Kit-San-Azusa, a Joint Venture v. The United States, Defendant/cross-Appellant

86 F.3d 1175
Court of Appeals for the Federal Circuit·Decided July 8, 1996·No. 95-5070·Unpublished

Opinion

86 F.3d 1175

40 Cont.Cas.Fed. (CCH) P 76,935

NOTICE: Federal Circuit Local Rule 47.6(b) states that opinions and orders which are designated as not citable as precedent shall not be employed or cited as precedent. This does not preclude assertion of issues of claim preclusion, issue preclusion, judicial estoppel, law of the case or the like based on a decision of the Court rendered in a nonprecedential opinion or order.
KIT-SAN-AZUSA, a joint venture, Plaintiff-Appellant,
v.
The UNITED STATES, Defendant/Cross-Appellant.

Nos. 95-5070, 95-5079.

United States Court of Appeals, Federal Circuit.

May 7, 1996.
Rehearing Denied July 8, 1996.

Before PLAGER, LOURIE and CLEVENGER, Circuit Judges.

CLEVENGER, Circuit Judge.

Kit-San-Azusa (KSA) appeals and the United States (government) cross-appeals the January 24, 1995 decision of the United States Court of Federal Claims, Kit-San-Azusa, J.V. v. United States, 32 Fed. Cl. 647 (1995). We affirm-in-part, modify-in-part, and remand for final disposition.

* In August of 1984, the United States Bureau of Reclamation (USBR) awarded a $15 million contract to KSA to build the third and final portion of an irrigation system. The project consisted of constructing pumping plants and 35 miles of pipeline. This dispute centers around the construction of the Osoyoos Pumping Plant (OPP).

On appeal, KSA challenges three decisions of the Court of Federal Claims: (1) that the Court of Federal Claims had jurisdiction to entertain the government's liquidated damages counterclaim against KSA; (2) that KSA did not establish that USBR's design of the OPP was faulty; and (3) that KSA was entitled to pre-judgment interest only on the difference between its claim and the government's counterclaim. The government cross-appeals the finding that KSA established that a differing site condition occurred at the OPP.

II

Findings of fact made by the Court of Federal Claims are reviewed under a clearly erroneous standard. Whitney Benefits, Inc. v. United States, 926 F.2d 1169, 1171 (Fed.Cir.), cert. denied, 502 U.S. 952 (1991). Legal conclusions of the Court of Federal Claims are reviewed de novo. Dehne v. United States, 970 F.2d 890, 892 (Fed.Cir.1992). We have jurisdiction under 28 U.S.C. § 1295(a)(3) (1994).

III

Because one of KSA's allegations involves the scope of the Court of Federal Claims' jurisdiction, we address that issue first. KSA argues that the Court of Federal Claims should not have allowed the government to litigate its liquidated damages counterclaim because the government allegedly failed to comply with the jurisdictional prerequisites of the Contract Disputes Act of 1978(CDA). The CDA provides in relevant part that:

All claims by a contractor against the government relating to a contract shall be in writing and shall be submitted to the contracting officer for a decision. All claims by the government against a contractor relating to a contract shall be the subject of a decision by the contracting officer.... The contracting officer shall issue his decisions in writing, and shall mail or otherwise furnish a copy of the decision to the contractor. The decision shall state the reasons for the decision reached, and shall inform the contractor of his rights as provided in this chapter.

41 U.S.C. § 605(a) (1994). Although the CDA does not specifically define "claim," the Federal Acquisitions Regulations define a "claim" as: "a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to the contract." 48 C.F.R. § 33.201 (1994).

KSA argues that the contracting officer (CO) never issued a final decision on USBR's assessment of liquidated damages against KSA for late performance. Since a final decision by the CO for a government claim is a prerequisite for the government to litigate its claim in the Court of Federal Claims, see Sharman Co. v. United States, 2 F.3d 1564, 1568-69 (Fed.Cir.1993), KSA asserts that the Court of Federal Claims lacked jurisdiction to entertain the government's liquidated damages claim. While we agree with KSA that the CO never issued a written final decision under the CDA on the government's claim, this deficiency does not preclude the government from litigating its liquidated damages counterclaim in the Court of Federal Claims. This exception to the rule is stated in Placeway Construction Corp. v. United States, 920 F.2d 903 (Fed.Cir.1990), a precedent which governs the jurisdictional question in this case.

In Placeway, the contractor Placeway entered into a contract with the United States Coast Guard to construct residential housing. After construction was completed, Placeway submitted a voucher on January 21, 1985 for the contract's unpaid balance of $297,057.12 plus compensation for various unforeseen expenses. On September 4, 1986, the CO denied Placeway's request to release the unpaid balance because Placeway had failed to complete the contract in a timely manner. In essence, the government set off its delay damages claim against the unpaid balance claimed by Placeway because Placeway's alleged delays exposed the government to liability to other contractors who might later submit delay claims against the government. Placeway then sued on its CDA claim in the Court of Federal Claims. In relevant part, the Court of Federal Claims held that because the CO failed to assert a sum certain of delay damages against Placeway, the CO had not issued a final decision necessary to invoke Court of Federal Claims' jurisdiction for review of the government's assessment of such damages. See Placeway Constr. Corp. v. United States, 18 Cl.Ct. 159, 164-65 (1989), aff'd-in-part and vacated-in-part, 920 F.2d 903 (Fed.Cir.1990).

Free access — add to your briefcase to read the full text and ask questions with AI

Kit-San-Azusa, a Joint Venture v. The United States, Defendant/cross-Appellant, 86 F.3d 1175 (Fed. Cir. 1996).

86 F.3d 1175 (Kit-San-Azusa, a Joint Venture v. The United States, Defendant/cross-Appellant) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Teller Environmental Systems, Inc. v. United States
802 F.2d 1385 (Federal Circuit, 1986)
Stuyvesant Dredging Company v. The United States
834 F.2d 1576 (Federal Circuit, 1987)
Placeway Construction Corporation v. The United States
920 F.2d 903 (Federal Circuit, 1990)
Denis E. Dehne v. The United States
970 F.2d 890 (Federal Circuit, 1992)
The Sharman Company, Inc. v. United States
2 F.3d 1564 (Federal Circuit, 1993)
Kit-San-Azusa J.V. v. United States
40 Cont. Cas. Fed. 76,732 (Federal Claims, 1995)
Placeway Construction Corp. v. United States
35 Cont. Cas. Fed. 75,709 (Court of Claims, 1989)