Kit-San-Azusa J.V. v. United States

40 Cont. Cas. Fed. 76,732, 32 Fed. Cl. 647, 1995 U.S. Claims LEXIS 14, 1995 WL 26200
CourtUnited States Court of Federal Claims
DecidedJanuary 24, 1995
DocketNo. 91-874C
StatusPublished
Cited by13 cases

This text of 40 Cont. Cas. Fed. 76,732 (Kit-San-Azusa J.V. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kit-San-Azusa J.V. v. United States, 40 Cont. Cas. Fed. 76,732, 32 Fed. Cl. 647, 1995 U.S. Claims LEXIS 14, 1995 WL 26200 (uscfc 1995).

Opinion

OPINION

BRUGGINK, Judge.

Trial in this contract action was held in Spokane, Washington between March 7 and March 18,1994. On April 28,1994, the court entered an order on liability. It specifically reserved most damage issues for further briefing and argument, although the record on damages was closed. In an unpublished opinion filed November 11, 1994, the court ruled on what it understood to be the outstanding damage issues and directed the parties to attempt to agree on a calculation of the precise amount of the judgment necessary to effectuate the opinion. The parties were unable to reach complete agreement and the remaining issues were briefed and argued. For reasons included in this comprehensive opinion, the court adopts plaintiffs calculation of damage as set forth in its January 11, 1995, status report. This opinion is conclusive of all issues as to both liability and damage. To the extent there is any material inconsistency between this opinion and the order of April 28 or the opinion of November 10, this opinion controls.

Kit San Azusa Joint Venture (“KSA”) organized its claims against the Bureau of Reclamation into three general sections: the [651]*651Osoyoos Pumping Plant (“OPP”) work; the West Osoyoos Tank; and the pipeline loss of efficiency claim. Claims relating to the OPP work, in turn, were divided into Phase I and Phase II. This opinion consists of three parts. Part I deals with liability issues. With respect to those items as to which liability is found against the Government, specific damage issues are resolved in the same discussion. Recoveries allowed are subject, however, to resolution of damage issues common to all recoveries, which are resolved in Part II. Part III resolves remaining matters.

I. Liability

A. OPP

1. Differing site condition claim (1-1, II-l, II-2)

Several of the OPP claims hinge on whether the soils encountered constituted a differing site condition. KSA contends that the amount of cobble and boulder it encountered could not have been anticipated from the borings and specifications.

The specifications indicate that much of the building site is composed of Quaternary Glacial Outwash (“Qw”). Paragraph 1.3.13 of the specifications defines Qw to be “generally composed of a heterogenous mixture of silt, sand, gravel, cobbles, and boulders.” At sub-paragraph (6), the specific site geology is described as composed of fill and slope wash overlaying fluviolacustrine deposits, which, in turn, overlay Qw deposits., Fluviolacustrine (“Qf’) is defined as “Undivided lake deposits (silt, sand, or clay) and interbedded shoreline accumulations of sand, gravel, and cobbles.”

The Bureau took a substantial number of soil borings at the site. They are referred to in the specifications at the same subpara-graph. There the contractor is informed that “glacial outwash ... was encountered at the site in all drill holes and consists of a heterogenous mixture of silt, sand, gravel, cobbles and boulders.”

The drilling notes bear out this description. The drillers indicate boulder in three of the five sets of notes available. When those notes were translated into the drilling logs furnished to the contractor, however, no reference was made to boulders. What did remain is reference in five of the drilling logs to cobble, or “scattered cobble,” as well as other soils.

While the contractor cannot ignore the site description, it is entitled to place greater reliance on boring logs if they are numerous and well spaced, as these were. The specifications’ reference to boulder, even at the site-specific level, was due to the general classification type of the soil. The Government places too much emphasis on the general classification of the soil and not enough on what was specifically found, at least insofar as what was shown the contractor in the boring logs. That there were, in a technical sense, boulders in the ground at the site is apparent from the results of excavation at Phase II. Rock of sufficient size to qualify as boulders was definitely present. We will never see what it was that caused problems at Phase I, but the court finds it must have been primarily boulder. This is apparent from the difficulty at several places in both Phase I and Phase II, as well as a few instances of complete refusal, and the condition of the ends of the piles when removed.

