Greenhill Reforestation, Inc. v. United States

42 Cont. Cas. Fed. 77,240, 39 Fed. Cl. 683, 1997 U.S. Claims LEXIS 295, 1997 WL 780919
CourtUnited States Court of Federal Claims
DecidedDecember 19, 1997
DocketNo. 95-802C
StatusPublished
Cited by5 cases

This text of 42 Cont. Cas. Fed. 77,240 (Greenhill Reforestation, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greenhill Reforestation, Inc. v. United States, 42 Cont. Cas. Fed. 77,240, 39 Fed. Cl. 683, 1997 U.S. Claims LEXIS 295, 1997 WL 780919 (uscfc 1997).

Opinion

OPINION

BRUGGINK, Judge.

Pending in this contract action is the Government’s motion to dismiss under RCFC 12(b)(1) for lack of subject-matter jurisdiction. The plaintiff proceeds under the Contract Disputes Act, 41 U.S.C. §§ 601-613 (1994) (CDA). The Government contends that the CDA has not been invoked properly because the Government did not issue a final decision on a claim within the meaning of the act and because the contractor did not properly certify its own claim. The matter is fully briefed, and oral argument is deemed unnecessary. For the following reasons, defendant’s motion is denied.

BACKGROUND1

Plaintiff, Greenhill Reforestation, entered into two contracts with the U.S. Forest Service. On March 18, 1994, Greenhill and the Forest Service entered into a contract to hand plant trees in areas within the Wallace Ranger District in Idaho (the ‘Wallace” contract). Four days later the two parties signed a similar contract for planting in the Avery Ranger District in Idaho (the “Avery” contract). Both contracts were for a base year (1994), with the possibility of two option years. Greenhill’s work on both contracts was accepted after the 1994 planting season, and it was paid $217,105.90 for the Wallace contract and $109,771.52 for the Avery contract. The Forest Service exercised the option to extend to the 1995 season as to both contracts.

With respect to the work on the Wallace contract for 1995, Greenhill alleges that its work was accepted after Forest Service inspection and that it was entitled to payment in the amount of $145,103.80, broken up into three pay estimates. Greenhill was paid on its first estimate of $54,328.15, but the second and third pay estimates in the amounts of $80,839.50 and $9,885.75 were never paid.2

As to the Avery contract work, meanwhile, Greenhill alleges that it completed its work, had the work inspected and accepted, and was entitled to payment of $27,103.51. It was never paid this amount. Consequently, Greenhill contends that it is still owed $90,-725.25 on the Wallace contract and $27,103.51 on the Avery contract.

[685]*685On September 19, 1995, James Luzzi, Vice President of Greenhill, wrote the U.S. Department of Agriculture and the Contracting Officer (CO), reciting, among other things, the following:

This represents a total of $117,828.76 being currently withheld from our company. We have fully fulfilled all of our contractual obligations on both of these contracts.... Please understand, the withholding of this much money is terribly damaging to our cash flow and is a threat to the continued ability of this company to continue in business. It may be a breach of these contracts, and may cause us to be unable to complete performance on other contracts. We have been too busy trying to just keep the bills paid and the company operating to have time to deal with these issues. We desperately need to be informed (1) what is the reason for withholding these payments, and (2) how soon can we expect to receive payment of these funds?

(Def.’s Mot. to Dismiss, app., at 1.)

Richard Simundson, the CO, wrote back on October 13, 1995, stating that the Forest Service had withheld the monies because “walk-through inspections [on the Wallace contract work] ... indicated that the 1995 planting quality was far below acceptable standards on all six units which were inspected. Additional inspection data was needed to confirm or refute the findings of this sample.” (Id. at 2.) Citing the Inspection for Services clause, see 48 C.F.R. § 52.246-4, he notified Greenhill that the Wallace monies were being withheld in the event the contract price was reduced. (See id.) “In addition to this withholding an offset was placed against the Avery Ranger District funds as grounded in the common law right ... of every creditor to apply the monies of his debtor in his hands to extinguishment of the amounts due him from the contractor.” (Id.) He concluded that “[u]ntil such time as our investigation is completed, I am withholding the amounts $90,725.25 and $27,103.51---- Consequently, the investigation of this matter, continues as it appears there are many unanswered questions. Upon completion of this investigation a determination will be made as to disposition of funds.” (Id.)

Greenhill concedes that it did not submit a certified claim on any of the contract payments before filing this complaint.3 The complaint does not recite what action, if any, the CO took after the investigation and determination projected in the October 13 letter.

DISCUSSION

The requirement in the CDA that claims “shall be in writing and submitted to the contracting officer for decision,” 41 U.S.C. § 605(a) (1994), has been construed as a jurisdictional prerequisite to proceeding in this court. See W.M. Schlosser Co. v. United States, 705 F.2d 1336, 1338-39 (Fed.Cir. 1983). In addition, although it is no longer a jurisdictional predicate, claims for over $100,-000 must be certified. See 41 U.S.C. § 605(c) (1994). Contractors do not have to file a claim, however, if what they are challenging in court is a government CDA claim. See 41 U.S.C. §§ 605(a), 609(a). The Government contends that there is no jurisdiction in the court to hear the pending complaint because there was neither a contractor claim nor a government claim to appeal.

Plaintiff offers two alternative theories in an effort to persuade the court that it can hear the complaint. The first is that the CO’s withholding of payment on Greenhill’s invoices constituted a government claim on which it can proceed here. Second, plaintiff contends that it submitted a valid CDA claim of its own to the CO prior to filing of this action and that the amounts claimed were below the threshold amount requiring certification.

A. Assertion of a Government Claim

The CDA dictates that claims by the Government against a contractor shall be the subject of a written decision by the CO and shall inform the contractor of its appeal [686]*686rights.4 See 41 U.S.C. § 605 (1994); 48 C.F.R. § 33.211 (1994). The regulations address the need for a final decision in the event the agency seeks money from the contractor:

For unilateral debt determinations, the contracting officer shall issue a decision as required by the clause at 52.2331-1, Disputes. Such decision shall include a demand for payment (see 33.211(a)(4)(vi)). No demand for payment under 32.610 shall be issued prior to a contracting officer’s final decision. A copy of the final decision shall be sent to the appropriate finance office.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

K-Con Building Systems, Inc. v. the United States 0
114 Fed. Cl. 595 (Federal Claims, 2014)
M. Maropakis Carpentry, Inc. v. United States
84 Fed. Cl. 182 (Federal Claims, 2008)
Kenney Orthopedic, LLC v. United States
83 Fed. Cl. 35 (Federal Claims, 2008)
NCLN20, Inc. v. United States
82 Fed. Cl. 103 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
42 Cont. Cas. Fed. 77,240, 39 Fed. Cl. 683, 1997 U.S. Claims LEXIS 295, 1997 WL 780919, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greenhill-reforestation-inc-v-united-states-uscfc-1997.