determined the amount of damages, the board did not, but instead “remanded” the case to the parties for such determination. We hold that this is not a final decision of the board, as required by 28 U.S.C. § 1295(a)(10) (1982) to give this court appellate jurisdiction, and dismiss without prejudice.

OPINION

I.

On May 30,1974, the United States Navy (Navy) awarded Teller a contract for furnishing and installing equipment for cleansing exhaust gases emitted by engines under test in Navy jet engine facilities located in Norfolk, Virginia, and Jacksonville, Florida. During the course of performance, one of Teller’s workmen accidentally caused a fire that damaged the concrete of one of the exhaust stacks of the Norfolk facility in which Teller’s equipment was being installed. Teller acknowledged responsibility for the accident and carried out repairs to the concrete according to instructions that had been approved by the Navy. On or about August 16, 1976, the Navy *1387 informed Teller that its repair work was acceptable. Teller then completed its contract and requested payment of the unpaid balance of the contract price.

At a later point in time, not specified in the record, “cracking” began to appear in the repaired surface of the exhaust stack. In a letter to Teller dated January 16,1979, the Navy took the position that there were defects in Teller’s performance of the repair work and requested Teller to submit its plan for correcting these defects. When Teller did not agree that it was responsible for the failure of the repairs, the Navy undertook an extensive investigation to determine the causes of the failure. By letter dated December 3, 1979, the Navy informed Teller that it had concluded, based upon reports of consultants, that Teller was responsible for the failure of the repairs and inquired of Teller what action it intended to take to provide adequate repairs. Teller responded on January 9, 1980, rejecting the Navy’s finding that it was responsible for the failure. The Navy then developed specifications for doing the necessary corrective work and awarded a contract to be performed by another contractor. By October 31, 1980, the corrective work was completed under that contract and accepted and paid for by the Navy.

Despite repeated demands for the unpaid balance due under its contract totalling approximately $21,100, the Navy delayed paying Teller. On June 28, 1979, Teller was informed by the Navy that there would be no further payments under the contract until the matter of liability for correcting the defects in the repair of the fire damage was determined. Teller thereafter submitted a formal claim for the unpaid contract price to the contracting officer. The Navy, by way of offset and for affirmative relief, asserted damages against Teller for the defective repair work. On October 3, 1980, the final decision of the contracting officer (CO) allowed the Navy’s offset against Teller’s request for payment of the unpaid contract price and assessed the Navy’s affirmative claim for damages against Teller in the net amount of $80,-660. 1 Teller did not agree with this decision and timely appealed to the board. 2

On March 28, 1985, the board rendered a decision adverse to Teller on the question of liability for the 1980 corrective work. The board determined that there were latent defects in the repair work performed by Teller on account of the fire damage, and held Teller liable under the terms of the contract for the costs incident to the performance of the corrective work. The allowed claim was then remanded to the parties for determination of the amounts due the government.

In its decision, the board stated that there was only a single claim at issue, relating to Teller’s negligent repair work, which involved several items of damages. Noting its de novo jurisdiction, 41 U.S.C. § 605(a) (1982), to review the contracting officer’s decision, the board held that it could consider additional items of damages not presented to the contracting officer so long as the increased damages were within the scope of the claim.

II.

As an initial matter, the government has raised the issue of the court’s jurisdiction to hear this appeal because the decision of the board determined only the liability of Teller, leaving the amount of damages payable to the government to be decided pursuant to the remand to the parties. It contends this is not a final decision of the *1388 board within the meaning of 28 U.S.C. § 1295(a)(10) (1982). 3

Teller notes preliminarily that uncertainty about the finality of the board’s decision, resulting from the board’s practice of bifurcating the issues of entitlement and quantum, presents a procedural dilemma for a contractor. By waiting to appeal until there is an order or decision to pay a specific amount, a contractor runs the risk of being barred by the statutory time limit for appeal if the earlier liability determination constitutes a final decision. On the other hand, filing an appeal after the liability determination can, at most, result in a dismissal of the appeal without prejudice. This reasoning led Teller to file an appeal from the board’s decision of liability.

Teller, nevertheless, believes that the liability determination should be considered a final decision because “there is nothing left before the Board for it to decide ... and nothing in the record ... suggests that the Board has in any sense retained jurisdiction over the matter.” In Teller’s view, the board’s “remand” to the parties makes it clear that the unresolved damages question is not before the board. And thus, Teller contends that the liability decision of the board is separately appealable.

The government counters with arguments that the statutory language clearly requires liability and damages to be treated as part of the same claim, that courts and boards have adopted this treatment, and that judicial economy favors a decision on both questions prior to appeal.

III.

The doctrine of “finality,” under the historic federal rule, has generally allowed appellate review only where a judgment has wholly disposed of a case, adjudicating all rights and ending litigation on the merits. Flanagan v. United States, 465 U.S. 259, 263, 104 S.Ct. 1051, 1054, 79 L.Ed.2d 288 (1984); Firestone Tire & Rubber Co. v. Risjord, 449 U.S. 368, 373, 101 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chu v. Boeing Co.
375 F. App'x 10 (Federal Circuit, 2010)
CNA Corp. v. United States
83 Fed. Cl. 1 (Federal Claims, 2008)
Sec. Of the Air Force v. Lockheed Martin Corp.
277 F. App'x 981 (Federal Circuit, 2008)
Roxco, Ltd. v. United States
77 Fed. Cl. 138 (Federal Claims, 2007)
Tamerlane, Ltd. v. United States
76 Fed. Cl. 512 (Federal Claims, 2007)
Greenhill Reforestation, Inc. v. United States
42 Cont. Cas. Fed. 77,240 (Federal Claims, 1997)
Spraytex, Inc. v. Djs&t and Homax Corporation
96 F.3d 1377 (Federal Circuit, 1996)
Htc Industries, Inc. v. Les Aspin Secretary of Defense
22 F.3d 1103 (Federal Circuit, 1994)
MISS. DEPT. OF HUMAN SERVICES v. Barnett
633 So. 2d 430 (Mississippi Supreme Court, 1993)
Team, Inc. v. Schlette
814 S.W.2d 12 (Missouri Court of Appeals, 1991)
Allied Signal, Inc. v. The United States
941 F.2d 1194 (Federal Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
802 F.2d 1385, 33 Cont. Cas. Fed. 74,613, 1986 U.S. App. LEXIS 20362, Counsel Stack Legal Research, https://law.counselstack.com/opinion/teller-environmental-systems-inc-v-united-states-cafc-1986.