The court concludes that to the extent there was boulder, and that the boulders interfered with construction, KSA encountered a differing site condition. To hold to the contrary means that a contractor has to assume from the possibility of boulder in a general type of geologic stratum, that boulder could be encountered at any point, despite the lack of indications in the boring logs. Such an assumption would be nearly impossible to factor into a bid. Richard Galster, a private consulting engineering geologist, testified for the Government that one cannot extrapolate more than a foot from a boring log. Under that approach, the site could have had no boulders, or, according to the Government, it could be virtually solid boulder. Would there be no differing site condition so long as there was no boulder within a few feet of any of the boring holes? Clearly at some point the degree of difficulty due to boulder becomes a differing site condition. That point was reached here.

The question of cobble is admittedly different, because cobble did show up in [652]*652some of the boring holes. There was testimony that nested cobble could result in problems similar to those caused by boulders. However, there was also testimony, which the court accepts, that, unless the cobble is closely packed, a vibrating hammer will be able to cause the sheet pile to penetrate. Moreover, the contract drawings and specifications called for use of sheet pile to create a coffer dam. This is a warranty of sorts that sheet pile may be driven without use of extraordinary effort, despite the presence of some cobble.

That plaintiff did in fact encounter substantial difficulties at various points in driving sheet pile is established. It tried extraordinary means to install sheets and to install wells during both Phase I and Phase II. The court concludes that the presence of either boulder or cobble sufficient to impede sheet pile driving constituted a differing site condition.

There were other causes for plaintiff’s difficulties in sheet pile driving, however. L.B. Foster, Inc., delivered sheet pile late, delivered the wrong sheets, omitted corner sheets, and delivered sheet pile with concrete and dirt in the grooves, warped sheets, and sheets in singles instead of doubles. All of those errors must have affected the production schedule, and some of them affected the efficiency of installation itself. The court finds that ten percent of the additional effort plaintiff claims for sheet pile driving was attributable to other causes for which the Government is not liable. KSA proved additional sheet pile costs in the amount of $40,-782.61. Less ten percent, it is entitled to recover $36,704.35 for this item, adjusted by rulings in Part II.

The Government argues, however, that additional deductions should be made for swing shifts and weekend work. Moreover, the Government argues, in light of testimony by Richard Walker, KSA’s project manager, that KSA never suffered a 100 percent loss of production, KSA’s damages for May 9-17, 1985, should be reduced to zero to reflect failure of proof. The court declines to do so.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sikorsky Aircraft Corp. v. United States
102 Fed. Cl. 38 (Federal Claims, 2011)
Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
M. Maropakis Carpentry, Inc. v. United States
84 Fed. Cl. 182 (Federal Claims, 2008)
Southern Comfort Builders, Inc. v. United States
67 Fed. Cl. 124 (Federal Claims, 2005)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
Energy Capital Corp. v. United States
47 Fed. Cl. 382 (Federal Claims, 2000)
Hamilton Securities Advisory Services, Inc. v. United States
43 Cont. Cas. Fed. 77,462 (Federal Claims, 1999)
Greenhill Reforestation, Inc. v. United States
42 Cont. Cas. Fed. 77,240 (Federal Claims, 1997)
Blinderman Construction Co. v. United States
42 Cont. Cas. Fed. 77,210 (Federal Claims, 1997)
Volmar Construction, Inc. v. United States
41 Cont. Cas. Fed. 77,010 (Federal Claims, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
40 Cont. Cas. Fed. 76,732, 32 Fed. Cl. 647, 1995 U.S. Claims LEXIS 14, 1995 WL 26200, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kit-san-azusa-jv-v-united-states-uscfc-1995.